CN204203470U - A kind of Channel Construction palm aided management system - Google Patents

A kind of Channel Construction palm aided management system Download PDF

Info

Publication number
CN204203470U
CN204203470U CN201420740890.5U CN201420740890U CN204203470U CN 204203470 U CN204203470 U CN 204203470U CN 201420740890 U CN201420740890 U CN 201420740890U CN 204203470 U CN204203470 U CN 204203470U
Authority
CN
China
Prior art keywords
channel construction
interface
circuit board
control circuit
communicator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201420740890.5U
Other languages
Chinese (zh)
Inventor
卢瀚清
向勇
李文勇
邓海
陈向进
梁世雄
石方梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Yuan Chang Bridges In Highway Engineering Co Ltd
Original Assignee
Guangxi Yuan Chang Bridges In Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi Yuan Chang Bridges In Highway Engineering Co Ltd filed Critical Guangxi Yuan Chang Bridges In Highway Engineering Co Ltd
Priority to CN201420740890.5U priority Critical patent/CN204203470U/en
Application granted granted Critical
Publication of CN204203470U publication Critical patent/CN204203470U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Position Fixing By Use Of Radio Waves (AREA)

Abstract

The utility model discloses a kind of Channel Construction palm aided management system, comprises hand-held device terminal and Channel Construction supervising device.Described hand-held device terminal is by 3G communicator I and remote server wireless connections, for managing Channel Construction and carrying out informationalized operation, and current position coordinates can be obtained by self GPS locating device, by the coordinate of comparison Channel Construction, may be used for the searching that navigation mark is thrown mark operation and lost navigation mark.Described Channel Construction supervising device by 3G communicator II and remote server wireless connections, can monitor the position of Channel Construction, duty, can situation around perception facility.Described hand-held device terminal can carry out wireless LAN communication by the 2.4G radio communication II of 2.4G radio communication I and Channel Construction supervising device, exchanges data.This system architecture is simple, reasonable in design, and the Added Management to Channel Construction when facilitating field work, is beneficial to site inspection and the maintenance work of navigation channel patrolman, increases work efficiency.

Description

A kind of Channel Construction palm aided management system
Technical field
The utility model relates to electronic applications, has been specifically related to the Channel Construction palm aided management system of a kind of communication of the utilized 3G based on gps system and 2.4G wireless LAN communication; It is mainly used in auxiliary cruiseway, cruise and facilities management in the navigation channel in seashore navigation channel.
Background technology
Navigation channel is the important public welfare traffic infrastructure of country, and strengthening sea-route management and maintenance is realize that water-borne transport is unimpeded, efficient, the important guarantee of safety, green.The time of more than ten years in past, national navigation channel cause achieves tremendous development, and sea-route management and maintenance achieve noticeable achievement, managerial ability obviously promotes, and Channel Condition obviously improves, and maintenance level significantly improves, ability of public service obviously strengthens, and facilitates water transport and socio-economic development effectively.2010, national cruiseway cruising range 12.42 ten thousand kilometers, maintenance mileage 10.22 ten thousand kilometers, coastal waterway maintenance mileage more than 10,000 kilometer, bidding more than 8000; The equipments such as the special navigation mark surveying vessel of navigation channel maintenance, large-scale dredging vessel and multi-beam measuring system come into operation successively, and maintenance ability in navigation channel significantly promotes; New technology, new material, the new equipments such as electronic channel chart, Pharos Remote Sensing and Control System, solar integration navigation light, synchronous flashing technology, differential GPS, AIS are applied in the maintenance of navigation channel, the maintenance of some importance navigation channel achieves informationization, digitizing, and navigation channel maintenance scientific and technological content improves constantly.
But existing management tool is all that Based PC end equipment has come, the data that cruise in navigation channel and facility maintenance manages are all on-the-spot first data collections, hold equipment input system again after getting back to office from PC.There is many deficiencies in such management, site administrator cannot obtain the latest news of Channel Construction in time and register Information Field such as facility setting, inspection, maintenances, add labour intensity, reduce work efficiency, be unfavorable for the field management of information-based monitor and control facility.
Summary of the invention
The purpose of this utility model is for the deficiencies in the prior art, provides the Channel Construction palm aided management system of a kind of utilized 3G based on gps system communication and 2.4G wireless LAN communication; It is not only conducive to field maintemance and the management of Channel Construction, and can provide information-based support to the navigation channel field management work in various situation.
To achieve these goals, the utility model have employed following technical scheme:
A kind of Channel Construction palm aided management system, comprises hand-held device terminal and Channel Construction supervising device, and described hand-held device terminal is primarily of equipment box I and the control circuit board I and the liquid crystal touch screen formation that are fixedly mounted on equipment box I inside; Described control circuit board I is provided with several wiring draw-in grooves, described wiring draw-in groove is installed respectively master controller I, GPS locating device I, 2.4G radio communication device I and 3G communicator I; Described control circuit board I is also provided with the liquid crystal display control chip be connected with liquid crystal touch screen; Described equipment box I is also provided with gps antenna, 3G communication antenna and 2.4G communication antenna interface I and power interface I; Described gps antenna is connected with GPS locating device I; Described 3G communication antenna is connected with 3G communicator I; Described 2.4G communication antenna interface I is connected with 2.4G radio communication device I; Described power interface I is connected with control circuit board I;
Described Channel Construction supervising device is formed primarily of equipment box II and the control circuit board II being fixedly mounted on equipment box II inside; Described control circuit board II is provided with several wiring draw-in grooves, described wiring draw-in groove is installed respectively master controller II, 2.4G radio communication device II, 3G communicator II and GPS locating device II; Described equipment box II is also provided with 2.4G communication antenna interface II, 3G communication antenna interface, gps antenna interface, serial line interface II and power interface II; Described gps antenna interface, 3G communication antenna interface and 2.4G communication antenna interface II are connected with 2.4G radio communication device II with GPS locating device II, 3G communicator II respectively; Described serial line interface is connected with master controller II; Described power interface II is connected with control circuit board II.
Described hand-held device terminal, by 3G communicator I and remote server wireless connections, realizes exchanges data; Described Channel Construction supervising device, by 3G communicator II and remote server wireless connections, realizes exchanges data; Described hand-held device terminal can carry out wireless LAN communication by the 2.4G radio communication device II of 2.4G radio communication device I and Channel Construction supervising device, exchanges data.
Further illustrate of the present utility model, the control circuit board I of described hand-held device terminal is also provided with reset circuit and operation control key; The control circuit board II of Channel Construction supervising device is provided with reset circuit and operation control key.
Further illustrate of the present utility model, described power interface I, serial line interface and power interface II adopt water proof type aviation plug respectively.
Hand-held device terminal is provided with 3G communicator I, and carries out radio communication by it and remote server, for managing Channel Construction and carrying out informationalized operation;
Navigation channel related facility is installed Channel Construction supervising device, because Channel Construction supervising device is provided with 3G communicator II and GPS locating device II, by it and remote server wireless connections, the position of Channel Construction, duty can be monitored, and can situation around perception facility;
