CN203939038U CN201420386447.2U CN201420386447U CN203939038U CN 203939038 U CN203939038 U CN 203939038U CN 201420386447 U CN201420386447 U CN 201420386447U CN 203939038 U CN203939038 U CN 203939038U
Authority
CN
China
Prior art keywords
steel drum
hole
fall
stone
cheat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201420386447.2U
Other languages
Chinese (zh)
Inventor
刘振
孟春柳
王天峰
张宗亮
李鹏程
陈杰
彭福定
袁盛尧
罗杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FOURTH CONSTRUCTION Co Ltd OF YUNNAN ARCHITECTURAL ENGINEERING GROUP
Original Assignee
FOURTH CONSTRUCTION Co Ltd OF YUNNAN ARCHITECTURAL ENGINEERING GROUP
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FOURTH CONSTRUCTION Co Ltd OF YUNNAN ARCHITECTURAL ENGINEERING GROUP filed Critical FOURTH CONSTRUCTION Co Ltd OF YUNNAN ARCHITECTURAL ENGINEERING GROUP
Priority to CN201420386447.2U priority Critical patent/CN203939038U/en
Application granted granted Critical
Publication of CN203939038U publication Critical patent/CN203939038U/en
Anticipated expiration legal-status Critical
Active legal-status Critical Current

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

In a kind of hole, cheat steel drum and fall dewatering installation, comprise the steel drum (1) of column type, described steel drum (1) bottom opening and gate valve (2) is installed in aperture, steel drum (1) outer wall surface welding seal ring (4), dig the hole of dark 800mm at the place of leaking, fill out the centimetre stone (8) that 100mm is thick in the bottom in hole, described dell is connected by french drain with other leakage point, steel drum (1) is put into the hole of filling in a centimeter stone (8), then use a centimeter stone (8) to fill up steel drum (1) bottom surrounding, finally put into the water pump (3) for drawing water in steel drum (1) the inside.The utility model can keep whole raft plate construction stage steel drum all at precipitation, make whole foundation ditch in anhydrous Construction State, advantageous particularly to waterproof construction and other operations, can not cause because of underground water the raft plate phenomenons such as cracking of leaking, when having ensured raft plate concrete pouring quality, allow yet and fall drainage works and become easily and effectively.

Description

In a kind of hole, cheat steel drum and fall dewatering installation
Technical field
The utility model is the device for water seal for deep foundation pit, is specifically in a kind of hole, to cheat steel drum to fall dewatering installation.
Background technology
The engineering of constructing than more rich place at underground water, particularly deep-foundation pit engineering, underground water yield is larger, must take corresponding measures of preventing water to ensure carrying out smoothly of construction in construction.
The method of water seal for deep foundation pit has conventionally: water-stop curtain, well-points dewatering and gutter; But have the deficiencies such as long, complicated operation of duration and cost be higher, water-stop curtain can become very poor or almost there is no effect the stagnant water effect that is gravel layer at construction layer.
Utility model content
The purpose of this utility model is for deficiency of the prior art, provides in a kind of hole, to cheat steel drum and fall dewatering installation.The utility model can keep whole raft plate construction stage steel drum all at precipitation, make whole foundation ditch in anhydrous Construction State, advantageous particularly to waterproof construction and other operations, can not cause because of underground water the raft plate phenomenons such as cracking of leaking, when having ensured raft plate concrete pouring quality, allow yet and fall drainage works and become easily and effectively.
The utility model adopts following technical scheme to be achieved:
In a kind of hole, cheat steel drum and fall dewatering installation, comprise the steel drum (1) of column type, described steel drum (1) bottom opening and gate valve (2) is installed in aperture, steel drum (1) outer wall surface welding seal ring (4), dig the hole of dark 800mm at the place of leaking, fill out the centimetre stone (8) that 100mm is thick in the bottom in hole, described dell is connected by french drain with other leakage point, steel drum (1) is put into the hole of filling in a centimeter stone (8), then use a centimeter stone (8) to fill up steel drum (1) bottom surrounding, finally put into the water pump (3) for drawing water in steel drum (1) the inside.
Described steel drum (1) diameter is that 800mm ~ 1200mm, wall thickness are 5mm, and height is determined by built plank thickness.
Described steel drum (1) welds one seal ring (4) along the every 3000mm of short transverse.
In described french drain, insert a dog stone (6), and cover with plastic sheeting (7).
Described steel drum (1) is placed on upper its top of a centimeter stone (8) and spills raft plate face (9) 50mm, and centimetre stone (8) fills up along steel drum (1) bottom surrounding.
Feature of the present utility model is:
1, water pump is put into steel drum, and hole bed mud sand can not stop up water pump;
2, when raft plate is built, water pump does not stop pumping, and underground water can not impact building of raft plate.
3,, after raft plate has been built, underground water continues to extract out by the water pump in steel drum, can not cause because of underground water raft plate to leak.
4,, after raft plate curing time finishes, can be simply reach the object of sealing by closing gate valve in steel drum.
Brief description of the drawings
Fig. 1 is the principle signal face of cheating steel drum in the hole the utility model proposes and fall water discharge method;
Fig. 2 is the layout schematic diagram of cheating steel drum and fall water discharge method in hole;
Fig. 3 is the french drain sectional drawing of cheating steel drum and fall water discharge method in hole;
Fig. 4 is the installation sectional drawing of cheating steel drum and fall water discharge method in hole;
In figure: 1-steel drum, 2-gate valve, 3-water pump, 4-seal ring, 5-soil layer, a 6-dog stone, 7-plastic sheeting, 8-centimetre stone, 9-raft plate face.
Detailed description of the invention
Below in conjunction with drawings and Examples, the utility model is further elaborated:
Cheat steel drum for the hole of water seal for deep foundation pit and fall dewatering installation, make the cylindrical steel drum (1) of diameter 800mm ~ 1200mm, a thick 5mm, height is determined by built plank thickness.Steel drum (1) bottom opening is also installed gate valve (2), the every 3000mm of outer wall surface of steel drum (1) is long along surrounding welding seal ring (4), in the construction of raft plate, dig the hole of dark 800mm at the place of leaking, and with centimetre stone (8) hole bottom fill out 100mm thickness, the water of other leakage point is incorporated in hole by french drain, then steel drum (1) is put into the hole of filling in a centimeter stone (8), then use a centimeter stone (8) to fill up steel drum (1) bottom surrounding; In french drain, insert a dog stone (6), and cover with plastic sheeting (7), by french drain, the water of other leakage points is incorporated in hole and enters steel drum (1), the water pump (3) that last resort is placed on steel drum (1) the inside draws water.In whole work progress, underground water can not impact.
From accompanying drawing 1, the structure of water seal for deep foundation pit steel drum: in steel drum (1) bottom, several gate valves (2) are installed, seal ring (4) is welded on steel drum (1) outer wall surface surrounding, and water pump (3) is put into steel drum (1) and drawn water.
From accompanying drawing 2, seal ring (4) is welded on steel drum (1) around, and gate valve (2) is arranged on steel drum (1) bottom.
From accompanying drawing 3, a dog stone (6) fills up whole french drain along soil layer (5), then uses plastic sheeting (7) to cover french drain.
From accompanying drawing 4, centimetre stone (8) is filled out at the upper 100mm of soil layer (5) thick, and it is upper that steel drum (1) is placed on a centimeter stone (8), and centimetre stone (8) fills up along steel drum (1) bottom surrounding, and steel drum (1) top spills raft plate face (9) 50mm.

Claims (5)

1. in a hole, cheat steel drum and fall dewatering installation, it is characterized in that, comprise the steel drum (1) of column type, described steel drum (1) bottom opening is also installed gate valve (2) in aperture, steel drum (1) outer wall surface welding seal ring (4), dig the hole of dark 800mm at the place of leaking, fill out the centimetre stone (8) that 100mm is thick in the bottom in hole, described dell is connected by french drain with other leakage point, steel drum (1) is put into the hole of filling in a centimeter stone (8), then use a centimeter stone (8) to fill up steel drum (1) bottom surrounding, finally put into the water pump (3) for drawing water in steel drum (1) the inside.
2. in hole as claimed in claim 1, cheat steel drum and fall dewatering installation, it is characterized in that, described steel drum (1) diameter is that 800mm ~ 1200mm, wall thickness are 5mm, and height is determined by built plank thickness.
3. in hole as claimed in claim 1, cheat steel drum and fall dewatering installation, it is characterized in that, described steel drum (1) welds one seal ring (4) along the every 3000mm of short transverse.
4. in hole as claimed in claim 1, cheat steel drum and fall dewatering installation, it is characterized in that, in described french drain, insert a dog stone (6), and cover with plastic sheeting (7).
5. in hole as claimed in claim 1, cheat steel drum and fall dewatering installation, it is characterized in that, described steel drum (1) is placed on upper its top of a centimeter stone (8) and spills raft plate face (9) 50mm, and centimetre stone (8) fills up along steel drum (1) bottom surrounding.
CN201420386447.2U 2014-07-14 2014-07-14 In a kind of hole, cheat steel drum and fall dewatering installation Active CN203939038U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420386447.2U CN203939038U (en) 2014-07-14 2014-07-14 In a kind of hole, cheat steel drum and fall dewatering installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420386447.2U CN203939038U (en) 2014-07-14 2014-07-14 In a kind of hole, cheat steel drum and fall dewatering installation

Publications (1)

Publication Number Publication Date
CN203939038U true CN203939038U (en) 2014-11-12

Family

ID=51858365

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420386447.2U Active CN203939038U (en) 2014-07-14 2014-07-14 In a kind of hole, cheat steel drum and fall dewatering installation

Country Status (1)

Country Link
CN (1) CN203939038U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106759372A (en) * 2016-11-12 2017-05-31 中国二十二冶集团有限公司 Deep basal pit bank protection, the construction method of precipitation integrated construction nearer apart from side slope

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106759372A (en) * 2016-11-12 2017-05-31 中国二十二冶集团有限公司 Deep basal pit bank protection, the construction method of precipitation integrated construction nearer apart from side slope

Similar Documents

Publication Publication Date Title
CN102797266B (en) Well sealing waterproof construction method for dewatering well
CN103343543B (en) Foundation pit dewatering well pressure-reduction-type plugging method
CN101250879B (en) Method for processing bottom solum trickleing water of deep building pit
CN204266220U (en) A kind of plugging device of precipitation well in foundation pit
CN103046565B (en) Draining method for ultra-deep batholith deep foundation pit
CN104711994A (en) Foundation pit deep well rainfall and plugging construction method
CN103161172B (en) Elevator shaft bottom precipitation construction method
CN202730786U (en) Well-sealing waterproof construction structure of dewatering well
CN104060622B (en) Steel drum Yield rainfall relation method is cheated in a kind of hole
CN106320353A (en) Basement construction dewatering and drainage device and construction method thereof
CN204530733U (en) Underground construction deep-well precipitation well head plugging structure
CN209339169U (en) A kind of precipitation well in foundation pit plugging device
CN103572764A (en) Watertight structure for retaining wall of ultra-deep manually excavated pile and construction method thereof
CN105484277A (en) Component for tubular well precipitation construction in elevator foundation pit or sump and construction method
CN205205844U (en) Member is used in construction of tubular well precipitation in elevator foundation ditch or sump pit
CN201794082U (en) Local precipitation and drainage device for deep foundation pit
CN105178342B (en) Precipitation well casing and method for blocking reserved hole of foundation pit through precipitation well casing
CN203768925U (en) Seal device for dewatering well in foundation pit
CN204959781U (en) Dewatering well plugging device
CN206495224U (en) A kind of foundation pit of elevator shaft dewatering process structure
CN202108045U (en) Sleeve pipe with anchor rod penetrating through underground continuous wall
CN203939038U (en) In a kind of hole, cheat steel drum and fall dewatering installation
CN115787691A (en) Construction method of well plugging device for dewatering well in underground water rich area
CN216586626U (en) Basement post-cast strip drainage system
CN110258660A (en) The manufacture craft and shut-in well technique of the decompression drainage sump of basement anti-floating

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant