CN203768941U - Fast installation mould for foundation bolt set - Google Patents
Fast installation mould for foundation bolt set Download PDFInfo
- Publication number
- CN203768941U CN203768941U CN201420176124.0U CN201420176124U CN203768941U CN 203768941 U CN203768941 U CN 203768941U CN 201420176124 U CN201420176124 U CN 201420176124U CN 203768941 U CN203768941 U CN 203768941U
- Authority
- CN
- China
- Prior art keywords
- location
- plate
- fast installation
- mould
- abutting plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Finishing Walls (AREA)
Abstract
The utility model discloses a fast installation mould for a foundation bolt set. The fast installation mould comprises an abutting plate, at least two positioning plates and a plurality of parallel studs. Each positioning plate is provided with a plurality of positioning holes. The abutting plate and the positioning plates are installed on the studs in sequence. Each stud is connected with a plurality of adjusting nuts in a screwed mode, and the adjusting nuts are used for clamping the abutting plate and the positioning plates. The abutting plate is fixedly connected with the positioning plates through first cross-bridging pieces. By means of the fast installation mould, it is avoided that a large amount of time is spent on adjustment and measurement because foundation bolts are difficult to position, and human resources are saved. Materials of the mould are on-site materials for general purposes, the complex manufacturing process is not needed, the design is simple, and the operability is high.
Description
Technical field
The utility model relates to a kind of stone bolt dress mould.
Background technology
Cote d'lvoire's sumbul thunder power station has the diversion pressure steel tube of three diameter 8m, every length 96m, the production routine of penstock is for being first made at home tile, after being transported to scene, spell circle and welding job, built at the scene the assembled factory building of penstock, factory building adopts lightweight steel construction, wide 14.5m for this reason, long 91m, altogether 1320m
2, in factory building, arrange a 2X10t electric block type bridge machine, bridge machine span 13.5m, hook height 11m.
The connected mode that the assembled factory building of steel pipe adopts post base plinth to bury stone bolt underground has construction facility, the superior feature of switching performance.But simultaneously also strict to the required precision of construction, the slight error of stone bolt in burying underground, may cause serious consequence.Investigate and be not difficult to find out from steel work practice of construction process, the pre-buried accuracy of steel structure base lower margin is to affect the very important factor of Construction unit's steel-structure factory building installation quality.
Summary of the invention
Given this, the utility model object is to provide a kind of installation mold of being convenient to quick, accurate mounting foot bolt.
For solving above technical problem, the technical scheme that the utility model provides is, a kind of stone bolt group Rapid installing mould is provided, comprise a follow block and at least two location-plates, the many double-screw bolts that are parallel to each other, on location-plate, be provided with multiple locating holes, follow block and location-plate are arranged on double-screw bolt in turn, are also connected with the adjustment nut of multiple clamping follow blocks and location-plate on every double-screw bolt; Described follow block is fixedly connected with by the first bridging with location-plate.
Compared with prior art, a technical scheme tool in technique scheme has the following advantages:
1, the utility model stone bolt group Rapid installing mould, avoids wasting a large amount of time because of the bad location of stone bolt and goes to adjust and measure, and has saved manpower.Mold materials is on-the-spot versatile material, does not need complicated making, and simplicity of design is workable.
2, by adjusting the double action of nut and the first bridging, make mould structure more stable, be more conducive to ensure the accuracy of stone bolt group, reduced the alignment error of stone bolt group, improved construction on behalf of production efficiency.
Brief description of the drawings
Fig. 1 is follow block schematic diagram in the utility model one preferred embodiment.
Fig. 2 is location-plate schematic diagram in the utility model one preferred embodiment.
Fig. 3 is the schematic perspective view of the utility model one preferred embodiment.
Fig. 4 is the front elevational schematic of the utility model one preferred embodiment.
Fig. 5 is the stone bolt group front elevational schematic of having assembled.
1 follow block in figure, 11 first stud bolt holes, 2 location-plates, 21 second stud bolt holes, 22 locating holes, 3 double-screw bolts, 31 adjust nut, 4 first bridgings, 5 bolts, 51 second bridgings.
Detailed description of the invention
Describe below in conjunction with accompanying drawing and a specific embodiment.
Referring to Fig. 1 to Fig. 4.The described stone bolt group of the present embodiment Rapid installing mould, comprises a follow block 1 and two location-plates 2, four double-screw bolts that are parallel to each other 3.Follow block 1 and two location-plates 2 are rectangular slab, on four angles of follow block 1, are provided with the first stud bolt hole 11, on four angles of location-plate 2, are provided with the second stud bolt hole 21, are provided with multiple locating holes 22 on location-plate 2.Distance between two location-plates 2 is anchor bolt length 1/3.The arrangement of locating hole 22 is corresponding with the arrangement of stone bolt 5 in stone bolt group.In the present embodiment, stone bolt group comprises 6 stone bolt 5, and one-tenth two is arranged and put, and 6 stone bolt are fixing by the second bridging 51.
Follow block 1 and location-plate 2 are arranged on double-screw bolt 3 in turn, are also connected with the adjustment nut 31 of multiple clamping follow blocks 1 and location-plate 2 on every double-screw bolt 3.Follow block 1 and location-plate 2 be by adjusting behind nut 31 location, it proofreaied and correct with transit, then be fixedly connected with by the first bridging 4, after fixedly completing, precisely checks again, after acceptance(check), comes into operation again.
When mounting foot bolt group, mould is put on the ground of level, follow block 1 is positioned at below.Stone bolt 5 is inserted in the locating hole 22 of mould, and with the second bridging 51 to bolt group proofread and correct, consolidation process.Bolt group can come into operation after taking out fast like this, and the stone bolt group of installation as shown in Figure 5.
Below be only preferred embodiment of the present utility model, it should be pointed out that above-mentioned preferred embodiment should not be considered as restriction of the present utility model, protection domain of the present utility model should be as the criterion with claim limited range.For those skilled in the art, not departing from spirit and scope of the present utility model, can also make some improvements and modifications, these improvements and modifications also should be considered as protection domain of the present utility model.
Claims (1)
1. a stone bolt group Rapid installing mould, it is characterized in that, comprise a follow block (1) and at least two location-plates (2), the many double-screw bolts that are parallel to each other (3), on location-plate (2), be provided with multiple locating holes (22), it is upper that follow block (1) and location-plate (2) are arranged on double-screw bolt (3) in turn, is also connected with the adjustment nut (31) of multiple clamping follow blocks (1) and location-plate (2) on every double-screw bolt (3); Described follow block (1) is fixedly connected with by the first bridging (4) with location-plate (2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420176124.0U CN203768941U (en) | 2014-04-11 | 2014-04-11 | Fast installation mould for foundation bolt set |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420176124.0U CN203768941U (en) | 2014-04-11 | 2014-04-11 | Fast installation mould for foundation bolt set |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203768941U true CN203768941U (en) | 2014-08-13 |
Family
ID=51286148
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420176124.0U Expired - Fee Related CN203768941U (en) | 2014-04-11 | 2014-04-11 | Fast installation mould for foundation bolt set |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203768941U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104314100A (en) * | 2014-11-24 | 2015-01-28 | 广西壮族自治区冶金建设公司 | Construction method for installing steel column at a time through reserved hole mold |
CN106193094A (en) * | 2016-08-30 | 2016-12-07 | 中铁二十局集团有限公司 | A kind of embedding anchor bolts construction mould and foundation bolt regulation construction method |
CN106759443A (en) * | 2017-01-11 | 2017-05-31 | 中交第二航务工程局有限公司 | Pre-embedded bolt positioning fixture and its localization method |
CN108691423A (en) * | 2017-04-05 | 2018-10-23 | 通州建总集团有限公司 | A kind of foundation bolt assembling fixing device |
-
2014
- 2014-04-11 CN CN201420176124.0U patent/CN203768941U/en not_active Expired - Fee Related
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104314100A (en) * | 2014-11-24 | 2015-01-28 | 广西壮族自治区冶金建设公司 | Construction method for installing steel column at a time through reserved hole mold |
CN106193094A (en) * | 2016-08-30 | 2016-12-07 | 中铁二十局集团有限公司 | A kind of embedding anchor bolts construction mould and foundation bolt regulation construction method |
CN106193094B (en) * | 2016-08-30 | 2018-08-03 | 中铁二十局集团有限公司 | A kind of embedding anchor bolts construction mould and foundation bolt adjust construction method |
CN106759443A (en) * | 2017-01-11 | 2017-05-31 | 中交第二航务工程局有限公司 | Pre-embedded bolt positioning fixture and its localization method |
CN106759443B (en) * | 2017-01-11 | 2019-09-24 | 中交第二航务工程局有限公司 | Pre-embedded bolt positioning fixture and its localization method |
CN108691423A (en) * | 2017-04-05 | 2018-10-23 | 通州建总集团有限公司 | A kind of foundation bolt assembling fixing device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203768941U (en) | Fast installation mould for foundation bolt set | |
CN204585497U (en) | A kind of Cast-in-situ Beam mould | |
CN204703182U (en) | Crab-bolt stock | |
CN106592775B (en) | A kind of high-accuracy built-in fitting reinforces mounting device and method, purposes | |
CN105350654A (en) | Construction method for adjusting steel plate embedded parts to reach design and construction accuracy | |
CN111007535A (en) | Beidou foundation enhancement system reference station observation pier | |
CN208733666U (en) | A kind of fixing bolt preformed hole template tool | |
CN202265778U (en) | High-precision precast-beam positioning structure | |
CN204139622U (en) | Adjustable segmented column steel bar positioning fixture | |
CN203238657U (en) | Tool type anchor bolt mounting positioner | |
CN204825945U (en) | A fixture for fixing buried bolt in advance | |
CN204983399U (en) | Section of hanging down is transferred to testing column steel pipe | |
CN203334433U (en) | Concrete vertical face embedded part mounting fixing device | |
CN105040826A (en) | Standard embedded assembly for structure concrete construction and construction method of standard embedded assembly | |
CN203145481U (en) | Manufacturing and positioning device of variable-angle steel pipe column splicing ear plate | |
CN104805910A (en) | Embedded part for cast-in-place concrete component and construction method of embedded part | |
CN203049608U (en) | Communication tower foundation pre-buried foundation bolt device | |
CN102444315A (en) | Device and method for installing and positioning pillars for outdoor switchgears of thermal power plant | |
CN203307931U (en) | Embedded part positioning screw connecting structure | |
CN102912993B (en) | Method and die for guaranteeing mounting precision of prefabricated concrete structural member | |
CN103184743B (en) | Template flange | |
CN203247718U (en) | Steel column butt-joint mounting device | |
CN203654784U (en) | Assembly and location mould for main beam and end plate of boiler steel frame structure | |
CN109443328B (en) | Prestressed pipeline coordinate positioning ruler and use method thereof | |
CN212052731U (en) | Tubular pile connecting device convenient to dismantle |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20140813 |