CN203742156U - Beret frame lower chord downward-hanging joist steel hoop type device - Google Patents
Beret frame lower chord downward-hanging joist steel hoop type device Download PDFInfo
- Publication number
- CN203742156U CN203742156U CN201320818696.XU CN201320818696U CN203742156U CN 203742156 U CN203742156 U CN 203742156U CN 201320818696 U CN201320818696 U CN 201320818696U CN 203742156 U CN203742156 U CN 203742156U
- Authority
- CN
- China
- Prior art keywords
- shaped
- iron
- type device
- platform connector
- hoop
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Joining Of Building Structures In Genera (AREA)
Abstract
本实用新型公开了一种贝雷架下弦下挂工字钢抱箍式装置,其特征在于包括平台连接件工字钢、U型抱箍式夹具、连接板及高强螺栓,所述U型抱箍式夹具的底端与所述连接板连接;所述U型抱箍式夹具抱住所述平台连接件工字钢;所述高强螺栓穿设所述U型抱箍式夹具的两端,并且与所述平台连接件工字钢的上翼缘板相抵接;所述连接板设有T型凹槽,吊车梁工字钢的上翼缘板插入所述T型凹槽。本实用新型结构简单、操作方便,通用性强,可以随时拆装,提高了贝雷架组合的灵活度,拓宽了贝雷架的应用面。
The utility model discloses an I-shaped steel hoop-type device for hanging under the lower chord of a Bailey rack, which is characterized in that it comprises a platform connector I-beam, a U-shaped hoop-type clamp, a connecting plate and a high-strength bolt. The bottom end of the hoop clamp is connected to the connecting plate; the U-shaped hoop clamp hugs the I-beam of the platform connector; the high-strength bolts pass through the two ends of the U-shaped hoop clamp, And abut against the upper flange plate of the I-beam of the platform connector; the connecting plate is provided with a T-shaped groove, and the upper flange plate of the I-beam of the crane beam is inserted into the T-shaped groove. The utility model has the advantages of simple structure, convenient operation and strong versatility, and can be disassembled and assembled at any time, thereby improving the flexibility of the combination of the Bailey frame and widening the application surface of the Bailey frame.
Description
技术领域 technical field
本实用新型涉及一种贝雷架下弦下挂工字钢抱箍式装置。 The utility model relates to an I-shaped steel hoop-type device for hanging under the lower chord of a Bailey frame. the
背景技术 Background technique
当前正处于高层建筑急剧发展期,越来越高的建筑不断涌现,顶模系统的应用也越来越广泛。传统的顶模系统中贝雷架下弦与吊车梁工字钢是通过螺栓连接或者焊接的方式连接,这些连接方式通用性不强,也不便于随时拆装移动;为此,根据贝雷架自身的特点,发明了一种贝雷架下弦下挂工字钢抱箍式装置,其操作方便,通用性强,便于随时拆装移动。 Currently in the period of rapid development of high-rise buildings, higher and higher buildings continue to emerge, and the application of top formwork systems is becoming more and more extensive. In the traditional top formwork system, the lower chord of the Bailey frame and the I-beam of the crane beam are connected by bolts or welding. According to the characteristics of the Bailey frame, a kind of I-shaped steel hoop type device is invented, which is easy to operate, has strong versatility, and is easy to disassemble and move at any time. the
实用新型内容 Utility model content
本实用新型所要解决的技术问题是提供一种贝雷架下弦下挂工字钢抱箍式装置,可以大幅提高操作人员的施工工效,并且安全可靠。 The technical problem to be solved by the utility model is to provide an I-steel hoop-type device for hanging under the lower chord of the Bailey frame, which can greatly improve the construction efficiency of operators, and is safe and reliable. the
本实用新型所要解决的技术问题是通过以下技术方案来实现的: The technical problem to be solved by the utility model is achieved through the following technical solutions:
一种贝雷架下弦下挂工字钢抱箍式装置,其特征在于:包括平台连接件工字钢、U型抱箍式夹具、连接板及高强螺栓,所述U型抱箍式夹具的底端与所述连接板连接;所述U型抱箍式夹具抱住所述平台连接件工字钢;所述高强螺栓穿设所述U型抱箍式夹具的两端,并且与所述平台连接件工字钢的上翼缘板相抵接;所述连接板设有T型凹槽,吊车梁工字钢的上翼缘板插入所述T型凹槽。 An I-shaped steel hoop-type device for hanging under the lower chord of a Bailey frame, which is characterized in that it includes a platform connector I-beam, a U-shaped hoop-type clamp, a connecting plate and high-strength bolts, and the U-shaped hoop-type clamp The bottom end is connected with the connecting plate; the U-shaped hoop clamp hugs the I-beam of the platform connector; the high-strength bolts pass through both ends of the U-shaped hoop clamp, and The upper flange plates of the I-beams of the platform connector are in contact with each other; the connecting plates are provided with T-shaped grooves, and the upper flange plates of the I-beams of the crane beam are inserted into the T-shaped grooves.