Hand-held device terminal can obtain current position coordinates by self GPS locating device I, by the coordinate of comparison Channel Construction, may be used for the searching that navigation mark is thrown mark operation and lost navigation mark.
When 3G network is obstructed, because hand-held device terminal and Channel Construction supervising device are separately installed with 2.4G radio communication device I and 2.4G radio communication device II, therefore hand-held device terminal can be communicated with Channel Construction supervising device by 2.4G WLAN (wireless local area network), mutual perception, interaction data.
Compared with prior art, the beneficial effect that has of the utility model:
1. the utility model achieves the information system management in the site work of Channel Construction, maintenance and field, convenient.
2. the utility model adopts 3G communication and 2.4G wireless LAN communication two kinds of patterns to manage Channel Construction, adds the reliability of communication, safer.
3, the utility model uses waterproof case, antidetonation shatter-resistant, is applicable to various outdoor environment and uses.
Accompanying drawing explanation
Fig. 1 is the structural representation of the utility model hand-held device terminal;
Fig. 2 is the structural representation of the utility model Channel Construction supervising device;
Fig. 3 is the functional schematic of the utility model hand-held device terminal;
Fig. 4 is the functional schematic of the utility model Channel Construction supervising device;
In figure: 1-equipment box I, 2-control circuit board I, 3-liquid crystal touch screen, 4-master controller I, 5-GPS locating device I, 6-gps antenna, 7-2.4G radio communication device I, 8-2.4G communication antenna interface I, 9-power interface I, 10-operation control key I, 11-3G communicator I, 12-3G communication antenna, 13-liquid crystal display control chip, 14-equipment box II, 15-control circuit board II, 16-master controller II, 17-2.4G radio communication device II, 18-2.4G communication antenna interface II, 19-3G communicator II, 20-3G communication antenna interface, 21-GPS locating device II, 22-GPS antennal interface, 23-operation control key II, 24-serial line interface II, 25-power interface II.
Embodiment
Below in conjunction with drawings and Examples, the utility model is further illustrated, but protection domain of the present utility model is not only confined to following specific embodiment.
Embodiment:
As shown in Figure 1-2, a kind of Channel Construction palm aided management system, comprise hand-held device terminal and Channel Construction supervising device, described hand-held device terminal is formed primarily of equipment box I1 and the control circuit board I2 and liquid crystal touch screen 3 being fixedly mounted on equipment box I1 inside; Described control circuit board I2 is provided with several wiring draw-in grooves, described wiring draw-in groove is installed respectively master controller I4, GPS locating device I5,2.4G radio communication device I7 and 3G communicator I11; Described control circuit board I2 is also provided with the liquid crystal display control chip 13 be connected with liquid crystal touch screen 3; Described equipment box I1 is also provided with gps antenna 6,3G communication antenna 12 and 2.4G communication antenna interface I8 and power interface I9; Described gps antenna 6 is connected with GPS locating device I5; Described 3G communication antenna 12 is connected with 3G communicator I11; Described 2.4G communication antenna interface I8 is connected with 2.4G radio communication device I7; Described power interface I9 is connected with control circuit board I2;
Described Channel Construction supervising device is formed primarily of equipment box II14 and the control circuit board II15 being fixedly mounted on equipment box II14 inside; Described control circuit board II15 is provided with several wiring draw-in grooves, described wiring draw-in groove is installed respectively master controller II16,2.4G radio communication device II17,3G communicator II19 and GPS locating device II21; Described equipment box II14 is also provided with 2.4G communication antenna interface II18,3G communication antenna interface 20, gps antenna interface 22), serial line interface II24) and power interface II25; Described gps antenna interface 22,3G communication antenna interface 20 and 2.4G communication antenna interface II18 are connected with 2.4G radio communication device II17 with GPS locating device II21,3G communicator II19 respectively; Described serial line interface 24 is connected with master controller II16; Described power interface II25 is connected with control circuit board II15.
The control circuit board I2 of described hand-held device terminal is also provided with reset circuit and operation control key 10; The control circuit board II15 of Channel Construction supervising device is provided with reset circuit and operation control key 23.Described power interface I9, serial line interface 24 and power interface II25 adopt water proof type aviation plug respectively.
Hand-held device terminal is provided with 3G communicator I11, and carries out radio communication by it and remote server, for managing Channel Construction and carrying out informationalized operation;
Navigation channel related facility is installed Channel Construction supervising device, because Channel Construction supervising device is provided with 3G communicator II19 and GPS locating device II21, by it and remote server wireless connections, the position of Channel Construction, duty can be monitored, and can situation around perception facility;
Hand-held device terminal can obtain current position coordinates by self GPS locating device I5, by the coordinate of comparison Channel Construction, may be used for the searching that navigation mark is thrown mark operation and lost navigation mark.
When 3G network is obstructed, because hand-held device terminal and Channel Construction supervising device are separately installed with 2.4G radio communication device I7 and 2.4G radio communication device II17, therefore hand-held device terminal can be communicated with Channel Construction supervising device by 2.4G WLAN (wireless local area network), mutual perception, interaction data.
The hand-held device device of the Added Management Channel Construction of the present embodiment, based on GPS positioning system, 3G communication and 2.4G wireless LAN communication is utilized to realize facilitating traffic department and hydraulic department to the real-time monitoring of Channel Construction, be beneficial to site inspection and the maintenance work of navigation channel patrolman, increase work efficiency.

Claims (3)

1. a Channel Construction palm aided management system, comprise hand-held device terminal and Channel Construction supervising device, it is characterized in that: described hand-held device terminal is primarily of equipment box I(1) and be fixedly mounted on equipment box I(1) inner control circuit board I(2) and liquid crystal touch screen (3) formation; Described control circuit board I(2) be provided with several wiring draw-in grooves, described wiring draw-in groove installs master controller I(4 respectively), GPS locating device I(5), 2.4G radio communication device I(7) and 3G communicator I(11); Described control circuit board I(2) on be also provided with the liquid crystal display control chip (13) be connected with liquid crystal touch screen (3); Described equipment box I(1) on be also provided with gps antenna (6), 3G communication antenna (12) and 2.4G communication antenna interface I(8) and power interface I(9); Described gps antenna (6) and GPS locating device I(5) be connected; Described 3G communication antenna (12) and 3G communicator I(11) be connected; Described 2.4G communication antenna interface I(8) with 2.4G radio communication device I(7) be connected; Described power interface I(9) with control circuit board I(2) be connected;
Described Channel Construction supervising device is primarily of equipment box II(14) and be fixedly mounted on equipment box II(14) inner control circuit board II(15) form; Described control circuit board II(15) be provided with several wiring draw-in grooves, described wiring draw-in groove installs master controller II(16 respectively), 2.4G radio communication device II(17), 3G communicator II(19) and GPS locating device II(21); Described equipment box II(14) on be also provided with 2.4G communication antenna interface II(18), 3G communication antenna interface (20), gps antenna interface (22), serial line interface II(24) and power interface II(25); Described gps antenna interface (22), 3G communication antenna interface (20) and 2.4G communication antenna interface II(18) respectively with GPS locating device II(21), 3G communicator II(19) with 2.4G radio communication device II(17) be connected; Described serial line interface (24) and master controller II(16) be connected; Described power interface II(25) with control circuit board II(15) be connected.
2. a kind of Channel Construction palm aided management system according to claim 1, is characterized in that: the control circuit board I(2 of described hand-held device terminal) on be also provided with reset circuit and operation control key (10); The control circuit board II(15 of Channel Construction supervising device) be provided with reset circuit and operation control key (23).
3. a kind of Channel Construction palm aided management system according to claim 1 and 2, is characterized in that: described power interface I(9), serial line interface (24) and power interface II(25) adopt water proof type aviation plug respectively.
CN201420740890.5U 2014-11-28 2014-11-28 A kind of Channel Construction palm aided management system Active CN204203470U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420740890.5U CN204203470U (en) 2014-11-28 2014-11-28 A kind of Channel Construction palm aided management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420740890.5U CN204203470U (en) 2014-11-28 2014-11-28 A kind of Channel Construction palm aided management system

Publications (1)

Publication Number Publication Date
CN204203470U true CN204203470U (en) 2015-03-11

Family

ID=52661415

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420740890.5U Active CN204203470U (en) 2014-11-28 2014-11-28 A kind of Channel Construction palm aided management system

Country Status (1)

Country Link
CN (1) CN204203470U (en)

Similar Documents

Publication Publication Date Title
CN205719067U (en) A kind of underground pipe network integrated monitoring apparatus
CN103699973A (en) Power grid typhoon prevention and disaster relief aid decision making support system based on GIS (Geographic Information System)
CN103680212A (en) Automatic identification and monitoring system for ships in sea area of 110kv submarine cable
CN103150914A (en) Visual intelligent transportation meteorological monitoring and forewarning management system based on Web geographic information system (GIS)
CN104210513A (en) Train approaching remote early warning method and system thereof
CN104950351B (en) The horizontal methods of exhibiting of many meteorological elements compound based on meteorology and system
CN204374177U (en) A kind of transmission line wire insulator contamination real-time monitoring system
CN109270597B (en) Mining security node for strong convection weather early warning
CN104035103B (en) A kind of method utilizing subregion networking to improve navigation mark positioning precision
CN203732989U (en) Transformer station intelligent routing inspection robot having three-dimensional laser scanning function
CN104808260A (en) Power gird radar early warning method based on GIS
CN202420486U (en) Tide gauge with remote communication function
CN204203470U (en) A kind of Channel Construction palm aided management system
CN201946087U (en) Device for avoiding mistaken or failing removal of ground wires
CN102957209A (en) Integrated measurement and control device of intelligent transformer substation
CN204290493U (en) A kind of power distribution automation detection and control terminal with bluetooth maintenance function
CN215734663U (en) Water conservancy wisdom pole station
CN105634074A (en) Electromobile charging pipe without overground box
CN203433340U (en) Shield machine control system based on double industrial personal computers
CN205101040U (en) Personnel in pit positioner based on RFID
CN104240420A (en) Beacon light anti-theft system based on beidou positioning and mobile network and Ethernet communication
CN204064307U (en) A kind of high precision marine navigation device based on the Big Dipper
CN202931033U (en) Integrated measurement and control apparatus for intelligent transformer station
CN204065410U (en) A kind of device utilizing subregion networking to improve navigation mark positioning precision
CN203405679U (en) Synchronous clock system capable of publishing advertisements in public places

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant