Prior art keywords
shear wall
reinforced
concrete shear
reinforced concrete
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420181272.1U
Other languages
Chinese (zh)
Inventor
黄靓
王海
李福安
郭建淼
尤少阳
高琦
贺方方
朱献峰
贺翔
包堂堂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xuchang Jinke Resource Recycling Co ltd
Zhuzhou Boerman Technology Development Co ltd
Original Assignee
Zhuzhou Boerman Science & Technology Development Co Ltd
Xuchang Jinke Architecture Cleaning And Transport Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhuzhou Boerman Science & Technology Development Co Ltd, Xuchang Jinke Architecture Cleaning And Transport Co Ltd filed Critical Zhuzhou Boerman Science & Technology Development Co Ltd
Priority to CN201420181272.1U priority Critical patent/CN203891247U/en
Application granted granted Critical
Publication of CN203891247U publication Critical patent/CN203891247U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The utility model discloses a mixing structure of an upper-portion reinforced masonry shear wall and a bottom reinforced concrete shear wall, and belongs to the field of building structure. The mixing structure is formed by no less than 6 layers of reinforced concrete shear walls, a reinforced masonry shear wall and a connecting beam, and is characterized in that the reinforced concrete shear walls is arranged at the bottom; the reinforced masonry shear wall is arranged in the upper portion; the connecting beam is arranged in the middle part; and the reinforced concrete shear walls, the reinforced masonry shear wall and the connecting beam are connected into the mixing structure via reinforced bars, the total height of the mixing structure is less than 100 m. Because the height of a building built by a single reinforced concrete shear wall is restrained into 20 layers, so space resources cannot fully used. The mixing structure provided by the utility model is free of such restrain, so space is fully used. The reinforced concrete shear walls are characterized by strong lateral stiffness, high strength and good anti-collision ability and are advantageous in that sources are saved, the reinforced concrete shear walls are environmentally-friendly, and earthquake resisting performance is good.

Description

Bottom reinforcement bars concrete shear force wall top reinforced masonry shear wall combination construction
Technical field
The application relates to building structure field, is specially a kind of bottom reinforcement bars concrete shear force wall top reinforced masonry shear wall combination construction.
Background technology
Along with day being becoming tight of the growing and construction land of urban construction, making full use of the usefull space is the direction that we will endeavour research.The multi-storey building that adopts reinforced concrete frame structure system, total cost increases by 1/3 left and right than brick mix structure conventionally, and adopts the multi-storey building anti-seismic performance of traditional brick mix structure system poor.Meanwhile, that country is greatly developing is energy-conservation, save land, the thermal insulation novel wall material that profit is useless, and restriction loam brick is produced and is used, and actively encourages novel wall material research and development.Therefore, the application of novel wall is anxious waits to expand.
Reinforced concrete shear wall has the characteristics such as intensity is high, ductility good, shatter-proof, but its cost is higher, and horizontal planning of building limitation is large, the space that more difficult acquisition is larger.
Reinforced masonry shear wall structure is to bear vertical and the built with ribbed bricks shear wall of horizontal force and the house architectural structure that concrete building, roof system form, and it has and economizes on resources, and environmentally friendly, anti-seismic performance is good, the advantage such as is suitable for flexibly.Reinforced masonry system is the first-elected new architecture of the Ministry of Construction, meets the requirement of national sustainable development.Its minimum steel ratio is half of concrete shear force wall, can save steel 30~50%, does not need template, can save timber 30~50%, and the existence of building block can be saved cement 30~50%, and the saving of resource can be so that construction costs reduces by 15 ~ 30%; Protection bed thickness, there is good fire prevention and sound insulation property, the design of heat insulation building block makes body of wall energy-conservation ventilative again, speed of application is fast, can reduce in a large number the noise pollution causing in work progress, and can significantly reduce on-the-spot sand, stone, cement stacking, the manufacturing process of building block can be utilized a large amount of industry and building debris; Reinforced masonry shear wall has the characteristics such as intensity is high, ductility good, shatter-proof, and both at home and abroad a large amount of such buildings show fabulous performance in earthquake, while being subject to the affecting of the many factors such as temperature, drying shrinkage, is not easy to occur crack; The span of building block House with Big Room Openning is accomplished 6m~8m or larger, has compliance, flexibility, correctability, meets a sexual demand.But because the height restriction of single reinforced masonry shear wall structure is 20 layers, and the height of present most of middle-high building all approaches 100 meters, and the building of single reinforced masonry shear wall structure can not make full use of effective architectural space.Bottom reinforcement bars concrete shear force wall top reinforced masonry shear wall combination construction has solved this problem, and has the advantage of two kinds of shear walls concurrently.
Utility model content
The purpose of this utility model is to provide that a kind of cost is low, intensity is high, ductility is good, anti-seismic performance is good, can make full use of again architectural space, economizes on resources, the construction wall structure of applicable, environmental protection flexibly.
The purpose of this utility model is achieved by the following technical solution:
A kind of bottom reinforcement bars concrete shear force wall top reinforced masonry shear wall combination construction, it is by reinforced concrete shear wall 1, reinforced masonry shear wall 2 and tie-beam 7 form, it is characterized in that: described reinforced concrete shear wall 1 is positioned at bottom, reinforced masonry shear wall 2 is positioned at top, in the middle of tie-beam 7 is positioned at, and connect into combination construction by reinforcing bar, the top of reinforced concrete shear wall 1 have stretch out certain length stretch out reinforcing bar 3, in reinforced masonry shear wall 2, be interspersed with and the vertical reinforcement 4 that stretches out reinforcing bar 3 and be connected, the depth of building of building by laying bricks or stones is 20 meters to 100 meters, the number of plies of reinforced concrete shear wall 1 is not less than 6 layers, stretching out reinforcing bar 3 is welding or colligation with the connected mode of vertical reinforcement 4, stretch out reinforcing bar 3 extensions and be bent to centre position.Bottom reinforcement bars concrete shear force wall top reinforced masonry shear wall combination construction has that cost is low, intensity is high, ductility is good, anti-seismic performance is good, can make full use of again architectural space, economizes on resources, the advantage such as applicable, environmental protection flexibly.
Accompanying drawing explanation
Fig. 1 is bottom reinforcement bars concrete shear force wall top reinforced masonry shear wall combination construction floor map;
Fig. 2 is bottom reinforcement bars concrete shear force wall and the local sectional side view that is connected of top reinforced masonry shear wall;
Fig. 3 is the local connection diagram of bottom reinforcement bars concrete shear force wall top reinforced masonry shear wall.
Description of reference numerals is as follows: 1-reinforced concrete shear wall 2-reinforced masonry shear wall 3-stretches out reinforcing bar 4-vertical reinforcement 5-transverse reinforcement 6-mortar 7-beam.
The specific embodiment
Below with reference to accompanying drawing, the application is described further:
Embodiment 1:
A kind of bottom reinforcement bars concrete shear force wall top reinforced masonry shear wall combination construction, its building method is: every layer of bottom is the fixing position of reinforcing bar first, and place template, maintenance a period of time after concreting, treat that concrete reaches enough intensity and with identical method, carries out building by laying bricks or stones of lower one deck more later, carrying out the 10th layer while building by laying bricks or stones, its top need be reserved and stretch out reinforcing bar 3, its upper end is bent to centre position, after completing the building by laying bricks or stones of beam and plate, on beam 7, carry out building by laying bricks or stones of top reinforced masonry shear wall, up build by laying bricks or stones on building block one skin one skin ground, after reaching a certain height, from the vertical hole of building block, insert vertical reinforcement 4, and in the clean-out hatch of a bottom skin building block by vertical reinforcement 4 with stretch out reinforcing bar 3 and be connected, and guarantee that the length connecting is enough, then concrete perfusion in building block hole, finally form the shear wall combination construction that stress performance is good.
Above-mentioned drawings and Examples are only more preferably a kind of for the application is described; protection domain to the application does not constitute any limitation, within those skilled in the art carries out common variation and replaces and should be included in the application's protection domain within the scope of the application's scheme.

Claims (5)

1. a bottom reinforcement bars concrete shear force wall top reinforced masonry shear wall combination construction, it is by reinforced concrete shear wall (1), reinforced masonry shear wall (2) and tie-beam (7) form, it is characterized in that: described reinforced concrete shear wall (1) is positioned at bottom, reinforced masonry shear wall (2) is positioned at top, in the middle of tie-beam (7) is positioned at, and connect into combination construction by reinforcing bar, the top of reinforced concrete shear wall (1) have stretch out certain length stretch out reinforcing bar (3), in reinforced masonry shear wall (2), be interspersed with and the vertical reinforcement (4) that stretches out reinforcing bar (3) and be connected.
2. a kind of bottom reinforcement bars concrete shear force wall according to claim 1 top reinforced masonry shear wall combination construction, is characterized in that: the depth of building of building by laying bricks or stones is 20 meters to 100 meters.
3. a kind of bottom reinforcement bars concrete shear force wall according to claim 1 top reinforced masonry shear wall combination construction, is characterized in that: the number of plies of reinforced concrete shear wall (1) is not less than 6 layers.
4. a kind of bottom reinforcement bars concrete shear force wall according to claim 1 top reinforced masonry shear wall combination construction, is characterized in that: stretching out reinforcing bar (3) is welding or colligation with the connected mode of vertical reinforcement (4).
5. a kind of bottom reinforcement bars concrete shear force wall according to claim 1 top reinforced masonry shear wall combination construction, is characterized in that: stretch out reinforcing bar (3) extension and be bent to centre position.
CN201420181272.1U 2014-04-16 2014-04-16 Mixing structure of upper-portion reinforced masonry shear wall and bottom reinforced concrete shear wall Expired - Fee Related CN203891247U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420181272.1U CN203891247U (en) 2014-04-16 2014-04-16 Mixing structure of upper-portion reinforced masonry shear wall and bottom reinforced concrete shear wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420181272.1U CN203891247U (en) 2014-04-16 2014-04-16 Mixing structure of upper-portion reinforced masonry shear wall and bottom reinforced concrete shear wall

Publications (1)

Publication Number Publication Date
CN203891247U true CN203891247U (en) 2014-10-22

Family

ID=51717668

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420181272.1U Expired - Fee Related CN203891247U (en) 2014-04-16 2014-04-16 Mixing structure of upper-portion reinforced masonry shear wall and bottom reinforced concrete shear wall

Country Status (1)

Country Link
CN (1) CN203891247U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104389360A (en) * 2014-12-29 2015-03-04 株洲博尔曼科技发展有限公司 Externally suspended insulation board type reinforcement brickwork shear wall system and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104389360A (en) * 2014-12-29 2015-03-04 株洲博尔曼科技发展有限公司 Externally suspended insulation board type reinforcement brickwork shear wall system and construction method thereof

Similar Documents

Publication Publication Date Title
CN103015565B (en) Prefabricated and assembled type integrated reinforced concrete load bearing wall and building construction method
CN103306501B (en) Energy-saving domestic architecture with cast-in-place industrial gypsum bearing wall and manufacturing method thereof
CN104213717A (en) Integrated reconstruction method for multi-storey residential
CN105003020A (en) Ceramsite concrete metal net rack light wallboard and splicing structure thereof
CN201972417U (en) Lightweight wood structure roof system
CN208168032U (en) Assembled built-in heat insulation layer concrete composite wall-light steel frame-floor connecting node
CN203270856U (en) Building wall
CN103046664A (en) Energy-saving wall with connecting keys and recycled concrete wall panels holding insulation block masonry, and manufacturing method of energy-saving wall
CN106320601B (en) Assembly concrete is whole without heat bridge board wall and its vertical connection method
CN204919968U (en) Ceramsite concrete metal rack light weight wallboard
CN204876313U (en) Take mesh frame clip heart light partition wall board
CN203891247U (en) Mixing structure of upper-portion reinforced masonry shear wall and bottom reinforced concrete shear wall
CN203891066U (en) Underground structure prefabricated ribbed-plate type component
CN103255834B (en) Prefabricated heat-preservation balcony suitable for industrial production and construction method thereof
CN203320751U (en) Formwork thermal insulation integrated wall body
CN103541478B (en) Lattice superposed beam and plate and construction method thereof
CN203701689U (en) Assembly structured module house
CN106638956A (en) Concrete wallboard and ribbed slab dry type connection node
CN203640154U (en) Engineering wood-profiled steel sheet-lightweight aggregate concrete composite beam
CN207892081U (en) One body composite board T shape walls of Fast Installation heat insulation decorative load-bearing
CN208023783U (en) A kind of prefabricated light gauge cold-formed steel shape regeneration concrete assembled wall
CN201614679U (en) Assembled building reinforced concrete precast plate
CN207597635U (en) One body composite board L-shaped wall of Fast Installation heat insulation decorative load-bearing
CN206616695U (en) A kind of concrete panel and girt strip floor dry type connecting node
CN206737125U (en) Low energy consumption prefabricated buildings

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: The northern section of Xuchang city in Henan province Dongcheng District Wei Road 461000

Patentee after: XUCHANG JINKE RESOURCE RECYCLING Co.,Ltd.

Patentee after: ZHUZHOU BOERMAN TECHNOLOGY DEVELOPMENT Co.,Ltd.

Address before: The northern section of Xuchang city in Henan province Dongcheng District Wei Road 461000

Patentee before: XUCHANG JINKE BUILDING REMOVING CO.,LTD.

Patentee before: ZHUZHOU BOERMAN TECHNOLOGY DEVELOPMENT Co.,Ltd.

TR01 Transfer of patent right

Effective date of registration: 20151126

Address after: The northern section of Xuchang city in Henan province Dongcheng District Wei Road 461000

Patentee after: XUCHANG JINKE RESOURCE RECYCLING Co.,Ltd.

Address before: The northern section of Xuchang city in Henan province Dongcheng District Wei Road 461000

Patentee before: XUCHANG JINKE RESOURCE RECYCLING Co.,Ltd.

Patentee before: ZHUZHOU BOERMAN TECHNOLOGY DEVELOPMENT Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141022

CF01 Termination of patent right due to non-payment of annual fee