CN203826781U - PT2 power distribution station - Google Patents
PT2 power distribution station Download PDFInfo
- Publication number
- CN203826781U CN203826781U CN201420149737.5U CN201420149737U CN203826781U CN 203826781 U CN203826781 U CN 203826781U CN 201420149737 U CN201420149737 U CN 201420149737U CN 203826781 U CN203826781 U CN 203826781U
- Authority
- CN
- China
- Prior art keywords
- transformer
- switch
- low
- section
- distribution station
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Patch Boards (AREA)
Abstract
本实用新型提供的PT2型配电站,一路10kV进线通过一套SF6负荷闸刀连通1号变压器,转换成0.4kV后为连接在1号变压器之后的0.4kV一段母线及其多条出线供电;另一路10kV进线通过另一套SF6负荷闸刀连通2号变压器,转换成0.4kV后为连接在2号变压器之后的0.4kV二段母线及其多条出线供电;所述一段母线与二段母线之间通过分段开关连接。本实用新型在不改变原有规模和主接线方式的前提下,对配电站一次设备进行更换,有利于提高设备的健康水平和安全运行水平,减少检修、维护的工作量,提高供电可靠性。
In the PT2 distribution station provided by the utility model, one 10kV incoming line is connected to the No. 1 transformer through a set of SF6 load switch, and after being converted into 0.4kV, it supplies power for the 0.4kV section of the busbar connected behind the No. 1 transformer and its multiple outgoing lines. ; The other 10kV incoming line is connected to the No. 2 transformer through another set of SF6 load switch blades, and after being converted into 0.4kV, it supplies power for the 0.4kV second-section bus and its multiple outlets connected after the No. 2 transformer; The section busbars are connected through section switches. The utility model replaces the primary equipment of the distribution station without changing the original scale and the main wiring mode, which is beneficial to improving the health level and safe operation level of the equipment, reducing the workload of inspection and maintenance, and improving the reliability of power supply .
Description
技术领域 technical field
本实用新型涉及电力配电领域,特别涉及一种PT2型配电站。 The utility model relates to the field of power distribution, in particular to a PT2 type distribution station. the
背景技术 Background technique
向商业区及居民住宅供电时,用户一般对供电可靠性要求比较高。在90年代投运的一些配电站,主接线采用两进两出带分段的方式,图1、图2给出了两种示例情况。 When supplying power to commercial areas and residential buildings, users generally have relatively high requirements for power supply reliability. In some substations put into operation in the 1990s, the main wiring adopts a two-input and two-outlet belt segment method. Figure 1 and Figure 2 show two examples.
如图1所示,一路10kV进线经开关K1、开关K11、熔断器连接至1号变压器,进而为连接于1号变压器之后的0.4kV一段母线及其六条出线供电;另一路10kV进线经开关K2、开关K21、熔断器连接至2号变压器,进而为连接于2号变压器之后的0.4kV二段母线及其六条出线供电。还设置了带有开关K3、开关K4的线缆来连接这两路10kV进线。 As shown in Figure 1, one 10kV incoming line is connected to No. 1 transformer through switch K1, switch K11, and fuse, and then supplies power to a 0.4kV section of busbar connected to No. 1 transformer and its six outgoing lines; the other 10kV incoming line passes through Switch K2, switch K21, and fuses are connected to No. 2 transformer, and then supply power to the 0.4kV second-section busbar and its six outgoing lines connected after No. 2 transformer. Cables with switch K3 and switch K4 are also set up to connect the two 10kV incoming lines.
如图2所示在0.4kV侧的器件连接结构与上述相似,而10kV侧的一路进线经开关S1、开关S11连接至1号变压器,10kV侧的另一路进线经开关S2、开关S21连接至2号变压器,10kV一段、二段母线通过分段开关S3连接,这两个母线处还分别设置有避雷器。 As shown in Figure 2, the device connection structure on the 0.4kV side is similar to the above, and one incoming line on the 10kV side is connected to No. 1 transformer through switch S1 and switch S11, and the other incoming line on the 10kV side is connected through switch S2 and switch S21 To the No. 2 transformer, the 10kV first and second busbars are connected through the section switch S3, and the two busbars are respectively equipped with lightning arresters.
图3是现有配电站的平面布置图,在低压室内设两台低压进线柜1、六台低压出线柜2、两台电容柜3和一台低压分段柜4来放置0.4kV侧的相关设备。在高压室放置四台高压柜6,来放置上述10kV侧的相关器件。1号及2号变压器通过若干线缆连接相应的高压柜6和低压进线柜1。 Figure 3 is the layout diagram of the existing distribution station. Two low-voltage incoming cabinets 1, six low-voltage outgoing cabinets 2, two capacitor cabinets 3 and one low-voltage section cabinet 4 are installed in the low-voltage room to place the 0.4kV side related equipment. Four high-voltage cabinets 6 are placed in the high-voltage room to place the above-mentioned related devices on the 10kV side. Transformers No. 1 and No. 2 are connected to corresponding high-voltage cabinets 6 and low-voltage incoming cabinets 1 through several cables.
然而现有技术中高压侧的器件(通常使用GG1A型的高压柜实现),设备陈旧,无备品备件,供电可靠性差,难以满足日益增长的用电要求。而对商业区及居民住宅供电的配电站,往往受场地限制,难以扩大规模,改造难度大。 However, the devices on the high-voltage side in the prior art (usually implemented by GG1A high-voltage cabinets) are outdated, have no spare parts, and have poor power supply reliability, making it difficult to meet the growing demand for electricity. However, distribution stations that supply power to commercial areas and residential buildings are often limited by the site, making it difficult to expand the scale and difficult to transform.
实用新型内容 Utility model content
本实用新型的目的是提供一种PT2型配电站,在不改变原有规模和主接线方式的前提下,对配电站一次设备进行更换,以提高设备供电可靠性。 The purpose of this utility model is to provide a PT2 distribution station, which can replace the primary equipment of the distribution station without changing the original scale and main wiring mode, so as to improve the reliability of power supply of the equipment.
为了达到上述目的,本实用新型的技术方案是提供一种PT2型配电站,其包含: In order to achieve the above purpose, the technical solution of the present utility model is to provide a PT2 type power distribution station, which includes:
一路10kV进线通过一套SF6负荷闸刀连通1号变压器,转换成0.4kV后为连接在1号变压器之后的0.4kV一段母线及其多条出线供电; One 10kV incoming line is connected to the No. 1 transformer through a set of SF6 load switch, and after being converted into 0.4kV, it supplies power for a 0.4kV section of the bus connected behind the No. 1 transformer and its multiple outgoing lines;
另一路10kV进线通过另一套SF6负荷闸刀连通2号变压器,转换成0.4kV后为连接在2号变压器之后的0.4kV二段母线及其多条出线供电;所述一段母线与二段母线之间通过分段开关连接。 The other 10kV incoming line is connected to the No. 2 transformer through another set of SF6 load switch blades, and after being converted into 0.4kV, it supplies power for the 0.4kV second-section bus and its multiple outgoing lines connected after the No. 2 transformer; the first section of the bus and the second section The busbars are connected through section switches.
优选地,所述SF6负荷闸刀设置于SF6环网柜。 Preferably, the SF6 load switch is set in the SF6 ring network cabinet.
优选地,所述SF6负荷闸刀的一端通过铜母排与10kV进线连接,该SF6负荷闸刀另一端通过熔断器、电流互感器之后分两路,一路通过电容接地,另一路则连接至出线端并进一步通过出线电缆连接至1号或2号变压器。 Preferably, one end of the SF6 load switch is connected to the 10kV incoming line through a copper busbar, and the other end of the SF6 load switch is divided into two paths through a fuse and a current transformer, one path is grounded through a capacitor, and the other path is connected to The outgoing terminal is further connected to the No. 1 or No. 2 transformer through the outgoing cable.
优选地,所述SF6负荷闸刀的一端通过铜母排与10kV进线连接,该SF6负荷闸刀另一端通过电流互感器之后分三路,两路分别连接至接地的电容和避雷器,另一路连接至出线端。 Preferably, one end of the SF6 load switch is connected to the 10kV incoming line through a copper busbar, and the other end of the SF6 load switch is divided into three circuits after passing through a current transformer, two of which are respectively connected to the grounded capacitor and the lightning arrester, and the other Connect to outlet.
优选地,1号、2号变压器的中性点接地形式为直接接地;1号、2号变压器的高压侧分别安装一组避雷器。 Preferably, the neutral point grounding form of No. 1 and No. 2 transformers is direct grounding; a set of lightning arresters are respectively installed on the high voltage sides of No. 1 and No. 2 transformers.
优选地,1号变压器的低压侧通过一个配变开关连接0.4kV一段母线,该一段母线的每个出线上分别设有出线开关; Preferably, the low-voltage side of No. 1 transformer is connected to a section of 0.4kV bus through a distribution switch, and each outlet of the section of bus is respectively equipped with an outlet switch;
2号变压器的低压侧通过另一个配变开关连接0.4kV二段母线,该二段母线的每个出线上分别设有出线开关; The low-voltage side of the No. 2 transformer is connected to the 0.4kV second-section bus through another distribution transformer switch, and each outlet of the second-section bus is equipped with an outlet switch;
两组电容器通过相应的电容器开关分别连接至所述一段母线和二段母线;所述配变开关、出线开关、电容器开关是真空断路器。 Two sets of capacitors are respectively connected to the first-stage busbar and the second-stage busbar through corresponding capacitor switches; the distribution transformer switch, outlet switch, and capacitor switch are vacuum circuit breakers.
优选地,两组分别设置SF6负荷闸刀的高压柜位于高压室内; Preferably, two sets of high-voltage cabinets respectively equipped with SF6 load switch knives are located in the high-voltage chamber;
两台相应设置配变开关的低压进线柜、六台相应设置出线开关的低压出线柜、两台电容器柜、一台设置分段开关的低压分段柜位于低压室内; Two low-voltage incoming line cabinets with corresponding distribution transformer switches, six low-voltage outgoing line cabinets with corresponding outgoing line switches, two capacitor cabinets, and one low-voltage section cabinet with section switches are located in the low-voltage room;
1号、2号变压器通过相应的进出线电缆,分别接入高压室的高压柜,以及通过低压铜母线接入低压室的低压进线柜。 Transformers No. 1 and No. 2 are respectively connected to the high-voltage cabinet in the high-voltage room through corresponding incoming and outgoing cables, and connected to the low-voltage incoming cabinet in the low-voltage room through low-voltage copper bus bars.
与现有技术相比,本实用新型提供的PT2型配电站,在不改变原有规模和主接线方式的前提下,对配电站一次设备进行更换,设置SF6负荷闸刀并配备SF6报警装置,有利于提高设备的健康水平和安全运行水平,减少检修、维护的工作量,提高供电可靠性。 Compared with the existing technology, the PT2 type distribution station provided by the utility model replaces the primary equipment of the distribution station without changing the original scale and main wiring mode, and installs SF6 load switch blades and is equipped with SF6 alarm The device is conducive to improving the health level and safe operation level of the equipment, reducing the workload of inspection and maintenance, and improving the reliability of power supply.
附图说明 Description of drawings
图1、图2是现有配电站的两种电气接线示意图; Figure 1 and Figure 2 are two schematic diagrams of electrical wiring in existing distribution stations;
图3是现有配电站的平面布置图; Figure 3 is a plan layout of the existing distribution station;
图4是本实用新型所述PT2型配电站中一次主接线的电气接线示意图; Fig. 4 is a schematic diagram of the electrical wiring of the primary main wiring in the PT2 type power distribution station described in the utility model;
图5是本实用新型所述PT2型配电站的电气接线示意图; Fig. 5 is a schematic diagram of the electrical wiring of the PT2 type power distribution station described in the utility model;
图6是本实用新型配电站的平面布置图。 Fig. 6 is a layout diagram of the distribution station of the utility model.
具体实施方式 Detailed ways
如图4、5所示,本实用新型提供一种PT2型配电站(PT2型,即带2台变压器及10kV出线的环网配电站),主接线仍然采用两进两出带分段的方式。即,一路10kV进线为10kV/0.4kV 的1号变压器、0.4kV一段母线及其六条出线供电,另一路10kV进线为10kV/0.4kV 的2号变压器、0.4kV二段母线及其六条出线供电。0.4kV一段、二段母线之间通过分段开关连接。 As shown in Figures 4 and 5, the utility model provides a PT2 type distribution station (PT2 type, that is, a ring network distribution station with 2 transformers and 10kV outgoing lines), and the main wiring still adopts two-input and two-outlet belt segments The way. That is, one 10kV incoming line is powered by 10kV/0.4kV No. 1 transformer, 0.4kV busbar and its six outgoing lines, and the other 10kV incoming line is 10kV/0.4kV No. 2 transformer, 0.4kV second-section busbar and its six outgoing lines powered by. The 0.4kV first and second busbars are connected through a section switch.
两组10kV高压柜(甲、乙)位于高压室内,分别采用SF6负荷闸刀,并配置弹簧操作机构,通过负荷闸刀来连通或断开相应的10kV进线。 Two sets of 10kV high-voltage cabinets (A and B) are located in the high-voltage chamber, respectively using SF6 load switches and equipped with spring operating mechanisms to connect or disconnect the corresponding 10kV incoming lines through the load switches.
