CN204111162U - Vertical hanger rope rope support - Google Patents
Vertical hanger rope rope support Download PDFInfo
- Publication number
- CN204111162U CN204111162U CN201420582056.8U CN201420582056U CN204111162U CN 204111162 U CN204111162 U CN 204111162U CN 201420582056 U CN201420582056 U CN 201420582056U CN 204111162 U CN204111162 U CN 204111162U
- Authority
- CN
- China
- Prior art keywords
- channel
- steel
- section steel
- hawser
- bar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 137
- 239000010959 steel Substances 0.000 claims abstract description 137
- 238000000034 method Methods 0.000 abstract description 12
- 238000010276 construction Methods 0.000 description 8
- 238000010586 diagram Methods 0.000 description 5
- 238000005516 engineering process Methods 0.000 description 4
- 230000002787 reinforcement Effects 0.000 description 4
- 239000000463 material Substances 0.000 description 3
- 210000005056 cell body Anatomy 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000004519 manufacturing process Methods 0.000 description 2
- 230000003247 decreasing effect Effects 0.000 description 1
- 239000013536 elastomeric material Substances 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Landscapes
- Load-Engaging Elements For Cranes (AREA)
Abstract
The purpose of this utility model is deformation of member problem, amount of deflection problems of too in hoisting process.The technical scheme adopted for realizing the utility model object is such, and a kind of vertical hanger rope rope support, is characterized in that: form rope support by the first channel-section steel, the second channel-section steel, steel disc I, steel disc II and latching device.Described rope support is arranged between the first hawser and the second hawser.The upper end of described first hawser and the second hawser is connected to the top of arm.The lower end of described first hawser and the second hawser is separately fixed at 2 points of growing up on component.The tail end of described first channel-section steel connects steel disc I.The tail end of described second channel-section steel connects steel disc II.Described steel disc I dorsad the first channel-section steel side install steel clamp I.Described steel disc II dorsad the second channel-section steel side install steel clamp II.Described second channel-section steel is fastened on the first channel-section steel.Described second channel-section steel and the first channel-section steel are fixed together by latching device.Described steel clamp I is clipped on the first hawser.Described steel clamp II is clipped on the second hawser.
Description
Technical field
The utility model relates to building operation lifting field.
Background technology
Constantly perfect along with Building technology is that industrial premises or public building are all towards the future development of " large area ", " the large scale of construction ".The lifting of the network frame hoisting of large span, the lifting of steel reinforcement cage, built-in fitting all becomes quotidian thing in project in construction.In hoisting process, the elastomeric material of some softnesses easily frees distortion in hoisting process, and even mid-span deflection exceedes code requirement, and make lifting be difficult to realize, though there are now some treatment measures, but its convenience, fiduciary level all remain to be discussed.
The continuous progress of Modern Construction Technology, engineering it is also proposed higher requirement to the precision of installation component, position.Along with the raising of mechanical application technology and continuing to optimize of equipment, the weight of lifting components has not been restriction lifting principal element, along with the lifting of lifting apparatus Lifting Capacity, it is increasing that the volume of component of lifting can do, can reduce the number of times of component assembly like this, actv. ensure that the globality of component.As shown in Figure 2, in hoisting process, because the effect of the external force factor such as gravity, wind-force, easily deformed by the component lifted, amount of deflection is excessive, had a strong impact on the quality of component itself.
Prior art provides some solutions of the above problems, and such as, according to length and the shape of lifting components, the special pad made below it puts object, or gives structure manufacture stretcher.But these schemes have some shortcomings.Particularly:
(1) need the length according to lifting components and shape, the special pad made below it puts object, or gives structure manufacture stretcher.Generally this is used as to pad the object put to be difficult to use on the component of difformity, volume, causes the waste of material.
(2) due to pad below component, to put object more difficult, puts at pad the lifting relating to component in upholder process, easily makes component produce distortion.
(3), after lifting puts in place, laying of component is cumbersome, and prior art does not have to make component put the effective scheme put in place.
(4) when the pad laying component puts thing, the safety of construction operation personnel is difficult to ensure.
Summary of the invention
The purpose of this utility model is deformation of member problem, amount of deflection problems of too in hoisting process.
The technical scheme adopted for realizing the utility model object is such, and a kind of vertical hanger rope rope support, is characterized in that: form rope support by the first channel-section steel, the second channel-section steel, steel disc I, steel disc II and latching device.Described rope support is arranged between the first hawser and the second hawser.The upper end of described first hawser and the second hawser is connected to the top of arm.The lower end of described first hawser and the second hawser is separately fixed at 2 points of growing up on component.
The tail end of described first channel-section steel connects steel disc I.The tail end of described second channel-section steel connects steel disc II.Described steel disc I dorsad the first channel-section steel side install steel clamp I.Described steel disc II dorsad the second channel-section steel side install steel clamp II.
Described second channel-section steel is fastened on the first channel-section steel.Described second channel-section steel and the first channel-section steel are fixed together by latching device.
Described steel clamp I is clipped on the first hawser.Described steel clamp II is clipped on the second hawser.
Further, the both sides of described first channel-section steel have bar-shaped trough I-I and bar-shaped trough I-II.The both sides of described second channel-section steel have bar-shaped trough II-I and bar-shaped trough II-II.
Also comprise two sleeve locking apparatus.Described latching device comprises bolt and fly nut.After wherein the bolt of a sleeve locking apparatus passes from bar-shaped trough I-I and bar-shaped trough II-I, screw in fly nut.After the bolt of an other sleeve locking apparatus passes from bar-shaped trough II-I and bar-shaped trough II-II, screw in fly nut.
Technique effect of the present utility model is mathematical.The support of this hawser in use, eliminates the time making fixing stretcher to component specially, shortens the construction period of lifting, and actv. improves construction economy benefit.Adopt this hawser to support, solve between hawser and lifting components and there is angle problem, effectively reduce the amount of deflection of component, very easy to use, use the different lifting across footpath component, before lifting, just can complete the erection work of hawser support, ensure that the safety of construction.Not only make lifting work convenient, simple and direct, and meet the safety in hoisting process.Some components amount of deflection in hoisting process is excessive, be out of shape an excessive difficult problem is readily solved.
Accompanying drawing explanation
Fig. 1 is using state reference diagram of the present utility model;
Fig. 2 is existing lifting component process schematic;
Fig. 3 is block diagram of the present utility model;
Fig. 4 is the block diagram in the utility model another one direction;
Fig. 5 is the first channel-section steel block diagram;
Fig. 6 is the second channel-section steel block diagram.
In figure: the first channel-section steel 1, bar-shaped trough I-I 101, bar-shaped trough I-II 102, second channel-section steel 2, bar-shaped trough II-I 201, bar-shaped trough II-II 202, steel disc I 3, steel clamp I 301, steel disc II 4, steel clamp II 401, latching device 5, arm 6, first hawser 601, second hawser 602, rope support 7, component 8 of growing up.
Detailed description of the invention
Below in conjunction with drawings and Examples, the utility model is described in further detail, but should not be construed the above-mentioned subject area of the utility model and be only limitted to following embodiment.When not departing from the above-mentioned technological thought of the utility model, according to ordinary skill knowledge and customary means, making various replacement and change, all should be included in protection domain of the present utility model.
Embodiment 1:
A vertical hanger rope rope support, forms rope support 7 by the first channel-section steel 1, second channel-section steel 2, steel disc I 3, steel disc II 4 and latching device 5.
See Fig. 5, described first channel-section steel 1 is faced upward and is put, and its upper end is uncovered, lower end closed.Head end and the tail end of the first channel-section steel 1 are all uncovered.See Fig. 6, described second channel-section steel 2 button is put, and its lower end is uncovered, upper end closed.Head end and the tail end of the second channel-section steel 2 are all uncovered.
Described rope support 7 is arranged between the first hawser 601 and the second hawser 602.See Fig. 1, hang down the first hawser 601 and the second hawser 602 for the top of crane arm 6.Namely the upper end of described first hawser 601 and the second hawser 602 is connected to the top of arm 6.The lower end of described first hawser 601 and the second hawser 602 is separately fixed at 2 points of growing up on component 8.In embodiment, described in component 8 of growing up are cylinder steel reinforcement cages, namely its cylindrical height is the length of component 8 of growing up.The side of steel reinforcement cage has two hooks, and the lower end of described first hawser 601 and the second hawser 602 is separately fixed on these two hooks.
The tail end of described first channel-section steel 1 connects steel disc I 3, and namely the tail end of steel disc I 3 shutoff first channel-section steel 1 is uncovered.The tail end of described second channel-section steel 2 connects steel disc II 4, and namely the tail end of steel disc II 4 shutoff second channel-section steel 2 is uncovered.Described steel disc I 3 dorsad the first channel-section steel 1 side install steel clamp I 301, described steel clamp I 301 is spring clipes, is preferably spring serrated clips, rope can be clipped in the surface of steel disc I 3.Described steel disc II 4 dorsad the second channel-section steel 2 side install steel clamp II 401, described steel clamp II 401 is spring clipes, is preferably spring serrated clips, rope can be clipped in the surface of steel disc II 4.。
The lower end of described second channel-section steel 2 is uncovered be fastened on the upper end of the first channel-section steel 1 uncovered on.Described second channel-section steel 2 and the first channel-section steel 1 are fixed together by latching device 5.When latching device 5 unclamps, the second channel-section steel 2 can slide along the first channel-section steel 1, makes the total length of the second channel-section steel 2 after fastening and the first channel-section steel 1 increase or reduce.
Described steel clamp I 301 is clipped on the first hawser 601.Described steel clamp II 401 is clipped on the second hawser 602.The second channel-section steel 2 and the first channel-section steel 1 is made all to be parallel to horizontal surface.
In the present embodiment, because the hawser in hoisting process and component have certain angle, solve the problem of lifting components Impact direction, reduce its deflection deformation.Solve dangerous problem when operating personnel lays underbed.Save the materials'use problem in order to fixing lifting components.Solve the situation that there is underbed, after lifting puts in place, component is difficult to the problem transferred.Improve the safety in hoisting process, after the length of the combination of the first channel-section steel 1 and the second channel-section steel 2 can regulate, more fixing with fly-headed bolt, so same hawser support can be suitable for the lifting components of multiple different length, different volumes.
Embodiment 2
The present embodiment keystone configuration is with embodiment 1, and further, the both sides of described first channel-section steel 1 have bar-shaped trough I-I 101 and bar-shaped trough I-II 102.The length direction of same first channel-section steel 1 of length direction of described bar-shaped trough I-I 101 and bar-shaped trough I-II 102.The both sides of described second channel-section steel 2 have bar-shaped trough II-I 201 and bar-shaped trough II-II 202.The length direction of same second channel-section steel 2 of length direction of described bar-shaped trough II-I 201 and bar-shaped trough II-II 202.
After the first channel-section steel 1 and the second channel-section steel 2 snap together, bar-shaped trough I-I 101 and bar-shaped trough II-I 201 overlap in the horizontal direction, and bar-shaped trough I-II 102 and bar-shaped trough II-II 202 overlap in the horizontal direction.
The present embodiment also comprises two sleeve locking apparatus 5.Described latching device 5 comprises bolt and fly nut.After wherein the bolt of a sleeve locking apparatus 5 passes from bar-shaped trough I-I 101 and bar-shaped trough II-I 201, screw in fly nut, bolt cap is stayed in the cell body of the second channel-section steel 2.After the bolt of an other sleeve locking apparatus 5 passes from bar-shaped trough II-I 201 and bar-shaped trough II-II 202, screw in fly nut, bolt cap is stayed in the cell body of the first channel-section steel 1.
Unclamp two fly nuts, the first channel-section steel 1 and the second channel-section steel 2 can be free to slide in the horizontal direction, to adjust the overall length of the combination of the first channel-section steel 1 and the second channel-section steel 2.Screw two fly nuts, the first channel-section steel 1 and the second channel-section steel 2 can be locked, the overall length of the combination of the first channel-section steel 1 and the second channel-section steel 2 is fixed.Usually, the overall length of the combination of the first channel-section steel 1 and the second channel-section steel 2 is equal with the distance waiting to lift between two attachment points (can be link up with) of growing up on component 8.Preferably, the overall length of the combination of the first channel-section steel 1 and the second channel-section steel 2 waits to lift 1/3 of component 8 length of growing up, and after the component 8 that makes to grow up is sling by the first hawser 601 and the second hawser 602, the possibility of torsional deflection reduces.
Embodiment 3:
The present embodiment have employed the device described in embodiment 2.Adopt " vertical hanger rope rope support " lifting steel reinforcement cage, trussed steel beam, strip shape embedded part more than 1000 times, the very big lifting amount of deflection decreasing component, effectively saves the material making lifting stretcher, improves the accuracy of lifting, for green construction provides condition.
Claims (2)
1. a vertical hanger rope rope support, is characterized in that: form rope support (7) by the first channel-section steel (1), the second channel-section steel (2), steel disc I (3), steel disc II (4) and latching device (5); Described rope support (7) is arranged between the first hawser (601) and the second hawser (602); The upper end of described first hawser (601) and the second hawser (602) is connected to the top of arm (6); The lower end of described first hawser (601) and the second hawser (602) is separately fixed at 2 points on component of growing up (8);
The tail end of described first channel-section steel (1) connects steel disc I (3); The tail end of described second channel-section steel (2) connects steel disc II (4); Described steel disc I (3) dorsad the first channel-section steel (1) side install steel clamp I (301); Described steel disc II (4) dorsad the second channel-section steel (2) side install steel clamp II (401);
Described second channel-section steel (2) is fastened on the first channel-section steel (1); Described second channel-section steel (2) and the first channel-section steel (1) are fixed together by latching device (5);
Described steel clamp I (301) is clipped on the first hawser (601); Described steel clamp II (401) is clipped on the second hawser (602).
2. vertical hanger rope rope support according to claim 1, is characterized in that: the both sides of described first channel-section steel (1) have bar-shaped trough I-I (101) and bar-shaped trough I-II (102); The both sides of described second channel-section steel (2) have bar-shaped trough II-I (201) and bar-shaped trough II-II (202);
Also comprise two sleeve locking apparatus (5); Described latching device (5) comprises bolt and fly nut; After wherein the bolt of a sleeve locking apparatus (5) passes from bar-shaped trough I-I (101) and bar-shaped trough II-I (201), screw in fly nut; After the bolt of an other sleeve locking apparatus (5) passes from bar-shaped trough II-I (201) and bar-shaped trough II-II (202), screw in fly nut.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420582056.8U CN204111162U (en) | 2014-09-30 | 2014-09-30 | Vertical hanger rope rope support |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420582056.8U CN204111162U (en) | 2014-09-30 | 2014-09-30 | Vertical hanger rope rope support |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204111162U true CN204111162U (en) | 2015-01-21 |
Family
ID=52328499
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420582056.8U Expired - Fee Related CN204111162U (en) | 2014-09-30 | 2014-09-30 | Vertical hanger rope rope support |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204111162U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105217439A (en) * | 2014-09-30 | 2016-01-06 | 重庆大学 | Vertical hanger rope rope support |
-
2014
- 2014-09-30 CN CN201420582056.8U patent/CN204111162U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105217439A (en) * | 2014-09-30 | 2016-01-06 | 重庆大学 | Vertical hanger rope rope support |
CN105217439B (en) * | 2014-09-30 | 2017-06-16 | 重庆大学 | Vertical hanger rope rope support |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204847764U (en) | Prefabricated component production is with hoist and mount frame | |
CN204024016U (en) | A kind of attachment type raise scaffold unidirectional self-lock anti-drop device | |
CN203255914U (en) | Unit-typed curtain wall lifting device | |
CN204111162U (en) | Vertical hanger rope rope support | |
CN213537032U (en) | Special clamp crown block for carbon pre-roasting anode workshop | |
CN204224020U (en) | A kind of buffer of elevator device for installing and adjusting | |
CN104291222A (en) | Rigid protection and crane integration system inside super high-rise building core tube | |
CN206273951U (en) | The hoisting apparatus of attachment type raise scaffold | |
CN201176365Y (en) | Light-duty adjustable hanger | |
CN207030735U (en) | Prefabricated balcony lifts servicing unit | |
CN105217439A (en) | Vertical hanger rope rope support | |
CN207276049U (en) | A kind of gantry crane | |
CN206770795U (en) | A kind of heavy load horizontal pipe pull bar suspension bracket | |
CN206395795U (en) | Hydraulic type cable well lid easy opening device | |
CN204689351U (en) | A kind of H profile steel structural elements suspender | |
CN211034952U (en) | Maintenance hanging bracket for substation equipment | |
CN204199185U (en) | A kind of prestressed stretch-draw support | |
CN209193373U (en) | A kind of heavy type H steel boom hoisting | |
CN208200142U (en) | A kind of architectural electricity equipment construction device | |
CN209242469U (en) | A kind of boat frame hoisting structure | |
CN110316649A (en) | A kind of suspender and hanging method suitable for irregular truss | |
CN106410671B (en) | A kind of device for aiding in changing tube type bus support porcelain vase | |
CN205501820U (en) | Easy bridge beam slab handling frame of adjusting | |
CN104120889B (en) | Tube truss structure integral lifting apparatus | |
CN204897147U (en) | Horizontal panel hoist |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150121 |