CN106988521B - A kind of integrated form climbing frame - Google Patents

A kind of integrated form climbing frame Download PDF

Info

Publication number
CN106988521B
CN106988521B CN201710311102.9A CN201710311102A CN106988521B CN 106988521 B CN106988521 B CN 106988521B CN 201710311102 A CN201710311102 A CN 201710311102A CN 106988521 B CN106988521 B CN 106988521B
Authority
CN
China
Prior art keywords
frame
keel
drawbar
main frame
integrated form
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710311102.9A
Other languages
Chinese (zh)
Other versions
CN106988521A (en
Inventor
李宇白
张利伟
于传东
王帆
王拼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Tianrun Construction Co Ltd
Original Assignee
Beijing Tianrun Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Tianrun Construction Co Ltd filed Critical Beijing Tianrun Construction Co Ltd
Priority to CN201710311102.9A priority Critical patent/CN106988521B/en
Publication of CN106988521A publication Critical patent/CN106988521A/en
Application granted granted Critical
Publication of CN106988521B publication Critical patent/CN106988521B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms

Abstract

The invention discloses a kind of integrated form climbing frames, belong to technical field of engineering equipment, design with integrated form climbing frame frame body in the presence of conflicting to solve the problems, such as to construct tower crane at present in attaching process.Integrated form climbing frame provided by the invention includes main frame, sub-frame, steel feet plate and more drawstrings, wherein one end of sub-frame and main frame are hinged, and the other end is overlapped between main frame and can fix under the action of drawstring with main frame;Steel feet plate is located in sub-frame, and one end of steel feet plate and main frame are hinged, and the other end is overlapped between sub-frame and can fix under the action of drawstring with main frame.The integrated form climbing frame of the invention tower crane that solves the problems, such as to construct at present exists with integrated form climbing frame frame body in attaching process and conflicts, and reduces tower crane attachment quantity, avoids the waste of material, saved construction cost, structure is simple, securely and reliably.

Description

A kind of integrated form climbing frame
Technical field
The present invention relates to technical field of engineering equipment, and in particular to a kind of integrated form climbing frame
Background technique
Climbing frame is called hoisting frame, and it is main several to be divided into fluid pressure type, electrodynamic type, manpower hand pulling type etc. according to its power resources Class, it is the new type scaffold system developed in recent years, is mainly used in high-layer shear force wall formula building, can be along building up Soaring or decline.Tower crane is a kind of most common lifting equipment also known as " derrick crane " on construction site, with a section Spreading (or high) is that one kind must can not on building site for hanging the construction raw material such as working reinforcing bar, wooden flute, concrete, steel pipe Few equipment.
Currently, there are two types of solutions for construction tower crane with collision problem existing for integrated form climbing frame frame body in attaching process Certainly mode: the first, climbing frame erection of frames tower crane is avoided, selection is in frame body with next layer of progress tower crane attachment work;The second, it is climbing The installation of tower crane attachment is carried out in frame frame body.First way has the disadvantage that additional increase adheres to together, increases attachment Quantity increases attachment number, increases the number (each top lifting height reduction) of jacking, increases construction cost, slows down Construction speed;The second way, which has the disadvantage that, need to temporarily damage monolithic frame body steel feet plate and stamped steel expanded metals, damage material Material, difficulty of construction is big and there are security risks.
Summary of the invention
The purpose of the present invention is to propose to a kind of integrated form climbing frame, it is in attaching process and integrated to solve construction tower crane at present There is conflict in formula climbing frame frame body.
To achieve this purpose, the present invention adopts the following technical scheme:
A kind of integrated form climbing frame, including main frame, sub-frame, steel feet plate and more drawstrings, wherein the sub-frame One end and the main frame are hinged, the other end be overlapped between the main frame and can under the action of the drawstring with the master Frame is fixed;The steel feet plate is located in the sub-frame, and one end of the steel feet plate and the main frame are hinged, and the other end is taken It connects between the sub-frame and can be fixed under the action of the drawstring with the main frame.
As a preferred solution of the present invention, the main frame includes two groups of keel components being oppositely arranged, every group of institute Stating keel component includes two main joists being vertically oppositely arranged.
As a preferred solution of the present invention, in keel component described in every group, two institutes being vertically oppositely arranged It states and is equipped with drawbar between main joist.
As a preferred solution of the present invention, the sub-frame includes two overlap joint keel, each overlap joint keel One end pass through shaft and connect with the main joist, the other end is overlapped on the drawbar.
As a preferred solution of the present invention, one end of the overlap joint keel is formed on the face towards the drawbar First notch, the overlap joint keel can be clamped on the drawbar by first notch.
As a preferred solution of the present invention, two drawbars are also worn respectively between two overlap joint keel, The steel feet plate can be accommodated in the frame that the every drawbar and two overlap joint keel are formed.
As a preferred solution of the present invention, the steel feet plate includes two, and one end of each steel feet plate is logical It crosses hinge to connect with the main joist, the other end is formed with the second notch on the face towards the drawbar, passes through described second Notch is clamped on the drawbar.
As a preferred solution of the present invention, it is additionally provided on the main frame multiple for fixing the drawstring of the drawstring Fixed part.
As a preferred solution of the present invention, the drawbar is bolt.
As a preferred solution of the present invention, the overlap joint keel are L-shaped.
The invention has the benefit that
Integrated form climbing frame of the invention includes main frame, sub-frame, steel feet plate and more drawstrings, one end of sub-frame Hinged with main frame, the other end is overlapped between main frame and can fix under the action of drawstring with main frame;Steel feet plate is located at In sub-frame, one end of steel feet plate and main frame are hinged, the other end be overlapped between sub-frame and can under the action of drawstring with Main frame is fixed, which has used for reference traditional suspension bridge working principle, transform the steel feet plate of traditional climbing frame as bridging type steel feet plate, It perfectly solves the problems, such as tower crane attachment in the positional relationship of climbing frame frame body, avoids the waste of material, saved and be constructed into This, accelerates construction speed, structure is simple, securely and reliably.
Detailed description of the invention
Fig. 1 is the structural schematic diagram for the integrated form climbing frame that the preferred embodiment of the present invention provides.
In the figure, it is marked as
1, steel feet plate;2, drawstring;3, main joist;4, keel are overlapped;5, the first notch;6, the second notch.
Specific embodiment
To further illustrate the technical scheme of the present invention below with reference to the accompanying drawings and specific embodiments.
Preferred embodiment:
This preferred embodiment discloses a kind of integrated form climbing frame.As shown in Figure 1, integrated form climbing frame include main frame, sub-frame, Steel feet plate 1 and more drawstrings 2 use for reference traditional suspension bridge principle for the steel feet plate of traditional climbing frame and transform bridging type steel feet plate as.
Main frame includes two groups of keel components being oppositely arranged, and every group of keel component includes two and vertically set relatively The main joist 3 set.In every group of keel component, drawbar is equipped between two main joists 3 being vertically oppositely arranged.This reality It applies in example, drawbar is preferably M16mm high-strength bolt.
Sub-frame includes two overlap joint keel 4, and overlap joint keel 4 are L-shaped, having a size of 80*40mm, each overlap joint keel 4 One end passes through shaft and connect with main joist 3, and the other end is overlapped on drawbar.One end of keel 4 is overlapped in the face towards drawbar On be formed with the first notch 5, overlap joint keel 4 can pass through the first notch 5 and be clamped on drawbar.
Also two drawbars, the frame that every drawbar and two overlap joint keel 4 are formed are worn between two overlap joint keel 4 respectively It is interior to accommodate a steel feet plate 1.Steel feet plate 1 includes two 3mm thickness, and the steel plate of 40*20mm is respectively received in drawbar and takes with two Building sequence bone 4 formed two frames in, one end of each steel feet plate 1 passes through hinge and connect with main joist 3, the other end towards It is formed with the second notch 6 on the face of drawbar, is clamped on drawbar by the second notch 6.
In the present embodiment, 1 one end of steel feet plate is hinged by hinge and main joist 3, overlap joint keel 4 by shaft or drawbar with Main joist 3 connects, and the position where hinge is higher than the position where shaft or drawbar, so that steel feet plate 1 at least partly can It is overlapped on the shaft or drawbar, structure is more safe and stable, reliable.
Multiple drawstring fixed parts for fixed pulling rope 2 are additionally provided on main frame, wherein drawstring 2 is the drawing of 4mm galvanized wire Rope.In two groups of keel components, wherein two groups of drawstrings 2 are fixed on two of the one group main joists 3 being vertically oppositely arranged, one Group drawstring 2 is for lifting two overlap joint keel 4, and another group of drawstring 2 is for lifting a steel feet plate 1;In another group of keel component Two main joists 3 being vertically oppositely arranged on be fixed with one group of drawstring 2, for lifting another steel feet plate 1.
Climbing frame step pitch is 1500mm, span 1500mm.Climbing frame promoted when, steel feet plate 1 under the promotion of drawstring 2 with main dragon Bone 3 is fixed, and it is also fixed with main joist 3 under the promotion of drawstring 2 to overlap keel 4.Two steel feet plates 1 are designed as putting up a bridge by the climbing frame Steel feet plate 1 can be fixed on main joist 3 by formula structure, tower crane attachment when climbing frame frame body, damage steel feet plate 1 without interim, It perfectly solves the problems, such as tower crane attachment in the positional relationship of climbing frame frame body, avoids the waste of material, saved and be constructed into This, accelerates construction speed, structure is simple, securely and reliably.
Finally, it is to be noted that, herein, relational terms such as first and second and the like be used merely to by One entity or operation are distinguished with another entity or operation, without necessarily requiring or implying these entities or operation Between there are any actual relationship or orders.Moreover, the terms "include", "comprise" or its any other variant meaning Covering non-exclusive inclusion, so that the process, method, article or equipment for including a series of elements not only includes that A little elements, but also including other elements that are not explicitly listed, or further include for this process, method, article or The intrinsic element of equipment.In the absence of more restrictions, the element limited by sentence "including a ...", is not arranged Except there is also other identical elements in the process, method, article or apparatus that includes the element.
It is the embodiment provided in conjunction with attached drawing above, is only to realize preferred embodiment of the invention rather than its limitations, it is any It modifies to a specific embodiment of the invention or some technical features can be equivalently replaced, without departing from skill of the present invention The spirit of art scheme should all cover within the scope of the technical scheme claimed by the invention.Protection scope of the present invention is also wrapped It includes those skilled in the art and does not make the creative labor the thinkable any alternate embodiments of institute.

Claims (4)

1. a kind of integrated form climbing frame, which is characterized in that including main frame, sub-frame, steel feet plate (1) and more drawstrings (2), In,
One end of the sub-frame and the main frame are hinged, and the other end is overlapped between the main frame and can be in the drawstring (2) it is fixed under the action of with the main frame;
The steel feet plate (1) is located in the sub-frame, and one end of the steel feet plate (1) and the main frame are hinged, the other end It is overlapped between the sub-frame and can be fixed under the action of the drawstring (2) with the main frame;
The main frame includes two groups of keel components being oppositely arranged, and keel component described in every group includes two vertically phases To the main joist (3) of setting;
In keel component described in every group, drawbar is equipped between two main joists (3) being vertically oppositely arranged;
The sub-frame includes two overlap joint keel (4), and one end of each overlap joint keel (4) passes through shaft and the master Keel (3) connection, the other end are overlapped on the drawbar;
One end of overlap joint keel (4) is formed with the first notch (5) on the face towards the drawbar, the overlap joint keel (4) it can be clamped on the drawbar by first notch (5);
Two drawbars, the every drawbar and two overlap joints are also worn respectively between two overlap joint keel (4) The steel feet plate (1) can be accommodated in the frame that keel (4) are formed;
The steel feet plate (1) includes two, and one end of each steel feet plate (1) passes through hinge and the main joist (3) even It connects, the other end is formed with the second notch (6) on the face towards the drawbar, is clamped on by second notch (6) described On drawbar.
2. a kind of integrated form climbing frame according to claim 1, which is characterized in that be additionally provided with multiple be used on the main frame The drawstring fixed part of the fixed drawstring (2).
3. a kind of integrated form climbing frame according to claim 1, which is characterized in that the drawbar is bolt.
4. a kind of integrated form climbing frame according to claim 1, which is characterized in that the overlap joint keel (4) are L-shaped.
CN201710311102.9A 2017-05-05 2017-05-05 A kind of integrated form climbing frame Active CN106988521B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710311102.9A CN106988521B (en) 2017-05-05 2017-05-05 A kind of integrated form climbing frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710311102.9A CN106988521B (en) 2017-05-05 2017-05-05 A kind of integrated form climbing frame

Publications (2)

Publication Number Publication Date
CN106988521A CN106988521A (en) 2017-07-28
CN106988521B true CN106988521B (en) 2019-11-22

Family

ID=59417425

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710311102.9A Active CN106988521B (en) 2017-05-05 2017-05-05 A kind of integrated form climbing frame

Country Status (1)

Country Link
CN (1) CN106988521B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007056628A (en) * 2005-08-26 2007-03-08 Teruo Nishihara Movable scaffolding
CN202831592U (en) * 2012-08-30 2013-03-27 珠海经济特区全达实业有限公司 Scaffold
CN203080894U (en) * 2012-09-28 2013-07-24 中国华冶科工集团有限公司 Building steel structure construction protector
CN203878964U (en) * 2014-04-21 2014-10-15 成都嘉泽正达科技有限公司 Attached lifting construction platform obstacle-crossing structure
CN204282796U (en) * 2014-11-05 2015-04-22 江南大学 Collapsible hanging basket
CN105201192A (en) * 2015-10-19 2015-12-30 金陵科技学院 Scaffold for interior trim

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007056628A (en) * 2005-08-26 2007-03-08 Teruo Nishihara Movable scaffolding
CN202831592U (en) * 2012-08-30 2013-03-27 珠海经济特区全达实业有限公司 Scaffold
CN203080894U (en) * 2012-09-28 2013-07-24 中国华冶科工集团有限公司 Building steel structure construction protector
CN203878964U (en) * 2014-04-21 2014-10-15 成都嘉泽正达科技有限公司 Attached lifting construction platform obstacle-crossing structure
CN204282796U (en) * 2014-11-05 2015-04-22 江南大学 Collapsible hanging basket
CN105201192A (en) * 2015-10-19 2015-12-30 金陵科技学院 Scaffold for interior trim

Also Published As

Publication number Publication date
CN106988521A (en) 2017-07-28

Similar Documents

Publication Publication Date Title
CN101736893B (en) Overhanging type scaffold supporting system
CN202227476U (en) High-altitude large-span overhung corridor-type reinforced concrete structure
CN201007041Y (en) Concrete prefabricated element hanging connecting mechanism
CN100351482C (en) Protective frame special for construction of building main body
CN102444203A (en) High-altitude long-span overhanging corridor type reinforced concrete structure and construction method
CN102900021B (en) Split mounting type bridge wet joint construction method
CN104453197A (en) High-altitude large-cantilever concrete structure structural steel supporting platform
CN102251483B (en) Construction method for hoisting concrete-filled steel tube lattice bridge pier through self-lifting attached crane
CN206903022U (en) A kind of steel bar truss floor support plate
CN206692235U (en) A kind of steel structure dome lifts by crane erecting device
CN106400691A (en) Integrated construction process for anti-collision wall formwork
CN106429883A (en) Tower crane foundation used for bridge construction
CN108560895A (en) A kind of adjustable type elevator shaft operating platform and its erection method
CN106758862A (en) Lattice tubular tower and frame pacifies, tears platform open
CN106988521B (en) A kind of integrated form climbing frame
CN103552911B (en) A kind of movable boom hoisting and the construction installation method of use thereof
CN210976552U (en) Foldable operation platform device in elevator shaft
CN105040592B (en) A kind of horizontal drawing cable bridge and its erection method
CN209244242U (en) A kind of fixed device of half tool-type U-bolt of the shaped steel suspension scaffolding
CN109457814B (en) Construction method for top cover of high-rise and large-diameter building based on Bailey truss structure
CN102605945B (en) Manufacturing method of big wood formwork
CN214271715U (en) Special die block of wet joint construction of iron bridge floor is striden to public
CN204982628U (en) Horizontal drawing cable bridge
CN210767248U (en) Connecting structure of steel plate concrete composite shear wall and concrete floor wrapped outside
CN106245530A (en) A kind of universal rod body CABLEWAY ERECTION SYSTEM removes engineering method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant