CN203813222U - Two-input two-output PT2 power distribution station with subsections - Google Patents
Two-input two-output PT2 power distribution station with subsections Download PDFInfo
- Publication number
- CN203813222U CN203813222U CN201420149736.0U CN201420149736U CN203813222U CN 203813222 U CN203813222 U CN 203813222U CN 201420149736 U CN201420149736 U CN 201420149736U CN 203813222 U CN203813222 U CN 203813222U
- Authority
- CN
- China
- Prior art keywords
- switch
- section
- bus
- distribution station
- power distribution
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Patch Boards (AREA)
Abstract
Description
技术领域 technical field
本实用新型涉及电力配电领域,特别涉及一种两进两出带分段的PT2型配电站。 The utility model relates to the field of electric power distribution, in particular to a PT2 type distribution station with two inputs and two outputs with segments. the
背景技术 Background technique
向商业区及居民住宅供电时,用户一般对供电可靠性要求比较高。在90年代投运的一些配电站,主接线采用两进两出带分段的方式。 When supplying power to commercial areas and residential buildings, users generally have relatively high requirements for power supply reliability. In some distribution substations put into operation in the 1990s, the main wiring adopts a two-input and two-outlet mode with segments.
如图1所示,一路10kV进线经开关S1、开关S11连接至1号变压器,另一路10kV进线经开关S2、开关S21连接至2号变压器,10kV一段、二段母线通过两个分段开关S3及引线连接。10kV一、二段母线处及1号、2号变压器的10kV进线侧分别设置有避雷器。之后,1号变压器为通过开关S14与之连接的0.4kV一段母线及其六条出线供电,2号变压器为通过开关S24与之连接的0.4kV二段母线及其六条出线供电;0.4kV一段、二段母线通过分段开关S31及引线连接;1号、2号0.4kV电容器通过各自的电容器开关分别连接至0.4kV一段、二段母线。 As shown in Figure 1, one 10kV incoming line is connected to No. 1 transformer through switch S1 and switch S11, and the other 10kV incoming line is connected to No. 2 transformer through switch S2 and switch S21. The 10kV first-stage and second-stage busbars pass through two sections Switch S3 and lead wire connection. Surge arresters are installed at the 10kV first and second section busbars and the 10kV incoming line sides of No. 1 and No. 2 transformers. Afterwards, No. 1 transformer supplies power to the 0.4kV first-stage bus and its six outgoing lines connected to it through switch S14, and No. 2 transformer supplies power to the 0.4kV second-stage bus and its six outgoing lines connected to it through switch S24; 0.4kV The section bus is connected through the section switch S31 and lead wires; No. 1 and No. 2 0.4kV capacitors are respectively connected to the 0.4kV section one and section two busbars through their respective capacitor switches.
图2是现有配电站的平面布置图,在低压室内设两台低压进线柜1、六台低压出线柜2、两台电容柜3和一台低压分段柜4来放置0.4kV侧的相关设备。在高压室放置四台高压柜6,来放置上述10kV侧的相关器件。1号及2号变压器通过若干线缆连接相应的高压柜6和低压进线柜1。 Figure 2 is the layout diagram of the existing distribution station. Two low-voltage incoming cabinets 1, six low-voltage outgoing cabinets 2, two capacitor cabinets 3 and one low-voltage section cabinet 4 are installed in the low-voltage room to place the 0.4kV side related equipment. Four high-voltage cabinets 6 are placed in the high-voltage room to place the above-mentioned related devices on the 10kV side. Transformers No. 1 and No. 2 are connected to corresponding high-voltage cabinets 6 and low-voltage incoming cabinets 1 through several cables.
然而,上述现有的配电站中设备陈旧(通常使用GG1A型的高压柜和PGL的低压柜),无备品备件,供电可靠性差,难以满足日益增长的用电要求。而对商业区及居民住宅供电的配电站,往往受场地限制,难以扩大规模,改造难度大。 However, the equipment in the above-mentioned existing distribution substations is outdated (usually using GG1A high-voltage cabinets and PGL low-voltage cabinets), there are no spare parts, and the reliability of power supply is poor, so it is difficult to meet the growing demand for electricity. However, distribution stations that supply power to commercial areas and residential buildings are often limited by the site, making it difficult to expand the scale and difficult to transform.
实用新型内容 Utility model content
本实用新型的目的是提供一种两进两出带分段的PT2型配电站,在不改变原有规模和主接线方式的前提下,对配电站一次设备进行更换,以提高设备供电可靠性。 The purpose of this utility model is to provide a PT2-type distribution station with two inlets and two outlets with segments. Under the premise of not changing the original scale and main wiring mode, the primary equipment of the distribution station can be replaced to improve the power supply of the equipment. reliability.
为了达到上述目的,本实用新型的技术方案是提供一种两进两出带分段的PT2型配电站,其包含: In order to achieve the above purpose, the technical solution of the present utility model is to provide a PT2-type power distribution station with two inputs and two outputs, which includes:
一路10kV进线连通10kV一段母线,还通过一套SF6负荷闸刀连通1号变压器,转换成0.4kV后为通过一套0.4kV进线开关连接在1号变压器之后的0.4kV一段母线及其多条出线供电; One 10kV incoming line is connected to a 10kV section of busbar, and is also connected to No. 1 transformer through a set of SF6 load switch. After conversion to 0.4kV, it is connected to a 0.4kV section of busbar and its multi-section after No. 1 transformer through a set of 0.4kV incoming line switch. outlet power supply;
另一路10kV进线连通10kV二段母线,还通过另一套SF6负荷闸刀连通2号变压器,转换成0.4kV后为通过另一套0.4kV进线开关连接在2号变压器之后的0.4kV二段母线及其多条出线供电; Another 10kV incoming line is connected to the 10kV second-section busbar, and it is also connected to the No. 2 transformer through another set of SF6 load switch. Segment busbar and its multiple outgoing lines supply power;
所述10kV一段母线与10kV二段母线之间通过10kV分段开关连接;所述0.4kV一段母线与0.4kV二段母线之间通过0.4kV分段开关连接。 The first 10kV busbar is connected to the second 10kV busbar through a 10kV sectional switch; the first 0.4kV busbar is connected to the second 0.4kV busbar through a 0.4kV sectional switch.
优选地,所述SF6负荷闸刀设置于SF6环网柜; Preferably, the SF6 load switch is set in the SF6 ring network cabinet;
所述0.4kV进线开关设置于GGD柜。 The 0.4kV incoming line switch is set in the GGD cabinet.
优选地,所述SF6负荷闸刀的一端通过铜母排与10kV进线连接,该SF6负荷闸刀另一端通过熔断器、电流互感器之后分两路,一路通过电容接地,另一路则连接至出线端并通过出线电缆连接至1号或2号变压器。 Preferably, one end of the SF6 load switch is connected to the 10kV incoming line through a copper busbar, and the other end of the SF6 load switch is divided into two paths through a fuse and a current transformer, one path is grounded through a capacitor, and the other path is connected to Outgoing terminal and connected to No. 1 or No. 2 transformer through the outgoing cable.
优选地,所述SF6负荷闸刀的一端通过铜母排与10kV进线连接,该SF6负荷闸刀另一端通过电流互感器之后分三路,两路分别连接至接地的电容和避雷器,另一路连接至出线端。 Preferably, one end of the SF6 load switch is connected to the 10kV incoming line through a copper busbar, and the other end of the SF6 load switch is divided into three circuits after passing through a current transformer, two of which are respectively connected to the grounded capacitor and the lightning arrester, and the other Connect to outlet.
优选地,1号、2号变压器的中性点接地形式为直接接地;1号、2号变压器的10kV侧分别安装一组避雷器。 Preferably, the neutral point grounding form of No. 1 and No. 2 transformers is direct grounding; a group of lightning arresters are respectively installed on the 10kV sides of No. 1 and No. 2 transformers.
优选地,0.4kV一段母线和0.4kV二段母线的每个出线上分别设有出线开关; Preferably, each outgoing line of the 0.4kV first-stage busbar and the 0.4kV second-stage busbar is respectively provided with an outlet switch;
两组电容器通过相应的电容器开关,分别连接至所述0.4kV一段母线和0.4kV二段母线;各个0.4kV进线开关、0.4kV分段开关、出线开关、电容器开关均是设置于GGD柜的真空断路器。 The two sets of capacitors are respectively connected to the 0.4kV first-stage busbar and the 0.4kV second-stage busbar through corresponding capacitor switches; each 0.4kV incoming line switch, 0.4kV sectional switch, outgoing line switch, and capacitor switch are all set in the GGD cabinet Vacuum circuit breaker.
优选地,两组分别设置SF6负荷闸刀的高压柜位于高压室内; Preferably, two sets of high-voltage cabinets respectively equipped with SF6 load switch knives are located in the high-voltage chamber;
两台相应设置0.4kV进线开关的低压进线柜、六台相应设置出线开关的低压出线柜、两台电容器柜、一台设置0.4kV分段开关的低压分段柜位于低压室内; Two low-voltage incoming cabinets with 0.4kV incoming switches, six low-voltage outgoing cabinets with outgoing switches, two capacitor cabinets, and one low-voltage section cabinet with 0.4kV section switches are located in the low-voltage room;
1号、2号变压器通过相应的进出线电缆,分别接入高压室的高压柜,以及通过低压铜母线接入低压室的低压进线柜。 Transformers No. 1 and No. 2 are respectively connected to the high-voltage cabinet in the high-voltage room through corresponding incoming and outgoing cables, and connected to the low-voltage incoming cabinet in the low-voltage room through low-voltage copper bus bars.
与现有技术相比,本实用新型提供的PT2型配电站,在不改变原有规模和电气接线方式的前提下,对配电站一次设备进行更换,设置SF6负荷闸刀并配备SF6报警装置,有利于提高设备的健康水平和安全运行水平,减少检修、维护的工作量,提高供电可靠性。 Compared with the existing technology, the PT2 type distribution station provided by the utility model replaces the primary equipment of the distribution station without changing the original scale and electrical connection mode, and is equipped with SF6 load switch knife and SF6 alarm The device is conducive to improving the health level and safe operation level of the equipment, reducing the workload of inspection and maintenance, and improving the reliability of power supply.
附图说明 Description of drawings
图1是现有配电站的电气接线示意图; Figure 1 is a schematic diagram of the electrical wiring of an existing distribution station;
图2是现有配电站的平面布置图; Figure 2 is a layout plan of the existing distribution station;
图3是本实用新型所述PT2型配电站中10kV电气接线示意图; Fig. 3 is a schematic diagram of 10kV electrical wiring in the PT2 type distribution station described in the utility model;
图4是本实用新型所述PT2型配电站中0.4kV电气接线示意图; Fig. 4 is a schematic diagram of 0.4kV electrical wiring in the PT2 type distribution station described in the utility model;
图5是本实用新型配电站的平面布置图。 Fig. 5 is a plane layout diagram of the distribution station of the present invention.
具体实施方式 Detailed ways
如图3、4所示,本实用新型提供一种PT2型配电站(PT2型,即带2台变压器及10kV出线的环网配电站),主接线仍然采用两进两出带分段的方式,0.4kV接线采用单母线分段接线方式。即,一路10kV进线为10kV/0.4kV 的1号变压器、0.4kV一段母线及其六条出线供电,另一路10kV进线为10kV/0.4kV 的2号变压器、0.4kV二段母线及其六条出线供电。10kV一段、二段母线之间通过10kV分段开关及引线连接;0.4kV一段、二段母线之间通过0.4kV分段开关及引线连接。 As shown in Figures 3 and 4, the utility model provides a PT2 type distribution station (PT2 type, that is, a ring network distribution station with 2 transformers and 10kV outgoing lines), and the main wiring still adopts two in and two out with segments The 0.4kV wiring adopts the single-bus section wiring method. That is, one 10kV incoming line is powered by 10kV/0.4kV No. 1 transformer, 0.4kV busbar and its six outgoing lines, and the other 10kV incoming line is 10kV/0.4kV No. 2 transformer, 0.4kV second-section busbar and its six outgoing lines powered by. The 10kV first and second busbars are connected through 10kV section switches and lead wires; the 0.4kV first and second section busbars are connected through 0.4kV section switch and lead wires.
两组10kV高压柜位于高压室内,分别采用SF6负荷闸刀来连通或断开相应的10kV进线。本例中,上述的10kV高压柜采用如图3所示的SF6环网柜,其中,有两个开关柜使用以下的器件方式布置:其中SF6负荷闸刀的一端通过铜母排与10kV进线连接,该SF6负荷闸刀另一端通过熔断器、电流互感器后一路通过电容接地,另一路则连接至出线端且进一步通过出线电缆连接至1号或2号变压器;各开关柜内还设置有SF6压力指示器、电容电压指示器、短路故障指示器、三位置开关辅助触点、气体压力辅助触点、熔断器辅助触点,等。 Two sets of 10kV high-voltage cabinets are located in the high-voltage room, and SF6 load switches are used to connect or disconnect the corresponding 10kV incoming lines. In this example, the above-mentioned 10kV high-voltage cabinet adopts the SF6 ring network cabinet as shown in Figure 3. Among them, two switch cabinets are arranged in the following device way: one end of the SF6 load switch is connected to the 10kV incoming line through the copper busbar connection, the other end of the SF6 load switch knife passes through the fuse and current transformer, and then one path is grounded through the capacitor, and the other path is connected to the outlet terminal and further connected to the No. 1 or No. 2 transformer through the outlet cable; each switch cabinet is also equipped with SF6 pressure indicator, capacitor voltage indicator, short circuit fault indicator, three-position switch auxiliary contact, gas pressure auxiliary contact, fuse auxiliary contact, etc.
还有四个开关柜中使用以下的另一种器件布置方式:SF6负荷闸刀通过电流互感器后分三路,分别连接至出线端以及接地的电容和避雷器,可以通过出线端连接相应的变压器,或者与其他开关柜中的器件配合连接以满足不同的接线需要(比如上述前一种方式布置的SF6负荷闸刀作为10kV进线开关,后一种方式布置的SF6负荷闸刀作为连接避雷器的开关或母线上的分段开关等等,相互配合来构建图1所示的接线方案等)。 There are four switchgears using the following another device arrangement: SF6 load switch is divided into three circuits after passing through the current transformer, and connected to the outlet terminal and grounded capacitor and lightning arrester respectively, and can be connected to the corresponding transformer through the outlet terminal , or cooperate with other devices in the switch cabinet to meet different wiring needs (for example, the SF6 load switch arranged in the former way is used as a 10kV incoming line switch, and the SF6 load switch arranged in the latter way is used as a connection to the arrester. Switches or section switches on the bus, etc., cooperate with each other to construct the wiring scheme shown in Figure 1, etc.).
本期短路电流水平参考前期设备进行选择,即10kV短路电流水平按20kA考虑。优选负荷闸刀的参数如下:额定电压12 kV、额定电流630 A、额定断路容量346 MVA、额定开断电流20 kA、动稳定开断电流峰值50 kA、4秒热稳定电流20 kA。 The short-circuit current level of this period is selected with reference to the previous equipment, that is, the short-circuit current level of 10kV is considered as 20kA. The parameters of the optimal load switch knife are as follows: rated voltage 12 kV, rated current 630 A, rated breaking capacity 346 MVA, rated breaking current 20 kA, dynamic stable breaking current peak value 50 kA, 4-second thermal stable current 20 kA.
另外,结合一次设备改造,对相应的进出线电缆做了改接,均使用阻燃电缆。例如,在10kV侧进线采用ZA-YJV-8.7/10-3X70电缆,10kV配变出线采用ZA-YJV-8.7/10-3X70电缆。各仓位一次设备接地使用5*40扁铁,并与室内接地干线相连。 In addition, combined with an equipment transformation, the corresponding incoming and outgoing cables were reconnected, and flame-retardant cables were used. For example, ZA-YJV-8.7/10-3X70 cable is used for the incoming line on the 10kV side, and ZA-YJV-8.7/10-3X70 cable is used for the outgoing line of the 10kV distribution transformer. 5*40 flat iron is used for the grounding of the primary equipment in each position, and is connected to the indoor grounding trunk line.
1号变压器和2号变压器是两台10kV/0.4kV变压器,分别位于1号、2号配变室,这两台变压器分别将各自10kV进线电压转变为0.4kV输出,变压器中性点接地形式为直接接地。1号、2号变压器的10kV进线侧各安装一组避雷器,起防雷作用。 Transformer No. 1 and Transformer No. 2 are two 10kV/0.4kV transformers, which are located in No. 1 and No. 2 distribution room respectively. These two transformers respectively transform their 10kV incoming line voltage into 0.4kV output, and the neutral point of the transformer is grounded. for direct grounding. A set of lightning arresters are respectively installed on the 10kV incoming line sides of No. 1 and No. 2 transformers to play the role of lightning protection.
如图4所示,所有0.4kV侧的开关均采用位于0.4kV开关室内的0.4kV成套开关柜,每个开关均采用真空断路器,可连通或断开相应出线或其供电部分。本实用新型的该配电站中共设有2个0.4kV进线开关、12个出线开关、2个电容器开关、1个0.4kV分段开关。 As shown in Figure 4, all switches on the 0.4kV side use a 0.4kV complete switchgear located in the 0.4kV switch room, and each switch uses a vacuum circuit breaker to connect or disconnect the corresponding outgoing line or its power supply part. The power distribution station of the utility model is provided with 2 0.4kV incoming line switches, 12 outgoing line switches, 2 capacitor switches, and 1 0.4kV section switch.
即,1号变压器的0.4kV低压侧通过0.4kV进线开关Q14、电流互感器连接至0.4kV一段母线,下设的6条出线上各自设置相应的出线开关Q15及电流互感器;2号变压器的0.4kV低压侧通过0.4kV进线开关Q24、电流互感器连接至0.4kV二段母线,下设另外6条出线上各自设置相应的出线开关Q25及电流互感器;0.4kV一段、二段母线之间设0.4kV分段开关Q31及引线。 That is, the 0.4kV low-voltage side of No. 1 transformer is connected to a 0.4kV section of busbar through 0.4kV incoming switch Q14 and current transformer, and the corresponding outgoing line switch Q15 and current transformer are set on each of the 6 outgoing lines; No. 2 transformer The 0.4kV low-voltage side is connected to the 0.4kV second-section busbar through the 0.4kV incoming line switch Q24 and current transformer, and the other 6 outgoing lines are equipped with corresponding outgoing line switches Q25 and current transformers; 0.4kV first-stage and second-stage busbars A 0.4kV segment switch Q31 and lead wires are set between them.
两组电容器(240kVar)起无功补偿作用,分别安装在两个电容器柜内,通过相应的电容器开关Q26分别连接至0.4kV一段、二段母线。 Two sets of capacitors (240kVar) play the role of reactive power compensation and are respectively installed in two capacitor cabinets, and are connected to the 0.4kV primary and secondary busbars through corresponding capacitor switches Q26.
如图5所示是本实用新型配电站的平面布置图,两组共六台10kV高压柜6(SF6环网柜)位于高压室内。两台相应设置0.4kV进线开关的0.4kV低压进线柜1(如GGD2-02)、六台相应设置出线开关的0.4kV低压出线柜2(如GGD2-38)、两台电容器柜3(如GGD)、一台设置0.4kV分段开关的低压分段柜4(如GGD2-02)及若干低压铜母线5(TMY-100×10)位于低压室内。1号变压器及2号变压器各自通过进出电缆连接至高压室和低压室内的相应设备。 As shown in Figure 5 is the layout of the distribution station of the utility model, two groups of six 10kV high-voltage cabinets 6 (SF6 ring network cabinets) are located in the high-voltage chamber. Two 0.4kV low-voltage incoming line cabinets 1 (such as GGD2-02) with corresponding 0.4kV incoming line switches, six 0.4kV low-voltage outgoing line cabinets 2 (such as GGD2-38) with corresponding outgoing line switches, and two capacitor cabinets 3 ( Such as GGD), a low-voltage section cabinet 4 with 0.4kV section switch (such as GGD2-02) and several low-voltage copper busbars 5 (TMY-100×10) are located in the low-voltage room. Transformer No. 1 and Transformer No. 2 are respectively connected to corresponding equipment in the high-voltage room and the low-voltage room through incoming and outgoing cables.
根据站址的污秽级别,本期工程设备的爬电比距按Ⅲ级进行选择,即10V及以下设备爬电比距户外按31mm/kV进行考虑,户内按25mm/kV考虑。在新增各配电装置室与保护屏屏柜下方,以及电缆改造、新增时所涉及的电缆夹层、穿墙楼板、墙壁、柜、盘处所有电缆孔洞和缝隙进行防火封堵。且将封堵处两侧各1m范围内的电缆外皮采用防火包带粘贴或涂防火涂料。 According to the pollution level of the station site, the creepage ratio distance of the project equipment in this phase is selected according to Class III, that is, the creepage ratio distance of equipment with 10V and below is considered as 31mm/kV outdoors and 25mm/kV indoors. Fireproof sealing shall be carried out at all cable holes and gaps at the bottom of newly added power distribution device rooms and protective screen cabinets, as well as at cable interlayers, wall-through floors, walls, cabinets, and panels involved in cable renovation and new additions. And the cable sheath within 1m on both sides of the blockage shall be pasted with fireproof tape or coated with fireproof paint.
如图2、图5所示,本例中可以在现有站址内对高压室内和低压室内设备进行改造,无需另外征地。 As shown in Figure 2 and Figure 5, in this example, the equipment in the high-pressure room and the low-voltage room can be remodeled within the existing station site without additional land acquisition.
综上所述,本实用新型提供的PT2型配电站,在不改变原有规模和电气接线方式的前提下,对配电站一次设备进行更换,设置SF6负荷闸刀并配备SF6报警装置,有利于提高设备的健康水平和安全运行水平,减少检修、维护的工作量,提高供电可靠性。 To sum up, the PT2 distribution station provided by the utility model replaces the primary equipment of the distribution station without changing the original scale and electrical wiring mode, and installs SF6 load switch blades and SF6 alarm devices. It is conducive to improving the health level and safe operation level of equipment, reducing the workload of inspection and maintenance, and improving the reliability of power supply.
尽管本实用新型的内容已经通过上述优选实施例作了详细介绍,但应当认识到上述的描述不应被认为是对本实用新型的限制。在本领域技术人员阅读了上述内容后,对于本实用新型的多种修改和替代都将是显而易见的。因此,本实用新型的保护范围应由所附的权利要求来限定。 Although the content of the present invention has been described in detail through the above preferred embodiments, it should be recognized that the above description should not be considered as a limitation of the present invention. Various modifications and substitutions of the present utility model will be obvious to those skilled in the art after reading the above content. Therefore, the protection scope of the present utility model should be defined by the appended claims.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201420149736.0U CN203813222U (en) | 2014-03-31 | 2014-03-31 | Two-input two-output PT2 power distribution station with subsections |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201420149736.0U CN203813222U (en) | 2014-03-31 | 2014-03-31 | Two-input two-output PT2 power distribution station with subsections |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN203813222U true CN203813222U (en) | 2014-09-03 |
Family
ID=51451932
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201420149736.0U Expired - Lifetime CN203813222U (en) | 2014-03-31 | 2014-03-31 | Two-input two-output PT2 power distribution station with subsections |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN203813222U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106327842A (en) * | 2016-10-26 | 2017-01-11 | 杭州欣美成套电器制造有限公司 | Ring main unit temperature and current wireless collection device and collection method |
-
2014
- 2014-03-31 CN CN201420149736.0U patent/CN203813222U/en not_active Expired - Lifetime
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106327842A (en) * | 2016-10-26 | 2017-01-11 | 杭州欣美成套电器制造有限公司 | Ring main unit temperature and current wireless collection device and collection method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101662132B (en) | 110kV/220kV voltage level composite apparatus and application thereof | |
| CN101577400A (en) | Chamber type liaison transforming plant reduced by 0.4kV from 20kV/10KV | |
| Grebovic et al. | Influence of shunt reactor switching on overvoltages in 400 kV substation | |
| CN108206531A (en) | Circuit and middle buckling stream case applied to energy storage frequency modulation system | |
| CN103840380A (en) | PT2 type power distribution station | |
| CN203813223U (en) | Integrated automation transformer substation | |
| CN103840378A (en) | Improved PT1 type power distribution station | |
| CN203813222U (en) | Two-input two-output PT2 power distribution station with subsections | |
| CN104037622A (en) | Two-in and two-out sectionalized power distribution station | |
| CN204230846U (en) | A kind of low-voltage cable junction box wiring system | |
| CN203826781U (en) | PT2 power distribution station | |
| CN101150246B (en) | 110kV and higher modular transformer substation and its construction method | |
| CN203813221U (en) | PT1 type power distribution station | |
| CN203813217U (en) | Improved PT1 type power distribution station | |
| CN205029223U (en) | Movable type transformer station | |
| CN216390531U (en) | A secondary voltage acquisition system on the low-voltage side of the main transformer of a new energy booster station | |
| CN204424772U (en) | Two main transformer four segmentation integrated automation converting stations | |
| CN210780123U (en) | Fully centralized monitoring protection device for electrical equipment of wind power booster station | |
| CN110165563A (en) | A kind of 220kV HGIS power distribution equipment applied to substation's single-trunk segmental wiring | |
| CN103840379A (en) | PT1 type power distribution station | |
| CN106451435A (en) | Distribution control system | |
| CN204290144U (en) | A kind of compact switch cabinet | |
| WO2016011636A1 (en) | Switch apparatus having voltage transformer or lightning arrester on busbar side | |
| CN207650286U (en) | It stands with change high-low pressure same period line loss measuring equipment | |
| Filipović-Grčić et al. | Analysis of transient recovery voltage on SF6 circuit breakers when switching unloaded 400 kV transmission lines |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CX01 | Expiry of patent term | ||
| CX01 | Expiry of patent term |
Granted publication date: 20140903 |