CN204000582U - The spacing bearing of the main pier of steel truss arched bridge - Google Patents

The spacing bearing of the main pier of steel truss arched bridge Download PDF

Info

Publication number
CN204000582U
CN204000582U CN201420167314.6U CN201420167314U CN204000582U CN 204000582 U CN204000582 U CN 204000582U CN 201420167314 U CN201420167314 U CN 201420167314U CN 204000582 U CN204000582 U CN 204000582U
Authority
CN
China
Prior art keywords
block
lower support
support plate
upper bracket
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420167314.6U
Other languages
Chinese (zh)
Inventor
罗世东
王新国
曾敏
瞿国钊
任巍峰
夏正春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Survey and Design Group Co Ltd
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN201420167314.6U priority Critical patent/CN204000582U/en
Application granted granted Critical
Publication of CN204000582U publication Critical patent/CN204000582U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses the spacing bearing of the main pier of a kind of steel truss arched bridge, comprise upper bracket plate, lower support plate, between upper bracket plate and lower support plate, be provided with spherical crown, described upper bracket plate and spherical crown are rotationally connected, and it is characterized in that: between described spherical crown and described lower support plate, be slidably connected; Along the glide direction of spherical crown, described lower support plate is provided with dismountable the first block and the second block, described the first block and the second block lay respectively at the opposite face of lower support plate, and described spherical crown and described upper bracket plate can slide between the first block and the second block; Between described the first block and upper bracket plate, be provided with multiple dismountable adjusting cushion blocks.The utility model replaces traditional interim tie-rod system and bears horizontal thrust, while being applied to the construction of steel truss arched bridge rigidity, do not affect navigation, degree of safety is high, easy to operate, reduced difficulty of construction, has saved the cost that channel maintenance, anchoring temporarily system and interim tie-rod drop into.

Description

The spacing bearing of the main pier of steel truss arched bridge
Technical field
The utility model relates to a kind of bridge pad, specifically the spacing bearing of the main pier of steel truss arched bridge.
Background technology
Steel truss arched bridge, after arch rib closes up, before bridge floor rigidity tie-rod closes up, needs to install interim tie-rod, form in advance tied arch system, and pass through the repeatedly interim tie-rod of stretch-draw, and balance impost horizontal thrust, control and the unstressed of rigid tie bar of realizing construction period bridge stress displacement close up.
For avoid too complicated structure and reduce the impact that interim tie-rod is installed bridge deck member as far as possible, interim tie-rod is generally positioned on the some nodes below bridge floor, however, interim tie-rod still can stop the smooth lifting of bridge deck member, affects construction speed; Meanwhile, the interim tie-rod being positioned at below bridge floor has greatly reduced navigational clearance height, and construction period needs expensive channel maintenance expense, requires high bridge site place in waterway classification, even can have influence on the enforcement of bridge scheme; And interim tie-rod need increase anchoring temporarily measure, causes Structural Tectonics complexity, and waste material; Along with the carrying out of construction, also need to be in high-altitude the interim tie-rod of stretch-draw repeatedly, construction control difficulty is large.
The strong point of existing main pier bearing all cannot regulate, and all can not replace interim tie-rod to bear horizontal thrust.
Utility model content
The utility model, for the deficiency of describing in above-mentioned background technology, provides the main pier of a kind of steel truss arched bridge that replaces interim tie-rod to bear horizontal thrust spacing bearing.
The technical solution used in the present invention is: the spacing bearing of the main pier of steel truss arched bridge, comprise upper bracket plate, lower support plate, between upper bracket plate and lower support plate, be provided with spherical crown, described upper bracket plate and spherical crown are rotationally connected, and it is characterized in that: between described spherical crown and described lower support plate, be slidably connected; Along the glide direction of spherical crown, described lower support plate is provided with dismountable the first block and the second block, described the first block and the second block lay respectively at the opposite face of lower support plate, and described spherical crown and described upper bracket plate can slide between the first block and the second block; Between described the first block and upper bracket plate, be provided with multiple dismountable adjusting cushion blocks.
Preferably, described upper bracket plate outside is provided with dismountable gear frame, described gear frame and lower support plate sliding-contact.
Preferably, described lower support plate one side is provided with dismountable lapping plate, described lapping plate and described lower support plate clamping; Described the second block is positioned on lapping plate.
The invention has the beneficial effects as follows: the knotted rope dorsal funciculus system adopting while coordinating bridge construction, the utility model has solved traditional interim tie-rod and has closed up the interim tie-rod of scheme and affect navigational clearance and interim tie-rod anchor measure complex structure and this key technology difficult problem of waste material, can save a large amount of directly engineering cost and channel maintenance expenses, and to greatest extent, reduce the impact of construction on navigation.Be applied to steel truss arched bridge rigidity when construction, do not affect navigation, degree of safety is high, easy to operate, has reduced difficulty of construction, has saved the cost of channel maintenance, anchoring temporarily system and interim tie-rod input.
Brief description of the drawings
Fig. 1 is the cross-sectional schematic of the spacing bearing of the main pier of the present invention
Fig. 2 is the cross-sectional schematic of Fig. 1
Detailed description of the invention
As depicted in figs. 1 and 2, the spacing bearing of main pier, comprises upper bracket plate 1, lower support plate 2, between upper bracket plate 1 and lower support plate 2, is provided with spherical crown 3, and described upper bracket plate 1 is rotationally connected with spherical crown 3; Between described spherical crown 3 and described lower support plate 2, be slidably connected; Along the glide direction of spherical crown 3, described lower support plate 2 is provided with dismountable the first block 4 and the second block 5, described the first block 4 and the second block 5 lay respectively at the opposite face of lower support plate 2, and described spherical crown 3 and described upper bracket plate 1 can slide between the first block 4 and the second block 5; Between described the first block 4 and upper bracket plate 5, be provided with multiple dismountable adjusting cushion blocks 6.In order to prevent that upper bracket plate 1 and spherical crown 3 from departing from, described upper bracket plate 1 outside is provided with dismountable gear frame 7, described gear frame 7 and lower support plate 2 sliding-contacts.Described lower support plate 2 one sides are provided with dismountable lapping plate 8, described lapping plate 8 and described lower support plate 2 clampings; Described the second block 5 is positioned on lapping plate 8.
Utilize the utility model can replace interim tie-rod, adopt the spacing bearing of main pier to substitute the horizontal thrust that the interim tie-rod of tradition bears construction period arch ring.Between the bridge deck installation period after arch rib closes up, do not remove buckle back cable system, to reduce the horizontal thrust of the spacing bearing of main pier.By adjusting the length travel amount of the spacing bearing of main pier, complete the function of interim tie-rod, control and the unstressed of rigid tie bar of realizing construction period bridge stress displacement close up.After rigid tie bar closes up, remove buckle back cable system, finally unload step by step the spacing bearing of main pier, rigid tie bar is stressed, completes system conversion.
After arch rib closes up, during cantilever bridge deck, do not remove knotted rope dorsal funciculus system, continue to use it to share bridge deck deadweight, can greatly reduce impost horizontal thrust, be conducive to pier shaft and basic stress.

Claims (3)

1. the spacing bearing of the main pier of steel truss arched bridge, comprise upper bracket plate, lower support plate, between upper bracket plate and lower support plate, be provided with spherical crown, described upper bracket plate and spherical crown are rotationally connected, and it is characterized in that: between described spherical crown and described lower support plate, be slidably connected; Along the glide direction of spherical crown, described lower support plate is provided with dismountable the first block and the second block, described the first block and the second block lay respectively at the opposite face of lower support plate, and described spherical crown and described upper bracket plate can slide between the first block and the second block; Between described the first block and upper bracket plate, be provided with multiple dismountable adjusting cushion blocks.
2. the spacing bearing of main pier according to claim 1, is characterized in that: described upper bracket plate outside is provided with dismountable gear frame, described gear frame and lower support plate sliding-contact.
3. the spacing bearing of main pier according to claim 1 and 2, is characterized in that: described lower support plate one side is provided with dismountable lapping plate, described lapping plate and described lower support plate clamping; Described the second block is positioned on lapping plate.
CN201420167314.6U 2014-04-04 2014-04-04 The spacing bearing of the main pier of steel truss arched bridge Expired - Lifetime CN204000582U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420167314.6U CN204000582U (en) 2014-04-04 2014-04-04 The spacing bearing of the main pier of steel truss arched bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420167314.6U CN204000582U (en) 2014-04-04 2014-04-04 The spacing bearing of the main pier of steel truss arched bridge

Publications (1)

Publication Number Publication Date
CN204000582U true CN204000582U (en) 2014-12-10

Family

ID=52040608

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420167314.6U Expired - Lifetime CN204000582U (en) 2014-04-04 2014-04-04 The spacing bearing of the main pier of steel truss arched bridge

Country Status (1)

Country Link
CN (1) CN204000582U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104831631A (en) * 2015-04-17 2015-08-12 中交第二航务工程局有限公司 An arch bridge rigid tie rod joining method without temporary stay cables
CN107313359A (en) * 2016-04-27 2017-11-03 成都亚佳工程新技术开发有限公司 One kind is general to exempt from steel bridge Rotary ball hinge system of weighing
CN111576635A (en) * 2020-04-30 2020-08-25 中建五局第三建设有限公司 First-sliding and then-hinging support and connecting method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104831631A (en) * 2015-04-17 2015-08-12 中交第二航务工程局有限公司 An arch bridge rigid tie rod joining method without temporary stay cables
CN104831631B (en) * 2015-04-17 2016-06-08 中交第二航务工程局有限公司 A kind of arch bridge rigid tie bar closure method without interim drag-line
CN107313359A (en) * 2016-04-27 2017-11-03 成都亚佳工程新技术开发有限公司 One kind is general to exempt from steel bridge Rotary ball hinge system of weighing
CN111576635A (en) * 2020-04-30 2020-08-25 中建五局第三建设有限公司 First-sliding and then-hinging support and connecting method

Similar Documents

Publication Publication Date Title
CN103938552B (en) Steel truss arched bridge self-balancing cantilever construction method and the spacing bearing of main pier
CN204000582U (en) The spacing bearing of the main pier of steel truss arched bridge
CN103669226B (en) River-crossing prestressed concrete continuous beam bridge box girder 0# block support construction method
CN103510475B (en) Three main truss steel truss girder simply connected twin spans are without nose girder long distance push construction method
CN103074854A (en) Rear supporting point triangular bracket hanging basket and bridge construction method using same
CN102535348B (en) Method for tensioning stayed cables of hinged tower cable stayed bridge
CN102418315A (en) Construction method for concrete-filled steel tube arched bridge with large low-buckle tower erection bridge width
CN102094389A (en) Separable large-section truss girder hydraulic lifting device
CN105350442A (en) Arching method for stiff skeleton concrete arch bridge
CN106835981B (en) A kind of self-balance type inhaul cable anchorage structure suitable in bridge pier and bridge tower
CN201605523U (en) Suspension cable type floating bridge
CN106758837A (en) A kind of Inclined cable-stayed construction system of combination spandrel column
CN107012797B (en) A kind of construction system that Support Method is combined with stayed knotting method and method
CN104264578A (en) Steel-concrete combining bridge of self-anchored suspension cable-cable-stayed cooperative system
CN106480866A (en) Partial equilibrium hydraulic hoisting ship elevator
CN208981146U (en) Half-through suspension bridge
CN104963292B (en) Construction method of reinforced concrete continuous-span arch bridge or continuous box structure bridge
CN204097983U (en) Tunnel formula water inlet Emergency Gate well construction
CN203174516U (en) Suspension bridge closure segment construction beam segment traction pre-deflection device
CN204919371U (en) Hang water a festival section construction on arched bridge draw sectional shelf -unit device to one side
US2914783A (en) Bridge construction
CN102251477A (en) Traversing construction method for tie bar arch
CN102168492B (en) Deformation control cantilever mounting method for large-diameter upright annular structure
CN204875663U (en) Be adapted to landing stage of oceanic tide
CN201952115U (en) Cantilever longitudinal beam balance mechanism

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20141210