CN203729176U - Highway subgrade settlement prevention facility - Google Patents

Highway subgrade settlement prevention facility Download PDF

Info

Publication number
CN203729176U
CN203729176U CN201420123834.7U CN201420123834U CN203729176U CN 203729176 U CN203729176 U CN 203729176U CN 201420123834 U CN201420123834 U CN 201420123834U CN 203729176 U CN203729176 U CN 203729176U
Authority
CN
China
Prior art keywords
layer
subgrade
layers
prevention facility
highway subgrade
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420123834.7U
Other languages
Chinese (zh)
Inventor
赵伟崇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201420123834.7U priority Critical patent/CN203729176U/en
Application granted granted Critical
Publication of CN203729176U publication Critical patent/CN203729176U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model discloses a highway subgrade settlement prevention facility. The highway subgrade settlement prevention facility comprises a pavement layer and subgrade piles, wherein a subgrade layer is arranged between the pavement layer and the subgrade piles, a sand treatment layer is arranged between the pavement layer and the subgrade layer, and at least two layers of geogrid layers are arranged in the subgrade layer. According to the highway subgrade settlement prevention facility, the combination of the sand treatment layer and the geogrid layers is adopted, the sand treatment layer can be used for effectively preventing pavement ponding from permeating into the subgrade layer, the geogrid layers can be used for improving the bearing capacity of the subgrade quickly and controlling the development of the settlement amount, and the load can be distributed to wider subbase layers effectively by the lateral confinement effect on the subgrade layer, so that the phenomenon of subgrade settlement can be prevented effectively, the driving safety is improved, and the service life of roads can be prolonged.

Description

Anti-settling device of highway subgrade
Technical field
The utility model relates to a kind of Anti-settling device of highway subgrade.
Background technology
Subgrade settlement is the common a kind of phenomenon that endangers traffic safety of highway use procedure, owing to bearing for a long time higher load effect, causes the whole sinking of roadbed, and formation is uneven, and when vehicle travels on this up-and-down road surface, being that driving is big really avoids.And existing anti-settling facility is only to lay one deck processing layer between the basic unit of roadbed and roadbed stake, too simple structural measure is difficult to thoroughly solve the problem of roadbed subsidence, especially the road of building in the poor location of geological conditions, carries out anti-settling measure particularly important.
Summary of the invention
The technical problems to be solved in the utility model is: the problem for the prior art solving in above-mentioned background technology exists, provides a kind of improved Anti-settling device of highway subgrade, to prevent better roadbed subsidence.
The utility model solves the technical scheme that its technical problem adopts: a kind of Anti-settling device of highway subgrade, comprise supercrust, roadbed stake, between supercrust and roadbed stake, it is base course, between described supercrust and base course, be provided with grains of sand processing layer, in base course, be provided with at least two-layer geogrids layer.
Preferably, in described base course, be provided with from bottom to up three layers of geogrids layer.
Further, described geogrids layer geo-grid used is unidirectional geo-grid.
The beneficial effects of the utility model are, the utility model adopts grains of sand processing layer to combine with geogrids layer, grains of sand processing layer can effectively prevent that surface gathered water from penetrating into base course, geogrids layer can improve rapidly bearing capacity of foundation soil, control the development of settling amount, to the side of base course, limit interaction energy effectively load to be distributed on wider subbase, thereby can effectively prevent the generation of subgrade settlement phenomenon, improve travel safety, extend Road Service Life.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the utility model is further illustrated.
Fig. 1 is structural representation of the present utility model.
In figure: 1. supercrust 2. roadbed stake 3. base course 4. grains of sand processing layer 5. geogrids layer
The specific embodiment
By reference to the accompanying drawings the utility model is described in further detail now.These accompanying drawings are the schematic diagram of simplification, basic structure of the present utility model is only described in a schematic way, so it only show the formation relevant with the utility model.
A kind of Anti-settling device of highway subgrade as shown in Figure 1, comprise supercrust 1, roadbed stake 2, between supercrust 1 and roadbed stake 2, it is base course 3, between described supercrust 1 and base course 3, be provided with grains of sand processing layer 4, grains of sand processing layer can fully absorb surface gathered water, prevents that ponding from penetrating into base course and causing subgrade settlement.
In described base course 3, be provided with from bottom to up three layers of geogrids layer 5, described geogrids layer 5 geo-grid used is unidirectional geo-grid.Because geo-grid can improve rapidly bearing capacity of foundation soil, control the development of settling amount, side limit interaction energy to base course 3 is distributed to load on wider subbase effectively, thereby reduces base course 3 thickness, reduces construction costs, reduction of erection time, increase the service life, so geo-grid can strengthening soft foundation, and geo-grid is during for reinforcement pitch or cement pavement, can reduce the rut degree of depth, extend road surface anti-fatigue life.
While carrying out geogrids layer 5 construction, should first smooth original ground on base course 3, then lay geo-grid, during laying, geo-grid stretch-draw is opened, elongation control during stretch-draw is between 0.5%~1%, the preferential coated that adopts during geogrids layer 5 construction, guarantee that geo-grid is stressed evenly, by hold-down bars or plastic ties, adjacent geo-grid is fixed, laid after first floor geogrids layer, fill out new one deck earthwork smooth thereon, on a section of the geo-grid parcel trough of having laid, turn over, then second layer geo-grid is paved, at the edge of earthen fill zone with plastic ties by second layer geo-grid together with the colligation of first floor geo-grid, other end pretensioning, when not loosening together with the geo-grid colligation of turning on first floor, each reserved 150 centimetres of left and right, two ends, finally cut off unnecessary geo-grid, complete the laying of second layer geogrids layer 5, in second layer geogrids layer 5, banket, according to aforementioned manner, lay the 3rd layer of geogrids layer 5.
The above-mentioned foundation desirable embodiment of the present utility model of take is enlightenment, and by above-mentioned description, relevant staff can, within not departing from the scope of this utility model technological thought, carry out various change and modification completely.The technical scope of this utility model is not limited to the content on manual, must determine its technical scope according to claim scope.

Claims (3)

1. an Anti-settling device of highway subgrade, comprise supercrust (1), roadbed stake (2), between supercrust (1) and roadbed stake (2), be base course (3), it is characterized in that: between described supercrust (1) and base course (3), be provided with grains of sand processing layer (4), in base course (3), be provided with at least two-layer geogrids layer (5).
2. Anti-settling device of highway subgrade according to claim 1, is characterized in that: in described base course (3), be provided with from bottom to up three layers of geogrids layer (5).
3. Anti-settling device of highway subgrade according to claim 1 and 2, is characterized in that: described geogrids layer (5) geo-grid used is unidirectional geo-grid.
CN201420123834.7U 2014-03-12 2014-03-12 Highway subgrade settlement prevention facility Expired - Fee Related CN203729176U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420123834.7U CN203729176U (en) 2014-03-12 2014-03-12 Highway subgrade settlement prevention facility

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420123834.7U CN203729176U (en) 2014-03-12 2014-03-12 Highway subgrade settlement prevention facility

Publications (1)

Publication Number Publication Date
CN203729176U true CN203729176U (en) 2014-07-23

Family

ID=51199261

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420123834.7U Expired - Fee Related CN203729176U (en) 2014-03-12 2014-03-12 Highway subgrade settlement prevention facility

Country Status (1)

Country Link
CN (1) CN203729176U (en)

Similar Documents

Publication Publication Date Title
CN107419630B (en) Soft soil foundation high-filling embankment capable of effectively controlling post-construction settlement and construction method
CN204401444U (en) A kind of high embankment filled soil end of the bridge anti-settling structure
CN203960883U (en) One both wired high embankment is helped wide ruggedized construction
CN202969393U (en) Ribbing load reduction structure of road high hill culvert
CN210766223U (en) Roadbed structure capable of preventing settlement during drainage
CN101962929B (en) Novel method for processing soft soil subgrade by pile-supporting reinforcing technology
CN103790151B (en) Plugging structure and construction method after a kind of soft soil roadbed draining precompressed
CN104358196B (en) Highway open to traffic Embankment Subsidence disposes the construction method of structure
CN203498721U (en) Three-dimensional drainage roadbed structure preventing damage by water of road in cold region
CN107938480A (en) A kind of microorganism cures the desert highway embankment and its construction method of joint TGXG
CN107700299B (en) Overpass lower-layer ground road structure and construction method thereof
CN104179105A (en) Top-down rigid pile compound foundation construction method
CN207714057U (en) A kind of anti-settling road structure
CN203270559U (en) Roadbed structure of screw pile network structure composite foundation
CN102465481A (en) Soilbag roadbed and method
CN208884292U (en) Soft soil roadbed and normal roadbed intersection anti-settling structure
CN207828727U (en) A kind of full impregnated pavement structure
CN203729176U (en) Highway subgrade settlement prevention facility
CN203741814U (en) Blocking structure used after soft soil roadbed drainage prepressing
CN203866814U (en) Medium-compressibility soil foundation reinforcing structure for high speed railway
CN206941324U (en) A kind of embankment of anti-settling formula
CN204385575U (en) Fill Reinforced With Geogrids clay bound edge CHARACTERISTICS OF TAILINGS SAND roadbed
CN104452805A (en) Roadbed structure of underpass expressway adjacent to bridge pier
CN210826965U (en) Highway subgrade settlement-preventing device
CN107604786A (en) A kind of full impregnated pavement structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140723

Termination date: 20150312

EXPY Termination of patent right or utility model