CN203755670U - Overhanging fire control corridor supporting structure - Google Patents

Overhanging fire control corridor supporting structure Download PDF

Info

Publication number
CN203755670U
CN203755670U CN201420087135.1U CN201420087135U CN203755670U CN 203755670 U CN203755670 U CN 203755670U CN 201420087135 U CN201420087135 U CN 201420087135U CN 203755670 U CN203755670 U CN 203755670U
Authority
CN
China
Prior art keywords
iron
encorbelmenting
overhanging
beams
fire control
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420087135.1U
Other languages
Chinese (zh)
Inventor
谢艺
张霞
王昌威
牛小平
侯海英
史永恒
张彦书
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Shanxi Sijian Group Co Ltd
Original Assignee
China Shanxi Sijian Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Shanxi Sijian Group Co Ltd filed Critical China Shanxi Sijian Group Co Ltd
Priority to CN201420087135.1U priority Critical patent/CN203755670U/en
Application granted granted Critical
Publication of CN203755670U publication Critical patent/CN203755670U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model belongs to building construction supporting structures, and particularly relates to an overhanging fire control corridor supporting structure. The problem that when a fire control corridor is not attached to a building, a conventional overhanging I-beam can not be used for supporting a formwork is solved. The overhanging fire control corridor supporting structure comprises a plurality of overhanging I-beams, and the ends of the I-beams are fixed by a round steel pressing ring embedded in a body. The overhanging I-beams comprise long overhanging I-beams and short overhanging I-beams, simple I-beams which are perpendicular to the overhanging I-beams are welded and fixed on the upper sides of the long overhanging I-beams, and the two ends of the simple I-beams are welded and fixed. The overhanging fire control corridor supporting structure is simple in structure and capable of meeting the demand of a fire control corridor formwork supporting system with a large overhanging distance, and achieves the purpose that the formwork supporting system meets the bearing force requirement of a fire control corridor.

Description

The fire-fighting vestibule braced structures of encorbelmenting
Technical field
The utility model belongs to building operations braced structures, specifically the one fire-fighting vestibule braced structures of encorbelmenting.
Background technology
Fire-fighting vestibule generally can be set in high level and super highrise building to meet fire protection requirement, fire-fighting vestibule can be close to building form bracing system conventionally, and cantilever span is less.Some engineering fire-fighting vestibule is not close to building, and the maximum distance of encorbelmenting is larger, can not simply rely on the routine i iron of encorbelmenting to carry out shuttering supporting.
Summary of the invention
When the utility model is not close to building in order to solve fire-fighting vestibule, the routine i iron of encorbelmenting cannot carry out the problem of shuttering supporting, and the one fire-fighting vestibule braced structures of encorbelmenting is provided.
The utility model is taked following technical scheme: the one fire-fighting vestibule braced structures of encorbelmenting, comprise the some i iron of encorbelmenting, the some i iron ends of encorbelmenting are fixed by the round steel pressure ring being embedded in main body, the i iron of encorbelmenting comprises long encorbelment i iron and the short i iron of encorbelmenting, wherein the long i iron upside of encorbelmenting is welded with the simple and easy i iron vertical with the i iron of encorbelmenting, and simple and easy i iron two ends are welded and fixed.
Described simple and easy i iron has 2, and 2 simple and easy i iron stack and weld together.
On the every described i iron of encorbelmenting, there are 3 for fixing round steel pressure ring.
Described round steel pressure ring is U-shaped, and round steel pressure ring downside is embedded in concrete, and the U-shaped pin place of round steel pressure ring upside is fixed on compressing tablet by nut, and the i iron of encorbelmenting is arranged in round steel pressure ring and compressing tablet.
Compared with prior art, the utility model is simple in structure, meets the fire-fighting vestibule form bracing system of the distance of encorbelmenting more greatly, has reached form bracing system and has met the completely object of fire-fighting vestibule requirement for bearing capacity.
Brief description of the drawings
Fig. 1 is the utility model structure chart;
Fig. 2 is that the utility model fire-fighting corridor construction completes plan view;
Fig. 3 is the utility model i iron end fixed structure schematic diagram of encorbelmenting;
The long i iron of encorbelmenting of 1-in figure, the simple and easy i iron of 2-, the short i iron of encorbelmenting of 3-, 4-round steel pressure ring, 5-compressing tablet.
Detailed description of the invention
As shown in Figure 1, 2, the one fire-fighting vestibule braced structures of encorbelmenting, comprise the some i iron of encorbelmenting, the some i iron ends of encorbelmenting are fixed by the round steel pressure ring 4 being embedded in main body, the i iron of encorbelmenting comprises long encorbelment i iron 1 and the short i iron 3 of encorbelmenting, wherein long i iron 1 upside of encorbelmenting is welded with the simple and easy i iron 2 vertical with the i iron of encorbelmenting, and simple and easy i iron 2 two ends are welded and fixed.
Described simple and easy i iron 2 has 2, and 2 simple and easy i iron 2 stack and weld together.
On the every described i iron of encorbelmenting, there are 3 for fixing round steel pressure ring 4.
Described round steel pressure ring 4 is U-shaped, and round steel pressure ring 4 downsides are embedded in concrete, and the U-shaped pin place of round steel pressure ring 4 upsides is fixed on compressing tablet 5 by nut, and the i iron of encorbelmenting is arranged in round steel pressure ring 4 and compressing tablet 5.
The utility model concrete operating procedure in engineering is as follows:
In completed substructure, set up freely-supported i iron, select 2 20# freely-supported i iron to stack setting, and i iron is carried out to welding procedure, guarantee that two i iron connect into entirety, utilize tower crane that i iron is winched to and sets up floor and be positioned over staircase with indoor absolute altitude place, two end bearing places and structure reinforcing bars are welded into entirety to ensure its stability.
The long i iron and freely-supported i iron is welded and fixed and both sides steel bar end is welded and fixed of encorbelmenting, the short i iron of encorbelmenting is directly encorbelmented.The i iron end dependence of encorbelmenting has been embedded in main body San road round steel pressure ring and has fixed.Reduce the cantilever span of the i iron of encorbelmenting, met support system load requirement.
Welded reinforcement short column on the i iron of encorbelmenting of installing, guarantee that every frame pipe is all inserted in this reinforcing bar short column to ensure the stability of scaffold system, thereby make whole i-beam structure form a stable shuttering supporting basis, on this, carry out the supporting template system construction of fire-fighting vestibule.

Claims (4)

1. the fire-fighting vestibule braced structures of encorbelmenting, comprise the some i iron of encorbelmenting, it is characterized in that: the some i iron ends of encorbelmenting are fixed by the round steel pressure ring (4) being embedded in main body, the i iron of encorbelmenting comprises long encorbelment i iron (1) and the short i iron of encorbelmenting (3), wherein long i iron (1) upside of encorbelmenting is welded with the simple and easy i iron (2) vertical with the i iron of encorbelmenting, and simple and easy i iron (2) two ends are welded and fixed.
2. the fire-fighting vestibule braced structures of encorbelmenting according to claim 1, is characterized in that: described simple and easy i iron (2) has 2, and 2 simple and easy i iron (2) stack and weld together.
3. the fire-fighting vestibule braced structures of encorbelmenting according to claim 1, is characterized in that: on the every described i iron of encorbelmenting, have 3 for fixing round steel pressure ring (4).
4. the fire-fighting vestibule braced structures of encorbelmenting according to claim 1, it is characterized in that: described round steel pressure ring (4) is for U-shaped, round steel pressure ring (4) downside is embedded in concrete, it is upper that the U-shaped pin place of round steel pressure ring (4) upside is fixed on compressing tablet (5) by nut, and the i iron of encorbelmenting is arranged in round steel pressure ring (4) and compressing tablet (5).
CN201420087135.1U 2014-02-28 2014-02-28 Overhanging fire control corridor supporting structure Expired - Lifetime CN203755670U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420087135.1U CN203755670U (en) 2014-02-28 2014-02-28 Overhanging fire control corridor supporting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420087135.1U CN203755670U (en) 2014-02-28 2014-02-28 Overhanging fire control corridor supporting structure

Publications (1)

Publication Number Publication Date
CN203755670U true CN203755670U (en) 2014-08-06

Family

ID=51250960

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420087135.1U Expired - Lifetime CN203755670U (en) 2014-02-28 2014-02-28 Overhanging fire control corridor supporting structure

Country Status (1)

Country Link
CN (1) CN203755670U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106088313A (en) * 2016-06-23 2016-11-09 青岛海川建设集团有限公司 Simply supported beam method is encorbelmented vestibule form bracing system construction technology
CN111677259A (en) * 2020-06-11 2020-09-18 北京城建十六建筑工程有限责任公司 High-rise Bailey truss cantilever construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106088313A (en) * 2016-06-23 2016-11-09 青岛海川建设集团有限公司 Simply supported beam method is encorbelmented vestibule form bracing system construction technology
CN111677259A (en) * 2020-06-11 2020-09-18 北京城建十六建筑工程有限责任公司 High-rise Bailey truss cantilever construction method

Similar Documents

Publication Publication Date Title
CN203867216U (en) Detachable steel frame supporting structure for ultra-high-rise building cantilevered plate
CN102733606B (en) The construction method of High Large Cantilever structure
CN102535845A (en) Construction method of bearing frame of corridor structure
CN203961238U (en) Bolt anchor slab adjustable tool formula builder's jack
CN202787926U (en) Overhanging scaffold simple and convenient to disassemble and assemble
CN103122691A (en) Tower crane standard knot bearing upper air supporting formwork steel platform structure and construction method
CN203961281U (en) Steel bar girder beam form frame and H section steel beam-cast-in-place concrete floor formwork system
CN203834926U (en) Formwork erecting structure for bare concrete basement exterior wall
CN203755670U (en) Overhanging fire control corridor supporting structure
CN103206075A (en) Suspension platform for construction of steel reinforced concrete cantilever structure
CN201915631U (en) High-altitude long-span reinforced concrete corridor construction supporting structure
CN213953189U (en) Supporting device for ensuring smooth surface of lower cone shell of prefabricated water tank
CN204282803U (en) To encorbelment formwork structure for mounting platform
CN203213019U (en) Long cantilever bent cap cast-in-place construction support system
CN203977840U (en) A kind of high-altitude long-span strengthening concrete vestibule braced structures
CN103758342A (en) Tool-type top form for buildings
CN104074275A (en) Prefabricated concrete column connecting joint structure
CN204212385U (en) Scaffold strengthened by truss
CN203334643U (en) Tower crane standard knot and structural steel combination high-altitude large-span operation frame device
CN203891442U (en) High-rise elevator shaft template supporting platform
CN203891218U (en) Beam, plate and column intersection node in main excavation-for-cover station structure
CN203755451U (en) Connecting device for dual-layer full-steel structure floor embedded with channel steel beam and column
CN205777531U (en) Floor slab construction beam string shuttering supporting equipment
CN201915630U (en) Combined platform of fire control joint gallery form supporting steel beam
CN103276889B (en) Full hall fastener type steel pipe scaffold anti-side shifting method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20140806