本例中,上述的10kV高压柜采用如图4所示的SF6环网柜。有两个开关柜使用以下的器件方式:其中SF6负荷闸刀的一端通过铜母排与10kV进线连接,该SF6负荷闸刀另一端通过熔断器、电流互感器后一路通过电容接地,另一路则连接至出线端,进而可以通过出线电缆连接至1号或2号变压器;各开关柜内还设置有SF6压力指示器、电容电压指示器、短路故障指示器、三位置开关辅助触点、气体压力辅助触点、熔断器辅助触点,等。 In this example, the above-mentioned 10kV high-voltage cabinet adopts the SF6 ring network cabinet as shown in Figure 4. There are two switchgears using the following devices: one end of the SF6 load switch is connected to the 10kV incoming line through a copper busbar, the other end of the SF6 load switch is grounded through a capacitor through a fuse and a current transformer, and the other Then it is connected to the outlet terminal, and then can be connected to No. 1 or No. 2 transformer through the outlet cable; each switch cabinet is also equipped with SF6 pressure indicator, capacitor voltage indicator, short circuit fault indicator, three-position switch auxiliary contact, gas Pressure auxiliary contacts, fuse auxiliary contacts, etc.
还有四个开关柜中使用以下的另一种器件布置方式:SF6负荷闸刀通过电流互感器后分别连接至出线端以及接地的电容和避雷器,可以通过出线端连接变压器,或者与其他开关柜中的器件配合连接以满足不同的接线需要(比如上述前一种方式布置的SF6负荷闸刀作为开关K11、K12或S11、S21,后一种方式布置的SF6负荷闸刀作为方框内的其他开关,相互配合来构建图1或图2所示的接线方案,等等)。 There are four switchgears using the following another device arrangement: SF6 load switch is connected to the outlet terminal and grounded capacitor and lightning arrester after passing through the current transformer, and can be connected to the transformer through the outlet terminal, or connected to other switch cabinets The devices in the device are matched and connected to meet different wiring needs (for example, the SF6 load switch blades arranged in the above-mentioned way are used as switches K11, K12 or S11, S21, and the SF6 load switch blades arranged in the latter way are used as other switches in the box. switch, cooperate with each other to construct the wiring scheme shown in Figure 1 or Figure 2, etc.).
本期短路电流水平参考前期设备进行选择,即10kV短路电流水平按20kA考虑。优选负荷闸刀的参数如下:额定电压12 kV、额定电流630 A、额定断路容量346 MVA、额定开断电流20 kA、动稳定开断电流峰值50 kA、4秒热稳定电流20 kA。 The short-circuit current level of this period is selected with reference to the previous equipment, that is, the short-circuit current level of 10kV is considered as 20kA. The parameters of the optimal load switch knife are as follows: rated voltage 12 kV, rated current 630 A, rated breaking capacity 346 MVA, rated breaking current 20 kA, dynamic stable breaking current peak value 50 kA, 4-second thermal stable current 20 kA.
另外,结合一次设备改造,对相应的进出线电缆做了改接,均使用阻燃电缆。例如,在10kV侧进线采用ZA-YJV-8.7/10-3X70电缆,10kV配变出线采用ZA-YJV-8.7/10-3X70电缆。各仓位一次设备接地使用5*40扁铁,并与室内接地干线相连。 In addition, combined with an equipment transformation, the corresponding incoming and outgoing cables were reconnected, and flame-retardant cables were used. For example, ZA-YJV-8.7/10-3X70 cable is used for the incoming line on the 10kV side, and ZA-YJV-8.7/10-3X70 cable is used for the outgoing line of the 10kV distribution transformer. 5*40 flat iron is used for the grounding of the primary equipment in each position, and is connected to the indoor grounding trunk line.
1号变压器和2号变压器是两台10kV/0.4kV变压器,分别位于1号、2号配变室,这两台变压器分别将各自10kV进线电压转变为0.4kV输出,变压器中性点接地形式为直接接地。1号、2号变压器的高压侧各安装一组避雷器,起防雷作用。 Transformer No. 1 and Transformer No. 2 are two 10kV/0.4kV transformers, which are located in No. 1 and No. 2 distribution room respectively. These two transformers respectively transform their 10kV incoming line voltage into 0.4kV output, and the neutral point of the transformer is grounded. for direct grounding. A set of lightning arresters are respectively installed on the high-voltage side of the No. 1 and No. 2 transformers to play the role of lightning protection.
所有0.4kV侧的开关均位于0.4kV开关室内,均采用真空断路器,每个开关可连通或断开相应出线或其供电部分。本实用新型的该配电站中共设有2个配变开关、12个出线开关、2个电容器开关、1个0.4kV分段开关。 All switches on the 0.4kV side are located in the 0.4kV switch room, and all use vacuum circuit breakers. Each switch can connect or disconnect the corresponding outgoing line or its power supply part. The power distribution station of the utility model is provided with 2 distribution transformer switches, 12 outlet switches, 2 capacitor switches, and 1 0.4kV section switch.
即,1号变压器的0.4kV低压侧通过配变开关Q31连接0.4kV一段母线,下设6个出线开关Q41;2号变压器的0.4kV低压侧通过配变开关Q32连接0.4kV二段母线,下设另外6个出线开关Q42;0.4kV一段、二段母线之间设分段开关Q5。 That is, the 0.4kV low-voltage side of No. 1 transformer is connected to the 0.4kV first-section busbar through the distribution transformer switch Q31, and there are 6 outlet switches Q41 under it; the 0.4kV low-voltage side of No. 2 transformer is connected to the 0.4kV second-section busbar through the distribution transformer switch Q32. Set another 6 outgoing line switches Q42; 0.4kV section 1 and section 2 busbars set section switch Q5.
两组电容器起无功补偿作用,分别安装在两个电容器柜内,通过相应的电容器开关分别连接0.4kV一段、二段母线。 The two sets of capacitors play the role of reactive power compensation and are installed in two capacitor cabinets respectively, and are connected to the 0.4kV first and second busbars through corresponding capacitor switches.
如图6所示是本实用新型配电站的平面布置图,两组共六台10kV高压柜6(SF6环网柜)位于高压室内。两台相应设置配变开关的0.4kV低压进线柜1(如GGD2-02)、六台相应设置出线开关的0.4kV低压出线柜2(如GGD2-38)、两台电容器柜(如GGD)3、一台设置0.4kV分段开关的低压分段柜(如GGD2-02)及若干低压铜母线5(TMY-100×10)位于低压室内。1号变压器及2号变压器各自通过进出电缆连接至高压室和低压室内的相应设备。 As shown in Figure 6 is the layout of the distribution station of the utility model, two groups of six 10kV high-voltage cabinets 6 (SF6 ring network cabinets) are located in the high-voltage room. Two 0.4kV low-voltage incoming line cabinets 1 (such as GGD2-02) with corresponding distribution transformer switches, six 0.4kV low-voltage outgoing line cabinets 2 (such as GGD2-38) with corresponding outgoing line switches, and two capacitor cabinets (such as GGD) 3. A low-voltage section cabinet (such as GGD2-02) with a 0.4kV section switch and several low-voltage copper busbars 5 (TMY-100×10) are located in the low-voltage room. Transformer No. 1 and Transformer No. 2 are respectively connected to corresponding equipment in the high-voltage room and the low-voltage room through incoming and outgoing cables.
根据站址的污秽级别,本期工程设备的爬电比距按Ⅲ级进行选择,即10V及以下设备爬电比距户外按31mm/kV进行考虑,户内按25mm/kV考虑。在新增各配电装置室与保护屏屏柜下方,以及电缆改造、新增时所涉及的电缆夹层、穿墙楼板、墙壁、柜、盘处所有电缆孔洞和缝隙进行防火封堵。且将封堵处两侧各1m范围内的电缆外皮采用防火包带粘贴或涂防火涂料。 According to the pollution level of the station site, the creepage ratio distance of the project equipment in this phase is selected according to Class III, that is, the creepage ratio distance of equipment with 10V and below is considered as 31mm/kV outdoors and 25mm/kV indoors. Fireproof sealing shall be carried out at all cable holes and gaps at the bottom of newly added power distribution device rooms and protective screen cabinets, as well as at cable interlayers, wall-through floors, walls, cabinets, and panels involved in cable renovation and new additions. And the cable sheath within 1m on both sides of the blockage shall be pasted with fireproof tape or coated with fireproof paint.
如图3、图6所示,本例中可以在现有站址内进行改造,无需另外征地,需对配电站高压室内的设备予以更换,而低压室内的设备及其连线布置均可以沿用原先方式,有效减少工作量。 As shown in Figure 3 and Figure 6, in this example, the existing station site can be rebuilt without additional land acquisition, and the equipment in the high-voltage room of the distribution station needs to be replaced, while the equipment in the low-voltage room and its connection layout can be Continue to use the original method to effectively reduce the workload.
综上所述,本实用新型提供的PT2型配电站,在不改变原有规模和主接线方式的前提下,对配电站一次设备进行更换,设置SF6负荷闸刀并配备SF6报警装置,有利于提高设备的健康水平和安全运行水平,减少检修、维护的工作量,提高供电可靠性。 To sum up, the PT2 distribution station provided by the utility model replaces the primary equipment of the distribution station without changing the original scale and main wiring mode, and installs SF6 load switch blades and SF6 alarm devices. It is conducive to improving the health level and safe operation level of equipment, reducing the workload of inspection and maintenance, and improving the reliability of power supply.
尽管本实用新型的内容已经通过上述优选实施例作了详细介绍,但应当认识到上述的描述不应被认为是对本实用新型的限制。在本领域技术人员阅读了上述内容后,对于本实用新型的多种修改和替代都将是显而易见的。因此,本实用新型的保护范围应由所附的权利要求来限定。 Although the content of the present invention has been described in detail through the above preferred embodiments, it should be recognized that the above description should not be considered as a limitation of the present invention. Various modifications and substitutions of the present utility model will be obvious to those skilled in the art after reading the above content. Therefore, the protection scope of the present utility model should be defined by the appended claims.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201420149737.5U CN203826781U (en) | 2014-03-31 | 2014-03-31 | PT2 power distribution station |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201420149737.5U CN203826781U (en) | 2014-03-31 | 2014-03-31 | PT2 power distribution station |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN203826781U true CN203826781U (en) | 2014-09-10 |
Family
ID=51482246
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201420149737.5U Expired - Lifetime CN203826781U (en) | 2014-03-31 | 2014-03-31 | PT2 power distribution station |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN203826781U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103840380A (en) * | 2014-03-31 | 2014-06-04 | 国网上海市电力公司 | PT2 type power distribution station |
-
2014
- 2014-03-31 CN CN201420149737.5U patent/CN203826781U/en not_active Expired - Lifetime
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103840380A (en) * | 2014-03-31 | 2014-06-04 | 国网上海市电力公司 | PT2 type power distribution station |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101662132B (en) | 110kV/220kV voltage level composite apparatus and application thereof | |
| CN101577400A (en) | Chamber type liaison transforming plant reduced by 0.4kV from 20kV/10KV | |
| CN103840380A (en) | PT2 type power distribution station | |
| CN103840378A (en) | Improved PT1 type power distribution station | |
| CN203813223U (en) | Integrated automation transformer substation | |
| CN203826781U (en) | PT2 power distribution station | |
| CN104037622A (en) | Two-in and two-out sectionalized power distribution station | |
| CN203813222U (en) | Two-input two-output PT2 power distribution station with subsections | |
| CN203813217U (en) | Improved PT1 type power distribution station | |
| CN204230846U (en) | A kind of low-voltage cable junction box wiring system | |
| CN203813221U (en) | PT1 type power distribution station | |
| CN205029223U (en) | Movable type transformer station | |
| CN103812086A (en) | High voltage electromotor protection system | |
| CN105794059B (en) | Switchgear with busbar-side voltage transformers or surge arresters | |
| CN204424772U (en) | Two main transformer four segmentation integrated automation converting stations | |
| CN201556842U (en) | Low voltage comprehensive protection compensation metering box | |
| CN110165563A (en) | A kind of 220kV HGIS power distribution equipment applied to substation's single-trunk segmental wiring | |
| CN103840379A (en) | PT1 type power distribution station | |
| CN208093426U (en) | A kind of interlock of outdoor vacuum circuit breaker | |
| CN205160080U (en) | Intelligent low tension circuit of drawer type combination | |
| CN204290144U (en) | A kind of compact switch cabinet | |
| CN104682224A (en) | Fast-moving power distribution integral device | |
| CN202042811U (en) | Switch type 10KV (kilovolt) temporary box type power transformation equipment with outlets capacity not larger than 800KVA (kilovolt ampere) | |
| CN207650286U (en) | It stands with change high-low pressure same period line loss measuring equipment | |
| CN217956508U (en) | Large-capacity vehicle-mounted movable substation |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CX01 | Expiry of patent term |
Granted publication date: 20140910 |
|
| CX01 | Expiry of patent term |