上述方案中,所述T型凹槽的宽度略大于所述吊车梁工字钢上翼缘板的宽度,所述T型凹槽与所述吊车梁工字钢上翼缘板相匹配。 In the above solution, the width of the T-shaped groove is slightly larger than the width of the upper flange plate of the I-beam of the crane beam, and the T-shaped groove matches the upper flange plate of the I-beam of the crane beam. the
上述方案中,所述的平台连接件工字钢与所述的吊车梁工字钢相垂直。 In the above solution, the I-beam of the platform connector is perpendicular to the I-beam of the crane beam. the
与现有技术相比,本实用新型的有益效果: Compared with prior art, the beneficial effect of the utility model:
本实用新型是一种用于贝雷架下弦下挂工字钢的夹具,其结构简单、操作方便,通用性强,可以随时拆装,提高了贝雷架组合的灵活度,拓宽了贝雷架的应用面。 The utility model is a clamp used for hanging I-beams under the lower chord of a Bailey frame. application side of the rack.
附图说明 Description of drawings
图1本实用新型的俯视图。 Fig. 1 is the top view of the utility model. the
图2为正面示意图。 Figure 2 is a front schematic view. the
图3为侧面示意图。 Figure 3 is a schematic side view. the
图中,1-平台连接件工字钢,2-U型抱箍式夹具,3-吊车梁工字钢, 4-连接板,5-高强螺栓。 In the figure, 1- I-beam of platform connector, 2- U-shaped clamp, 3- I-beam of crane beam, 4- connecting plate, 5- high-strength bolt. the
具体实施方式 Detailed ways
为了更好地理解本实用新型,下面结合附图进一步阐明本实用新型的内容,但本实用新型不仅仅局限于下面的实施例。 In order to better understand the utility model, the content of the utility model is further explained below in conjunction with the accompanying drawings, but the utility model is not limited to the following embodiments. the
如图1-3所示,一种贝雷架下弦下挂工字钢抱箍式装置,包括平台连接件工字钢1、U型抱箍式夹具2、连接板4及高强螺栓5,所述U型抱箍式夹具2的底端与所述连接板4连接;所述U型抱箍式夹具2抱住所述平台连接件工字钢1;所述高强螺栓5穿设所述U型抱箍式夹具2的两端,并且与所述平台连接件工字钢1的上翼缘板相抵接;所述连接板4设有T型凹槽,吊车梁工字钢3的上翼缘板插入所述T型凹槽。 As shown in Figure 1-3, an I-beam hoop-type device for hanging under the lower chord of a Bailey rack includes a platform connector I-beam 1, a U-shaped hoop-type clamp 2, a connecting plate 4 and high-strength bolts 5. The bottom end of the U-shaped hoop clamp 2 is connected to the connecting plate 4; the U-shaped hoop clamp 2 embraces the I-beam 1 of the platform connector; the high-strength bolt 5 passes through the U The two ends of the hoop type clamp 2, and abut against the upper flange plate of the I-beam 1 of the platform connector; the connecting plate 4 is provided with a T-shaped groove, and the upper wing of the I-beam 3 of the crane beam The edge plate is inserted into the T-groove. the
所述T型凹槽的宽度略大于所述吊车梁工字钢3上翼缘板的宽度,所述吊车梁工字钢3上翼缘板刚好可以插入所述T型凹槽。 The width of the T-shaped groove is slightly larger than the width of the upper flange plate of the crane beam I-beam 3 , and the upper flange plate of the crane beam I-beam 3 can just be inserted into the T-shaped groove. the
所述的平台连接件工字钢1与所述的吊车梁工字钢3相垂直。 The I-beam 1 of the platform connector is perpendicular to the I-beam 3 of the crane beam. the
顶模系统安装过程中需在贝雷架下弦下挂工字钢来安装单轨行车,将U型抱箍式夹具套住平台连接件工字钢,然后通过高强螺栓固定,再将吊车梁工字钢上翼缘插入U型抱箍式夹具的下端连接板上的T型凹槽,即可将贝雷架平台连接件和吊车梁工字钢连接成一个整体。 During the installation process of the top formwork system, it is necessary to hang the I-beam under the lower chord of the Bailey frame to install the monorail crane, put the U-shaped hoop clamp on the I-beam of the platform connector, and then fix it with high-strength bolts, and then install the I-beam of the crane beam. The upper flange of the steel is inserted into the T-shaped groove on the lower connecting plate of the U-shaped hoop clamp, so that the connecting piece of the Bailey frame platform and the I-beam of the crane beam can be connected as a whole. the
Claims (3)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201320818696.XU CN203742156U (en) | 2013-12-13 | 2013-12-13 | Beret frame lower chord downward-hanging joist steel hoop type device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201320818696.XU CN203742156U (en) | 2013-12-13 | 2013-12-13 | Beret frame lower chord downward-hanging joist steel hoop type device |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN203742156U true CN203742156U (en) | 2014-07-30 |
Family
ID=51341974
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201320818696.XU Expired - Fee Related CN203742156U (en) | 2013-12-13 | 2013-12-13 | Beret frame lower chord downward-hanging joist steel hoop type device |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN203742156U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105366576A (en) * | 2015-09-25 | 2016-03-02 | 贵州新建业工程有限责任公司 | Underground monorail crane |
-
2013
- 2013-12-13 CN CN201320818696.XU patent/CN203742156U/en not_active Expired - Fee Related
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105366576A (en) * | 2015-09-25 | 2016-03-02 | 贵州新建业工程有限责任公司 | Underground monorail crane |
| CN105366576B (en) * | 2015-09-25 | 2018-10-12 | 贵州新建业工程有限责任公司 | Underground monorail crane |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN204611104U (en) | A kind of fixture being applicable to I-shape beam | |
| CN202299465U (en) | Quick adjustment device for steel beam hoisting | |
| CN204487029U (en) | A kind of safety belt suspension clamp | |
| CN205806689U (en) | A kind of pipeline elevator being easily installed | |
| CN203669346U (en) | Screw-in type clamp for bailey truss lower chord and lower suspended I-steel | |
| CN204386608U (en) | A kind of tunnel invert construction tool | |
| CN203742156U (en) | Beret frame lower chord downward-hanging joist steel hoop type device | |
| CN203361603U (en) | Detachable anchoring part of building-type steel beam overhanging scaffold | |
| CN204850047U (en) | Two davits of both shoulders and crane beam connection structure | |
| CN203667813U (en) | Bailey frame bottom chord downwards-hanging I-steel pin-type clamp | |
| CN204400502U (en) | Bottle gouard moved by hands support | |
| CN102704696B (en) | Space locator for high, big and heavy steel upright column | |
| CN102383613B (en) | Hoisting construction method for steel roof truss of main power house of power plant and special hoisting device | |
| CN202544399U (en) | Supporting frame for overhang floor slab with steel structure | |
| CN204681017U (en) | A kind of joist steel upright base | |
| CN203867164U (en) | Cantilever type scaffold structure with positioning steel pipe | |
| CN204590617U (en) | The universal connection boots of large form support system | |
| CN103386573B (en) | PN locomotive cooling chamber cooling fan installing plate assembly tool | |
| CN202627275U (en) | Keel structure for dry-hanging stone curtain walls | |
| CN202467221U (en) | Power plant main workshop steel roof truss hoisting lifting device | |
| CN206800975U (en) | A kind of foot guard plate of scaffold sets up system | |
| CN204237442U (en) | For clamping the fixture of I-beam section | |
| CN204940528U (en) | A kind of steel structure platform beam syndeton | |
| CN204199723U (en) | A kind of clamping device for Steel Structure Installation | |
| CN204980860U (en) | I -beam hoisting clamp |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| TR01 | Transfer of patent right | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20221128 Address after: 3301, Office Building 3B, Vanke Times Square, No. 85, Longcheng Avenue, Shangjing Community, Longcheng Street, Longgang District, Shenzhen, Guangdong 518172 Patentee after: China Construction Third Engineering Bureau Science and Innovation Industry Development Co.,Ltd. Address before: 430040, No. 1, Soochow Road, Dongxihu District, Hubei, Wuhan Patentee before: CHINA CONSTRUCTION THIRD BUREAU FIRST ENGINEERING Co.,Ltd. |
|
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20140730 |