CN103161172B - Elevator shaft bottom precipitation construction method - Google Patents

Elevator shaft bottom precipitation construction method Download PDF

Info

Publication number
CN103161172B
CN103161172B CN201210169685.3A CN201210169685A CN103161172B CN 103161172 B CN103161172 B CN 103161172B CN 201210169685 A CN201210169685 A CN 201210169685A CN 103161172 B CN103161172 B CN 103161172B
Authority
CN
China
Prior art keywords
elevator shaft
sump
construction method
shaft bottom
metal tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210169685.3A
Other languages
Chinese (zh)
Other versions
CN103161172A (en
Inventor
初彦辰
鲍贵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Beijing Tianrun Construction Co Ltd
Original Assignee
China 22MCC Group Corp Ltd
Beijing Tianrun Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd, Beijing Tianrun Construction Co Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN201210169685.3A priority Critical patent/CN103161172B/en
Publication of CN103161172A publication Critical patent/CN103161172A/en
Application granted granted Critical
Publication of CN103161172B publication Critical patent/CN103161172B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

一种建筑物电梯井底降水施工方法,该方法包括如下步骤:将电梯井底向下挖集水坑;集水坑内预埋金属管;集水坑内回填石子,回填至垫层标高,并将金属管固定在集水坑内;采用自吸式水泵进行抽水作业,并在抽水的同时浇筑混凝土垫层;铺设防水卷材;进行混凝土保护层施工作业;进行基础底板施工作业。本发明建筑物电梯井底降水施工方法,可以有效的控制电梯井内因积水过多给施工带来的无法进行下道工序的实际困难;保证了垫层的正常施工;有效的防止防水卷材因积水而鼓出基础底面。

A construction method for dewatering the bottom of a building elevator shaft, the method comprising the following steps: digging a sump downward at the bottom of the elevator shaft; pre-burying metal pipes in the sump; Metal pipes are fixed in the sump; self-priming pumps are used for pumping operations, and concrete cushions are poured while pumping water; waterproof membranes are laid; concrete protective layer construction operations are carried out; foundation floor construction operations are carried out. The construction method for dewatering at the bottom of the elevator shaft of a building in the present invention can effectively control the actual difficulty that the next process cannot be carried out due to excessive water accumulation in the elevator shaft; it ensures the normal construction of the cushion layer; The bottom surface of the foundation is bulging due to accumulated water.

Description

电梯井底降水施工方法Construction Method of Elevator Shaft Bottom Dewatering

技术领域 technical field

本发明涉及一种建筑物施工方法,具体的说,是涉及一种建筑物电梯井底降水施工方法。 The invention relates to a building construction method, in particular to a construction method for dewatering the bottom of a building elevator well.

背景技术 Background technique

目前建筑物基础施工时,由于地下水的反水,电梯井内经常出现积水过多,造成电梯井无法进行混凝土垫层和防水卷材铺贴工序的施工,如果强行施工垫层并铺设防水卷材,则防水卷材容易被水鼓出底板表面。 At present, during the construction of the building foundation, due to the backwater of the groundwater, there is often too much water in the elevator shaft, which makes it impossible to carry out the construction of the concrete cushion and waterproof membrane laying process in the elevator shaft. If the cushion is forcibly constructed and the waterproof membrane is laid , the waterproof membrane is easy to be bulged out of the surface of the bottom plate by water.

目前建筑工地上降水均使用基坑周边井点降水,此方法可以控制基坑内部水位标高。但是此方法存在如下缺陷:电梯井底部标高均在基坑下部,随着楼层的增高,电梯井深度也相对增加,因此很容易出现电梯井内积水过多无法排干的现象,因此对垫层施工会造成很大的困难,如果将水抽干并强行施工垫层和防水卷材,则会出现防水卷材被水鼓出底板表面,并将防水保护层顶裂的现象。因此对下道工序的施工造成一定的困难。 At present, the precipitation on the construction site is dewatered from wells around the foundation pit. This method can control the water level inside the foundation pit. However, this method has the following defects: the elevation of the bottom of the elevator shaft is at the lower part of the foundation pit. The construction will cause great difficulties. If the water is drained and the cushion and waterproof membrane are forcibly constructed, the waterproof membrane will be bulged out of the surface of the bottom plate by the water, and the waterproof protective layer will be cracked. Therefore cause certain difficulty to the construction of next working procedure.

发明内容 Contents of the invention

针对上述现有技术中的不足,本发明有效杜绝防水卷材被水鼓出底板表面,造成电梯井底无法进行混凝土垫层和防水卷材铺贴工序的施工的技术难题,而提供一种建筑物电梯井底降水施工方法。 Aiming at the deficiencies in the above-mentioned prior art, the present invention effectively eliminates the technical problem that the waterproof coiled material is bulged out of the surface of the bottom plate by water, resulting in the inability to carry out the construction of the concrete cushion and the waterproof coiled material laying process at the bottom of the elevator shaft, and provides a building A construction method for dewatering at the bottom of an elevator well.

本发明所采取的技术方案是: The technical scheme that the present invention takes is:

一种建筑物电梯井底降水施工方法,该方法包括如下步骤: A construction method for dewatering at the bottom of a building elevator shaft, the method comprising the following steps:

a.将电梯井底向下挖1m~1.2m,做成底部直径500mm~700mm,顶部直径700mm~900mm的集水坑;集水坑内预埋金属管,所述金属管直径80mm~120mm; a. Dig down the bottom of the elevator shaft by 1m to 1.2m to make a sump with a diameter of 500mm to 700mm at the bottom and a diameter of 700mm to 900mm at the top; a metal pipe is embedded in the sump, and the diameter of the metal pipe is 80mm to 120mm;

b.集水坑内回填石子,回填至垫层标高,并将金属管固定在集水坑内; b. Backfill the sump with stones to the level of the cushion layer, and fix the metal pipe in the sump;

c.采用自吸式水泵进行抽水作业,将集水坑内的积水抽出,并在抽水的同时浇筑混凝土垫层;铺设防水卷材;在防水卷材与金属管结合处,使用防水油膏将金属管密封; c. Use self-priming pumps for pumping operations, pump out the accumulated water in the sump, and pour concrete cushions while pumping water; lay waterproof membranes; use waterproof ointment at the junction of waterproof membranes and metal pipes Metal pipe seal;

d.进行混凝土保护层施工作业; d. Carry out concrete protective layer construction work;

e.进行基础底板施工作业; e. Carry out foundation floor construction work;

f.金属管在基础底板层设置有圆环止水板: f. The metal pipe is provided with a ring water stop plate on the base floor layer:

g.切断金属管;将金属管封堵密实。 g. Cut off the metal pipe; seal the metal pipe tightly.

所述金属管根部设置有直径10mm~20mm的圆孔。 A circular hole with a diameter of 10 mm to 20 mm is provided at the root of the metal pipe.

所述回填石子的颗粒的直径为:20mm~40mm。 The particle diameter of the backfilled stones is 20mm-40mm.

所述金属管封堵是将油麻和石棉水泥塞入金属管,然后使用微膨胀水泥封口;或者使用金属板将金属管口焊死进行封堵。 The sealing of the metal pipe is to insert linoleum and asbestos cement into the metal pipe, and then use micro-expansion cement to seal; or use a metal plate to weld the metal pipe mouth to seal.

所述圆环止水板至少为两道。 There are at least two circular water stop plates.

所述圆环止水板设置在基础底板层中间位置。 The ring water stop plate is arranged in the middle of the base floor layer.

所述圆环止水板的厚度为3mm~8mm;外径150mm~180mm。 The thickness of the ring water stop plate is 3mm-8mm; the outer diameter is 150mm-180mm.

所述圆环止水板是在施工时焊接也可以是提前焊接。 The ring water stop plate is welded during construction or welded in advance.

所述金属管下端距集水坑底部的高度为集水坑总高度的四分之一。本发明相对现有技术的有益效果: The height between the lower end of the metal pipe and the bottom of the sump is 1/4 of the total height of the sump. The beneficial effect of the present invention relative to prior art:

本发明建筑物电梯井底降水施工方法,可以有效的控制电梯井内因积水过多给施工带来的无法进行下道工序的实际困难;保证了垫层的正常施工;有效的防止防水卷材因积水而鼓出基础底面。 The construction method for dewatering at the bottom of the elevator shaft of a building in the present invention can effectively control the actual difficulty that the next process cannot be carried out due to excessive water accumulation in the elevator shaft; it ensures the normal construction of the cushion layer; The bottom surface of the foundation is bulging due to accumulated water.

附图说明 Description of drawings

图1是本发明建筑物电梯井底降水施工结构示意图; Fig. 1 is a schematic diagram of construction structure for dewatering at the bottom of a building elevator shaft of the present invention;

附图中主要部件符号说明: Explanation of symbols of main components in the accompanying drawings:

图中: In the picture:

1、混凝土基础底板2、混凝土保护层 1. Concrete base plate 2. Concrete protective layer

3、防水卷材4、混凝土垫层 3. Waterproof membrane 4. Concrete cushion

5、圆环止水板6、金属管 5. Ring water stop plate 6. Metal pipe

7、石子8、圆孔 7. Stone 8. Round hole

9、防水油膏10、集水坑。 9, waterproof ointment 10, sump.

具体实施方式 detailed description

以下参照附图及实施例对本发明进行详细的说明: The present invention is described in detail below with reference to accompanying drawing and embodiment:

附图1可知,一种建筑物电梯井底降水施工方法,该方法包括如下步骤: Accompanying drawing 1 as can be known, a kind of building elevator shaft bottom dewatering construction method, this method comprises the steps:

a.将电梯井底向下挖1m~1.2m,做成底部直径500mm~700mm,顶部直径700mm~900mm的集水坑;集水坑10内预埋金属管6,所述金属管6直径80mm~120mm; a. Dig the bottom of the elevator shaft down 1m-1.2m to make a sump with a diameter of 500mm-700mm at the bottom and a diameter of 700mm-900mm at the top; a metal pipe 6 is embedded in the sump 10, and the diameter of the metal pipe 6 is 80mm ~120mm;

b.集水坑10内回填石子7,回填至垫层标高,并将金属管6固定在集水坑10内; b. Backfill the sump 10 with stones 7 to the level of the cushion layer, and fix the metal pipe 6 in the sump 10;

c.采用自吸式水泵进行抽水作业,将集水坑内10的积水抽出,并在抽水的同时浇筑混凝土垫层4;铺设防水卷材3;在防水卷材3与金属管6结合处,使用防水油膏9将金属管6密封; c. Use a self-priming pump to pump water, pump out the accumulated water in the sump 10, and pour the concrete cushion 4 while pumping; lay the waterproof membrane 3; at the junction of the waterproof membrane 3 and the metal pipe 6, Use waterproof ointment 9 to seal metal pipe 6;

d.进行混凝土保护层2施工作业; d. Carry out the construction work of concrete protection layer 2;

e.进行基础底板1施工作业; e. Carry out the construction work of the base plate 1;

f.金属管6在基础底板层1设置有圆环止水板5: f. The metal pipe 6 is provided with a circular water stop plate 5 on the base floor layer 1:

g.切断金属管6;将金属管6封堵密实。 g. Cut off the metal pipe 6; seal the metal pipe 6 tightly.

所述金属管6根部设置有直径10mm~20mm的圆孔。 The root of the metal pipe 6 is provided with a round hole with a diameter of 10mm-20mm.

所述回填石子7的颗粒的直径为:20mm~40mm。 The diameter of the particles of the backfilled stones 7 is 20mm-40mm.

所述金属管6封堵是将油麻和石棉水泥塞入金属管6,然后使用微膨胀水泥封口;或者使用金属板将金属管口焊死进行封堵。 The sealing of the metal pipe 6 is to stuff linseed and asbestos cement into the metal pipe 6, and then use micro-expansion cement to seal; or use a metal plate to weld the metal pipe mouth to seal.

所述圆环止水板5至少为两道。 There are at least two annular water stop plates 5 .

所述圆环止水板5设置在基础底板层1中间位置。 The ring water stop plate 5 is arranged in the middle of the base floor layer 1 .

所述圆环止水板5的厚度为3mm~8mm;外径150mm~180mm。 The thickness of the ring water stop plate 5 is 3mm-8mm; the outer diameter is 150mm-180mm.

所述圆环止水板5是在施工时焊接也可以是提前焊接。 The ring water stop plate 5 is welded during construction and can also be welded in advance.

所述金属管6下端距集水坑10底部的高度为集水坑10总高度的四分之一。 The height of the lower end of the metal pipe 6 from the bottom of the sump 10 is 1/4 of the total height of the sump 10 .

如果电梯井内防水保护层已经浇筑,且被防水卷材顶裂,则将保护层混凝土凿开,割开鼓出的防水卷材,然后进行上述施工。 If the waterproof protective layer in the elevator shaft has been poured and is cracked by the waterproof coiled material, then the concrete of the protective layer is cut open, the bulged waterproof coiled material is cut, and then the above construction is carried out.

本发明所采用的金属管也可以是有足够壁厚的非金属管材,在封堵时可以采用粘结封堵的方式。 The metal pipe used in the present invention can also be a non-metallic pipe with sufficient wall thickness, and a bonding sealing method can be used for sealing.

本发明建筑物电梯井底降水施工方法,可以有效的控制电梯井内因积水过多给施工带来的无法进行下道工序的实际困难;保证了垫层的正常施工;有效的防止防水卷材因积水而鼓出基础底面。 The construction method for dewatering at the bottom of the elevator shaft of a building in the present invention can effectively control the actual difficulty that the next process cannot be carried out due to excessive water accumulation in the elevator shaft; it ensures the normal construction of the cushion layer; The bottom surface of the foundation is bulging due to accumulated water.

Claims (9)

1. a building elevator shaft bottom precipitation construction method, is characterized in that the method comprises the steps:
A. elevator shaft bottom is dug 1m ~ 1.2m downwards, make base diameter 500mm ~ 700mm, the sump of top diameter 700mm ~ 900mm; Built-in metal pipe in sump, described metal tube diameter 80mm ~ 120mm;
B. backfill stone in sump, is backfilled to bed course absolute altitude, and is fixed in sump by metal tube;
C. adopt self prime pump to carry out drawing water operation, the ponding in sump is extracted out, and the Pouring concrete at the same time bed course drawn water; Laying water-proof coiled material; In waterproof roll and metal tube junction, waterproofing unction is used to be sealed by metal tube;
D. concrete cover construction operation is carried out;
E. sole plate construction operation is carried out;
F. metal tube is provided with annulus seal plate at sole plate layer:
G. metal tube is cut off; By closely knit for metal tube shutoff.
2. building elevator shaft bottom precipitation construction method according to claim 1, is characterized in that: described metal tube root is provided with the circular hole of diameter 10mm ~ 20mm.
3. building elevator shaft bottom precipitation construction method according to claim 1, is characterized in that: the diameter of the particle of described backfill stone is: 20mm ~ 40mm.
4. building elevator shaft bottom precipitation construction method according to claim 1, is characterized in that: described metal tube shutoff is that spunyarn and asbestos cement are filled in metal tube, then uses micro-expansion cement sealing; Or use metal sheet metal pipe mouth to be welded and carry out shutoff.
5. building elevator shaft bottom precipitation construction method according to claim 1, is characterized in that: described annulus seal plate is at least twice.
6. building elevator shaft bottom precipitation construction method according to claim 1, is characterized in that: described annulus seal plate is arranged on sole plate layer centre position.
7. building elevator shaft bottom precipitation construction method according to claim 1, is characterized in that: the thickness of described annulus seal plate is 3mm ~ 8mm; External diameter 150mm ~ 180mm.
8. building elevator shaft bottom precipitation construction method according to claim 1, is characterized in that: described annulus seal plate is the welding or weld in advance when constructing.
9. building elevator shaft bottom precipitation construction method according to claim 1, is characterized in that: the height of described metal tube lower end bottom sump is 1/4th of sump overall height.
CN201210169685.3A 2012-05-29 2012-05-29 Elevator shaft bottom precipitation construction method Active CN103161172B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210169685.3A CN103161172B (en) 2012-05-29 2012-05-29 Elevator shaft bottom precipitation construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210169685.3A CN103161172B (en) 2012-05-29 2012-05-29 Elevator shaft bottom precipitation construction method

Publications (2)

Publication Number Publication Date
CN103161172A CN103161172A (en) 2013-06-19
CN103161172B true CN103161172B (en) 2016-01-20

Family

ID=48584681

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210169685.3A Active CN103161172B (en) 2012-05-29 2012-05-29 Elevator shaft bottom precipitation construction method

Country Status (1)

Country Link
CN (1) CN103161172B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103967028A (en) * 2014-05-27 2014-08-06 江苏南通三建集团有限公司 Immersed tube drainage structure and method for handling suddenly-produced foundation pit water bursting and fountains through immersed tube drainage structure
CN104452786A (en) * 2014-11-14 2015-03-25 武汉一冶建筑安装工程有限责任公司 Deep foundation pit elevator shaft sump dewatering construction method
CN106223351B (en) * 2016-07-26 2019-03-19 中国二十二冶集团有限公司 Construction method of self-priming pump to lower local groundwater level
CN106638642B (en) * 2017-02-21 2019-08-27 宏源防水科技集团有限公司 A method for treating precipitation in waterproof construction of underground building pit body
CN106894431B (en) * 2017-02-21 2019-08-27 宏源防水科技集团有限公司 A method for water-proof construction precipitation treatment of underground building pits in an environment rich in water resources
CN107152031B (en) * 2017-06-24 2022-04-22 中铁十一局集团第二工程有限公司 Drainage device of elevator without auxiliary pit
CN108487276A (en) * 2018-04-27 2018-09-04 陕西建工机械施工集团有限公司 A kind of embed-type shallow-layer combined water drain pipe and construction method
CN112695779A (en) * 2021-01-26 2021-04-23 山西三建集团有限公司 High-rise building foundation pit construction method for local precipitation of elevator shaft foundation pit

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4260334A (en) * 1976-02-11 1981-04-07 Kelley Contract Dewatering Company Ground dewatering system
CN101148884A (en) * 2007-10-30 2008-03-26 山东天齐置业集团股份有限公司 Waterproof and plugging construction method for precipitation well in foundation pit
CN101768976A (en) * 2009-12-29 2010-07-07 中建城市建设发展有限公司 Base pit dewatering and water saving device and construction method thereof
CN101936010A (en) * 2010-08-19 2011-01-05 天津二十冶建设有限公司 Construction method of dewatering well in underground concrete structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4260334A (en) * 1976-02-11 1981-04-07 Kelley Contract Dewatering Company Ground dewatering system
CN101148884A (en) * 2007-10-30 2008-03-26 山东天齐置业集团股份有限公司 Waterproof and plugging construction method for precipitation well in foundation pit
CN101768976A (en) * 2009-12-29 2010-07-07 中建城市建设发展有限公司 Base pit dewatering and water saving device and construction method thereof
CN101936010A (en) * 2010-08-19 2011-01-05 天津二十冶建设有限公司 Construction method of dewatering well in underground concrete structure

Also Published As

Publication number Publication date
CN103161172A (en) 2013-06-19

Similar Documents

Publication Publication Date Title
CN103161172B (en) Elevator shaft bottom precipitation construction method
CN103343543B (en) Foundation pit dewatering well pressure-reduction-type plugging method
CN105178344B (en) The construction method of the built-in anti-float anchor rod plugging structure of sole plate precipitation of deep well
CN102797266B (en) Well sealing waterproof construction method for dewatering well
CN104929143B (en) A kind of bottom of foundation ditch dewatering well shut-in well method
CN103046565B (en) Draining method for ultra-deep batholith deep foundation pit
CN103912009B (en) The high residential building baseset puddle construction method of quicksand geology
CN109736340B (en) Dewatering device and method for guaranteeing integrity of cushion layer by reserving dewatering well on foundation slab
CN103321256A (en) Anti-pollution three-dimensional composite seepage-proofing barrier system
CN105544622B (en) A kind of anti-floating system and its checking device of underground structure
CN101691756A (en) Construction method of foundation pit confined water inrushing emergency water-lowering well
CN102839691B (en) Quick sealing method and device for sandless cement pipe deep well dewatering wellhead
CN209669902U (en) Foundation sump seepage drainage system
CN205152970U (en) Underground structure oozes drainage system
CN111021333A (en) Spiral steel pile with segmental pressure grouting and its grouting technology
CN201567582U (en) A water-saving device for foundation pit dewatering
CN105484277A (en) Component for tubular well precipitation construction in elevator foundation pit or sump and construction method
CN203145029U (en) Plugging structure for deep foundation pit dewatering well
CN103898915B (en) Building small-area deep foundation pit anti-floating water stop construction method
WO2018214143A1 (en) Construction method for plugging dewatering well having penetrating bottom plate in foundation pit
CN209723004U (en) Built-in precipitation structure of raft and shut-in well structure of precipitation well
CN109025899B (en) Well sealing device
CN210712963U (en) Drainage structure of basement bottom plate post-cast strip
CN205205844U (en) Member is used in construction of tubular well precipitation in elevator foundation ditch or sump pit
CN111042212A (en) A rear-mounted thin-walled steel pipe drainage device and method for anti-floating of large bottom plate

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant