CN202931033U - Integrated measurement and control apparatus for intelligent transformer station - Google Patents
Integrated measurement and control apparatus for intelligent transformer station Download PDFInfo
- Publication number
- CN202931033U CN202931033U CN 201220578919 CN201220578919U CN202931033U CN 202931033 U CN202931033 U CN 202931033U CN 201220578919 CN201220578919 CN 201220578919 CN 201220578919 U CN201220578919 U CN 201220578919U CN 202931033 U CN202931033 U CN 202931033U
- Authority
- CN
- China
- Prior art keywords
- module
- communication
- host cpu
- function sub
- cpu module
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000005259 measurement Methods 0.000 title abstract 3
- 238000004891 communication Methods 0.000 claims abstract description 22
- 230000003993 interaction Effects 0.000 claims abstract description 10
- 230000015572 biosynthetic process Effects 0.000 claims description 11
- 238000003786 synthesis reaction Methods 0.000 claims description 11
- 230000001360 synchronised effect Effects 0.000 claims description 6
- 241000272814 Anser sp. Species 0.000 claims description 5
- 238000000034 method Methods 0.000 abstract description 9
- 238000010276 construction Methods 0.000 abstract description 7
- 238000012544 monitoring process Methods 0.000 description 2
- 238000012360 testing method Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000004973 liquid crystal related substance Substances 0.000 description 1
- 230000006855 networking Effects 0.000 description 1
- 239000013307 optical fiber Substances 0.000 description 1
Images
Landscapes
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
The utility model discloses an integrated measurement and control apparatus for an intelligent transformer station, comprising a management main CPU module, a power supply, a man-machine interaction module, a function sub-module, a GPS hardware and a network station control layer, wherein the management main CPU module is connected with the power supply module and the function sub-module respectively through internal buses, the management main CPU module is connected with the man-machine interaction module in a manner of communication through a serial port, the GPS hardware is connected with the management main CPU module in a manner of communication through a network signal line, and the management main CPU module is connected with the power supply module and the function sub-module respectively in a manner of communication through clock synchronization buses. The integrated measurement and control apparatus for an intelligent transformer station, through flexible software and hardware configuration, can satisfy the demands of the process level digital access or traditional cable access mode, and can satisfy the construction demands of brand new intelligent transformer stations and the gradual intelligentized reconstruction demands of old transformer stations.
Description
Technical field
The utility model relates to a kind of intelligent substation synthesis observe and control device.
Background technology
Along with constantly carrying out of intelligent substation construction, there is brand-new intelligent substation to implement, also there is traditional transformer station to carry out intellectualized reconstruction, for existing brand-new intelligent substation construction and the progressively intellectualized reconstruction engineering of always standing, can be summarized as following several Implementation Modes: pattern one: station level is realized digitlization, adopt the IEC61850 standard with wall, bay device is realized interval connection locking by the GOOSE service, process layer devices is legacy equipment, and all signals access measure and control device by cable mode; Pattern two: station level and wall adopt the IEC61850 standard, and the collection of process layer current/voltage adopts unconventional instrument transformer to realize digitlization, access the measure and control device collection by merge cells according to IEC61850-9 or FT3 standard.Other are opened into leaving and are the traditional cable connected mode; Pattern three: station level and wall adopt the IEC61850 standard, after leaving signal and disposing on the spot intelligent terminal or intelligent operation box in-site collecting by traditional primary equipment, passing through layer by layer GOOSE network and interval telemetry communication, and realizing opening into leaving function; Exchange collection and access the measure and control device collection for conventional P T/CT by cable; Pattern four: process layer open into/leave/measure collection, all adopt optical fiber connected mode and wall telemetry communication.
More than four kinds of Implementation Modes all have process layer digitlization access or traditional cable access way problem, thereby cause brand-new intelligent substation construction and the progressively difficulty of intellectualized reconstruction of always standing.
The utility model content
For addressing the above problem, the purpose of this utility model is to provide a kind of intelligent substation synthesis observe and control device, it passes through flexibly software and hardware configuration, satisfy the requirement of process layer digitlization access or traditional cable access way, satisfy brand-new intelligent substation construction and the progressively requirement of intellectualized reconstruction of always standing.
The utility model is the purpose that reaches above-mentioned, and the utility model adopts following technical scheme:
A kind of intelligent substation synthesis observe and control device comprises management host CPU module, power module, human-computer interaction module, function sub-modules, GPS hardware and network station level; Wherein said management host CPU module is connected with power module, function sub-modules communication respectively by internal bus; Management host CPU module is connected with the human-computer interaction module communication by serial line interface; Described GPS hardware is connected with management host CPU module communication by the network signal line; Communication is connected management host CPU module with function sub-modules with power module respectively by the clock synchronous bus.
Described function sub-modules comprises conventional module and digital module, and wherein said conventional module employing intelligent DC module, intelligence developed module, intelligence are opened wherein one or more into module, intelligent AC module; Described digital module adopts intelligent GOOSE/SV module.
Described station level is connected with management host CPU module communication by two 100 m ethernets.
The beneficial effects of the utility model are: the utility model provides a kind of intelligent substation synthesis observe and control device, it passes through flexibly software and hardware configuration, satisfy the requirement of process layer digitlization access or traditional cable access way, satisfy brand-new intelligent substation construction and the progressively requirement of intellectualized reconstruction of always standing.
Description of drawings
Fig. 1 is structural representation of the present utility model.
Embodiment
As shown in Figure 1 and Figure 2, present embodiment provides a kind of intelligent substation synthesis observe and control device, comprises management host CPU module 1, power module 2, human-computer interaction module 3, function sub-modules 4, GPS hardware 7 and network station level 8; Wherein said management host CPU module 1 is connected with power module 2, function sub-modules 4 communications respectively by internal bus 5; Management host CPU module 1 is connected with human-computer interaction module 3 communications by serial line interface; Described GPS hardware 7 is connected with 1 communication of management host CPU module by the network signal line; Management host CPU module 1 is connected communication with power module 2 respectively by clock synchronous bus 6 and is connected with function sub-modules.Described function sub-modules 4 comprises conventional module and digital module, and wherein said conventional module employing intelligent DC module 10, intelligence developed module 11, intelligence are opened wherein one or more into module 12, intelligent AC module 13; Described digital module adopts intelligent GOOSE/SV module 14.Described station level 8 is connected with 1 communication of management host CPU module by two 100 m ethernets.
The utility model is when using the intelligent substation synthesis observe and control device to test, provide working power by 2 pairs of whole testing apparatuss of power module, in power module 2 with a processor of single chip computer, and designing power supply monitoring circuit, but real time monitoring internal work power supply (3.3V/5V/24V) output state.When human-computer interaction module 3 is received extraneous input signal, carry out the communication transmission by 1 pair of function sub-modules of management host CPU 4.Human-computer interaction module 3 adopts the large liquid crystal display output of 320X240 dot patternization, and touch-sensitive display is adopted in input, and I/O is succinctly convenient.When GPS hardware 7 is received external clock synchronous signal, carry out time-controllable by time synchronized bus 6 function sub-modules 4, enable submodule 4 time synchronized.Described station level 8 is connected with 1 communication of management host CPU module by two 100 m ethernets, and two net working methods can externally be provided.
A kind of intelligent substation synthesis observe and control device that present embodiment provides, it passes through flexibly software and hardware configuration, satisfy the requirement of process layer digitlization access or traditional cable access way, satisfy brand-new intelligent substation construction and the progressively requirement of intellectualized reconstruction of always standing.
Claims (3)
1. an intelligent substation synthesis observe and control device is characterized in that: comprise management host CPU module (1), power module (2), human-computer interaction module (3), function sub-modules (4), GPS hardware (7) and network station level (8); Wherein said management host CPU module (1) is connected with power module (2), function sub-modules (4) communication respectively by internal bus (5); Management host CPU module (1) is connected with human-computer interaction module (3) communication by serial line interface; Described GPS hardware (7) is connected with the communication of management host CPU module (1) by the network signal line; Management host CPU module (1) is connected 4 with power module (2) with function sub-modules respectively by clock synchronous bus (6)) communication is connected.
2. a kind of intelligent substation synthesis observe and control device according to claim 1, it is characterized in that: described function sub-modules (4) comprises conventional module and digital module, and wherein said conventional module employing intelligent DC module (10), intelligence developed module (11), intelligence are opened wherein one or more into module (12), intelligent AC module (13); Described digital module adopts intelligent GOOSE/SV module (14).
3. a kind of intelligent substation synthesis observe and control device according to claim 1 is characterized in that: described station level (8) by two 100 m ethernets with manage host CPU module (1) communication and be connected.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220578919 CN202931033U (en) | 2012-11-06 | 2012-11-06 | Integrated measurement and control apparatus for intelligent transformer station |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220578919 CN202931033U (en) | 2012-11-06 | 2012-11-06 | Integrated measurement and control apparatus for intelligent transformer station |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202931033U true CN202931033U (en) | 2013-05-08 |
Family
ID=48220943
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201220578919 Expired - Lifetime CN202931033U (en) | 2012-11-06 | 2012-11-06 | Integrated measurement and control apparatus for intelligent transformer station |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202931033U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102957209A (en) * | 2012-11-06 | 2013-03-06 | 浙江省电力公司 | Integrated measurement and control device of intelligent transformer substation |
CN105553761A (en) * | 2015-12-11 | 2016-05-04 | 国网四川省电力公司电力科学研究院 | IEC61850 conformance testing hardware platform |
-
2012
- 2012-11-06 CN CN 201220578919 patent/CN202931033U/en not_active Expired - Lifetime
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102957209A (en) * | 2012-11-06 | 2013-03-06 | 浙江省电力公司 | Integrated measurement and control device of intelligent transformer substation |
CN105553761A (en) * | 2015-12-11 | 2016-05-04 | 国网四川省电力公司电力科学研究院 | IEC61850 conformance testing hardware platform |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104280710B (en) | General portable satellite power supply and distribution system equivalent device | |
CN203135591U (en) | Micro-grid centralized monitoring system used for photovoltaic building integrated combination | |
CN103944272A (en) | General measuring and control device for transformer substation | |
CN206489484U (en) | A kind of Embedded Hardware Platform client/server layout designs | |
CN102957209A (en) | Integrated measurement and control device of intelligent transformer substation | |
CN104201986A (en) | Photovoltaic power generation and supervisory control integrated device | |
CN1929223A (en) | Integrated automation converting station debugging apparatus | |
CN103529327B (en) | A kind of full station equipment for monitoring power quality and monitoring method being suitable for Intelligent transformer station | |
CN102738903A (en) | Alternating current-direct current integrated power monitoring device used for station | |
CN202931033U (en) | Integrated measurement and control apparatus for intelligent transformer station | |
CN203104110U (en) | Digital circuit protection and monitoring device based on multiprocessor platform | |
CN204089871U (en) | Mine explosion-suppression and intrinsic safety type switch | |
CN204481574U (en) | A kind of high integration intelligent substation secondary device | |
CN204287792U (en) | Be applicable to the numerical model analysis simulation interface system that simulate signal long-distance transmissions is mutual | |
CN103259334A (en) | Three-state integrated measuring and controlling device for transformer substation | |
CN203734380U (en) | Integrated power supply monitoring system based on PLC | |
CN105337411A (en) | Digital power distribution transformer monitoring terminal | |
CN202393811U (en) | On-line monitoring apparatus for lightning arrester for protecting series compensation capacitor | |
CN203660662U (en) | Single-space five-in-one device for intelligent transformer station | |
CN103746450A (en) | Monitoring system of integrated power equipment | |
CN202268901U (en) | Distributed controller for simple communication | |
CN202475023U (en) | Protection measurement and control device for carrying out high-precision measurement on small signals | |
CN202625533U (en) | On-line intelligent management energy-saving feedback device for elevator | |
CN205157660U (en) | Monitoring device | |
CN205920365U (en) | Power switch cabinet intelligent online monitoring controlling means |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CX01 | Expiry of patent term |
Granted publication date: 20130508 |
|
CX01 | Expiry of patent term |