Attached lifting construction platform obstacle-crossing structure Download PDFInfo
- Publication number
- CN203878964U CN203878964U CN201420195703.XU CN201420195703U CN203878964U CN 203878964 U CN203878964 U CN 203878964U CN 201420195703 U CN201420195703 U CN 201420195703U CN 203878964 U CN203878964 U CN 203878964U
- Authority
- CN
- China
- Prior art keywords
- row
- column
- platform
- protective screen
- lifting operation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Movable Scaffolding (AREA)
Abstract
The utility model discloses an attached lifting construction platform obstacle-crossing structure which comprises at least two rows of stand columns, platform bottom plates, and two rope winding and unwinding devices. The number of the platform bottom plates which are installed between the two rows of stand columns at the same horizontal height is two. One end of each platform bottom plate is connected with the corresponding row of stand columns in a rotating mode, and the other end of each platform bottom plate is connected with the corresponding rope winding and unwinding device through an inhaul cable. Protective net plates of an unfolding and folding structure are arranged between the two rows of stand columns, and the number of the protective net plates is at least two. One side of each protective net plate is connected with the corresponding row of stand columns in a rotating mode, and the other three sides of each protective net plate are connected with one another through connecting lug plates. By means of the attached lifting construction platform obstacle-crossing structure, the platform bottom plate can be quite conveniently turned so as to unfold and fold the protective net plates, and a construction platform can smoothly cross obstacles in construction.
Description
Technical field
The utility model relates to the Construction Formwork & Scaffold Technology field of building operations, is specifically related to a kind of adhering lifting operation platform obstacle detouring structure.
Background technology
Scaffold (scaffold) for workman operates and solve the various supports that high-rise working is set up, is the generic term of building field at the construction field (site), and along with the fast development of building field, super highrise building is more and more at present.Simultaneously also more and more higher to the requirement of scaffold, traditional steel tube fastener formula scaffold can not meet construction needs.Construction of super highrise building adopts attachment type raise scaffold more at present, namely adhering lifting operation platform.
Because adhering lifting operation platform is set up installation around building surrounding, the overwhelming majority is continuously and seals, and that objects such as tower machine attachment arm in building operations lie across is inner at top or the support body of operation platform, lifting formation obstacle that just must be to operation platform.In the case, just need to not destroy under the integrally-built prerequisite of operation platform, allow platform floor, protective screen plate etc. when lifting, cross this obstruction, and after clearing the jumps, make again platform floor, protective screen plate reset, and recover its corresponding function.But existing platform floor, web plate are all completely fixed, and if desired clear the jumps, can only be removed, after crossing, to reinstall again, this makes operation very complicated, and is high-altitude assembling and disassembling stand body component, exists very large falling object from high altitude dangerous.For above problem, be necessary the obstacle detouring structure of adhering lifting operation platform to be improved further.
Utility model content
The utility model has overcome the deficiencies in the prior art, and a kind of adhering lifting operation platform obstacle detouring structure is provided, and makes operation platform can cross smoothly the obstruction occurring in work progress.
Consider the problems referred to above of prior art, according to the disclosed aspect of the utility model, the utility model by the following technical solutions:
An adhering lifting operation platform obstacle detouring structure, comprises at least two row's columns, platform floor, two cover withdrawing rope devices; The platform floor that is arranged on the same level height between described two row's columns is two;
One end of a platform floor and row's column are rotationally connected, and the other end of a described platform floor is connected with a withdrawing rope device by a drag-line, and a described withdrawing rope device is arranged on described row's column;
One end of another piece platform floor and another row's column are rotationally connected, and the other end of described another piece platform floor is connected with another withdrawing rope device by another drag-line, and described another withdrawing rope device is arranged on described another row's column.
In order to realize better the utility model, further technical scheme is:
According to an embodiment of the present utility model, the other end of described two platform floors is respectively provided with an anti-collapse safety block.
According to an embodiment of the present utility model, between two anti-collapse safety blocks that are oppositely arranged, be bolted.
According to an embodiment of the present utility model, on described two anti-collapse safety blocks, be respectively provided with the sling point being connected with drag-line.
According to an embodiment of the present utility model, described withdrawing rope device is hand-operated gear roll type withdrawing rope, adopts click locking.
According to an embodiment of the present utility model, described two withdrawing rope devices are all arranged on the column of described two platform floors top.
According to an embodiment of the present utility model, between described two row's columns, be also provided with the protective screen plate of opening-closing structure, described protective screen plate is at least two, and a side of a protective screen plate and row's column are rotationally connected, and a side of another piece protective screen plate and another row's column are rotationally connected.
According to an embodiment of the present utility model, a side of a described protective screen plate is rotationally connected by hinge and row's column, and a side of another piece protective screen plate is also rotationally connected by hinge and another row's column.
According to an embodiment of the present utility model, on the relative opposite side of described two protective screen plates, be respectively arranged with one and connect otic placode.
The utility model can also be:
According to an embodiment of the present utility model, the both sides up and down of described two protective screen plates are also respectively arranged with one and connect otic placode.
Compared with prior art, one of the beneficial effects of the utility model are:
A kind of adhering lifting operation platform obstacle detouring structure of the present utility model, can overturn platform floor very easily by withdrawing rope device, to avoid tower crane attachment arm during operation platform lifting; Protective screen plate adopts can opening type hinge engaging structure, makes folding very convenient.Make platform floor, protective screen plate not need dismounting just can cross easily the obstruction in construction works, the potential safety hazard of having avoided high-altitude assembling and disassembling stand body component to bring.
Accompanying drawing explanation
For clearer explanation present specification embodiment or technical scheme of the prior art, to the accompanying drawing of required use in the description of embodiment or prior art be briefly described below, apparently, the accompanying drawing the following describes is only the reference to some embodiment in present specification, for those skilled in the art, in the situation that not paying creative work, can also obtain according to these accompanying drawings other accompanying drawing.
Fig. 1 shows the adhering lifting operation platform obstacle detouring structural representation according to an embodiment of the utility model.
Fig. 2 shows according to the front schematic view of the adhering lifting operation platform obstacle detouring structure that comprises protective screen plate of an embodiment of the utility model.
Fig. 3 shows according to the schematic top plan view of the adhering lifting operation platform obstacle detouring structure that comprises protective screen plate of an embodiment of the utility model.
The specific embodiment
Below in conjunction with embodiment, the utility model is described in further detail, but embodiment of the present utility model is not limited to this.
Fig. 1 shows the adhering lifting operation platform obstacle detouring structural representation according to an embodiment of the utility model.A kind of adhering lifting operation platform obstacle detouring structure as shown in Figure 1, comprises at least two row columns 1, platform floors 2, two withdrawing rope devices 3; The platform floor 2 that is arranged on the same level height between described two row's columns 1 is two.
One end of a platform floor 2 and row's column 1 are rotationally connected, and the other end of a described platform floor 2 is connected with a withdrawing rope device 3 by a drag-line 4, and a described withdrawing rope device 3 is arranged on described row's column 1.One, left side platform floor 2 is received drag-line 4 in short situation by withdrawing rope device 3 as shown in Figure 1, and one, this left side platform floor 2 rotates the tie point around row's column 1, and upwards upset.
One end of another piece platform floor 2 and another row's column 1 are rotationally connected, and the other end of described another piece platform floor 2 is connected with another withdrawing rope device 3 by another drag-line 4, and described another withdrawing rope device 3 is arranged on described another row's column 1.One, the right platform floor 2 is received drag-line 4 in short situation by withdrawing rope device 3 as shown in Figure 1, and one, this right platform floor 2 rotates the tie point around another row's column 1, and upwards upset.
When adhering lifting operation platform runs into obstacle, by withdrawing rope device 3, control upwards upset of two platform floors 2, after it is cleared the jumps, make again withdrawing rope device 3 emit drag-line 4, two platform floors 2 upset is downwards set level, made the functional rehabilitation of platform floor 2 normal.
Continue as shown in Figure 1, the other end of two platform floors 2 is respectively provided with an anti-collapse safety block 5, anti-collapse safety block 5 is arranged on the top of platform floor 2, at drag-line 4, occur under fracture or other fortuitous event, when two platform floors 2 will soon subside downwards, two anti-collapse safety blocks 5 can produce squeezing action power mutually, to form rock-steady structure, avoid platform floor 2 continue subside.
Two anti-collapse safety blocks 5 that are oppositely arranged in other words every pair of anti-collapse safety block 5 can be bolted, and further strengthen the supporting capacity of platform.
On described two anti-collapse safety blocks 5, be respectively provided with the sling point being connected with drag-line 4, drag-line 4 can be connected with platform floor 2 by the sling point of this anti-collapse safety block 5.
For withdrawing rope device 3, can be hand-operated gear roll type withdrawing rope device, can be by manual mode to the unlatching of two platform floors 2 or close and control.The locking of employing click, the length that drag-line 4 maintenances are needed is constant.
Setting position for withdrawing rope device 3 can be to be positioned on the column 1 of platform floor 2 tops that will control, and in preferred an enforcement as shown in Figure 1, described two withdrawing rope devices 3 are all arranged on the column 1 of described two platform floor 2 tops.
Fig. 2 shows according to the front schematic view of the adhering lifting operation platform obstacle detouring structure that comprises protective screen plate of an embodiment of the utility model.Fig. 3 shows according to the schematic top plan view of the adhering lifting operation platform obstacle detouring structure that comprises protective screen plate of an embodiment of the utility model.Between two row's columns 1 as shown in Figures 2 and 3, be also provided with the protective screen plate 6 of opening-closing structure, described protective screen plate 6 is at least two (in Fig. 2, illustrated is the situation of 4 protective screen plates 6), one side of a protective screen plate 6 and row's column 1 are rotationally connected, and a side of another piece protective screen plate 6 and another row's column 1 are rotationally connected.Two protective screen plates 6, by the column 1 around being rotationally connected separately, are realized the function that two protective screen plates 6 open and close.
A kind of optimal way being rotationally connected for protective screen plate 6 and described column 1 can be, one side of a described protective screen plate 6 is rotationally connected by hinge 61 and row's column 1, and a side of another piece protective screen plate 6 is also rotationally connected by hinge 61 and another row's column 1.By hinge 61 can realize protective screen plate 6 in open or external-open.
On the relative opposite side of described two protective screen plates 6, can arrange respectively one and connect otic placode 62, two protective screen plates 6, after closing, connect by the connection otic placode 62 on the relative opposite side of these two protective screen plates 6.
The both sides up and down of described two protective screen plates 6 are also respectively arranged with one and connect otic placode 62, and the connection otic placode 62 of the both sides up and down by these two protective screen plates 6 can connect the protective screen plate 6 of protective screen plate 6 tops, below.
In this manual, each embodiment adopts the mode of going forward one by one to describe, and each embodiment stresses is the difference with other embodiment, identical similar part cross-references between each embodiment.
" embodiment " that spoken of in this manual, " another embodiment ", " embodiment ", etc., refer to specific features, structure or the feature in conjunction with this embodiment, described and be included at least one embodiment that the application's generality describes.In manual, a plurality of local appearance statement of the same race is not necessarily to refer to same embodiment.Furthermore, while describing a specific features, structure or feature in conjunction with arbitrary embodiment, what advocate is in conjunction with other embodiment, to realize this feature, structure or feature also to drop in scope of the present utility model.
Although the utility model is described with reference to a plurality of explanatory embodiment of the present utility model here, but, should be appreciated that, those skilled in the art can design a lot of other modification and embodiments, and these are revised and within embodiment will drop on the disclosed principle scope and spirit of the application.More particularly, in the scope of, accompanying drawing open in the application and claim, can carry out multiple modification and improvement to the building block of subject combination layout and/or layout.Except modification that building block and/or layout are carried out with improving, to those skilled in the art, other purposes will be also obvious.
Claims (10)
1. an adhering lifting operation platform obstacle detouring structure, is characterized in that, comprises at least two row's columns (1), platform floor (2), two cover withdrawing rope devices (3); The platform floor (2) that is arranged on the same level height between described two row's columns (1) is two;
One end of a platform floor (2) and row's column (1) are rotationally connected, the other end of a described platform floor (2) is connected with a withdrawing rope device (3) by a drag-line (4), and a described withdrawing rope device (3) is arranged on described row's column (1);
One end of another piece platform floor (2) and another row's column (1) are rotationally connected, the other end of described another piece platform floor (2) is connected with another withdrawing rope device (3) by another drag-line (4), and described another withdrawing rope device (3) is arranged on described another row's column (1).
2. adhering lifting operation platform obstacle detouring structure according to claim 1, is characterized in that, the other end of described two platform floors (2) is respectively provided with an anti-collapse safety block (5).
3. adhering lifting operation platform obstacle detouring structure according to claim 2, is characterized in that, between the two anti-collapse safety blocks (5) that are oppositely arranged, is bolted.
4. adhering lifting operation platform obstacle detouring structure according to claim 2, is characterized in that, is respectively provided with the sling point being connected with drag-line (4) on described two anti-collapse safety blocks (5).
5. adhering lifting operation platform obstacle detouring structure according to claim 1, is characterized in that, described withdrawing rope device (3) adopts hand-operated gear roll type withdrawing rope, click locking.
6. adhering lifting operation platform obstacle detouring structure according to claim 1, is characterized in that, described two withdrawing rope devices (3) are all arranged on the column (1) of described two platform floors (2) top.
7. according to the adhering lifting operation platform obstacle detouring structure described in claim 1~6 any one, it is characterized in that, between described two row's columns (1), be also provided with the protective screen plate (6) of opening-closing structure, described protective screen plate (6) is at least two, one side of a protective screen plate (6) and row's column (1) are rotationally connected, and a side of another piece protective screen plate (6) and another row's column (1) are rotationally connected.
8. adhering lifting operation platform obstacle detouring structure according to claim 7, it is characterized in that, one side of a described protective screen plate (6) is rotationally connected by hinge (61) and row's column (1), and a side of another piece protective screen plate (6) is also rotationally connected by hinge (61) and another row's column (1).
9. adhering lifting operation platform obstacle detouring structure according to claim 7, is characterized in that, is respectively arranged with one and connects otic placode (62) on the relative opposite side of described two protective screen plates (6).
10. adhering lifting operation platform obstacle detouring structure according to claim 8, is characterized in that, the both sides up and down of described two protective screen plates (6) are also respectively arranged with one and connect otic placode (62).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420195703.XU CN203878964U (en) | 2014-04-21 | 2014-04-21 | Attached lifting construction platform obstacle-crossing structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420195703.XU CN203878964U (en) | 2014-04-21 | 2014-04-21 | Attached lifting construction platform obstacle-crossing structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203878964U true CN203878964U (en) | 2014-10-15 |
Family
ID=51679480
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420195703.XU Expired - Fee Related CN203878964U (en) | 2014-04-21 | 2014-04-21 | Attached lifting construction platform obstacle-crossing structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203878964U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106988521A (en) * | 2017-05-05 | 2017-07-28 | 北京天润建设有限公司 | A kind of integrated form climbing frame |
-
2014
- 2014-04-21 CN CN201420195703.XU patent/CN203878964U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106988521A (en) * | 2017-05-05 | 2017-07-28 | 北京天润建设有限公司 | A kind of integrated form climbing frame |
CN106988521B (en) * | 2017-05-05 | 2019-11-22 | 北京天润建设有限公司 | A kind of integrated form climbing frame |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102383588B (en) | Lifting platform for protecting safety of high-level construction | |
CN102797222B (en) | Hanging bracket hinge joint type bridge maintenance vehicle capable of avoiding bridge-side obstacles | |
CN206408920U (en) | A kind of collapsible operating platform for narrow space | |
CN206088920U (en) | Construction scaffold | |
CN105226560B (en) | A kind of crossing frame and its construction method | |
CN202864749U (en) | Stretching arm type crane | |
CN215407311U (en) | A protective structure for climbing frame group seam department | |
CN103422662A (en) | Integral mobile construction platform for cast-in-place of elevator shaft and method for using same | |
CN209369308U (en) | A kind of climbing frame wall-attached supporting seat | |
CN203878964U (en) | Attached lifting construction platform obstacle-crossing structure | |
CN203097248U (en) | Integral type flexible scaffold | |
CN203769305U (en) | Formwork overturning passage plate of steel platform | |
CN205558915U (en) | Portable operation device | |
CN107587711A (en) | A kind of regularization assembled overhanging protection canopy and its assembly method | |
JP5456201B1 (en) | Truss type tower construction / repair work tethering device and truss type steel tower construction / repair method using moving lifting scaffold using the tethering device | |
CN107130786B (en) | Construction lifting platform | |
CN203430008U (en) | Integrally movable type construction platform for cast-in-situ of elevator shaft | |
CN102817327A (en) | Cat ladder device for steel tube arch bridge operation platform and building method of cat ladder device | |
CN207553565U (en) | A kind of crosshead of truss | |
CN204059897U (en) | Truss | |
CN208055892U (en) | A kind of multifunctional dolly for the installation of bridge drainpipe and guardrail repairing | |
CN211691392U (en) | Climbing frame | |
CN203878957U (en) | Protective screen module unit | |
CN103643790B (en) | It is applicable to the self-crawling type operating platform of colossal column | |
CN205187703U (en) | Swing arm tower machine triangle -shaped guardrail |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |