CN203701158U - 桩基础竖向承载力检测装置 - Google Patents

桩基础竖向承载力检测装置 Download PDF

Info

Publication number
CN203701158U
CN203701158U CN201420031446.6U CN201420031446U CN203701158U CN 203701158 U CN203701158 U CN 203701158U CN 201420031446 U CN201420031446 U CN 201420031446U CN 203701158 U CN203701158 U CN 203701158U
Authority
CN
China
Prior art keywords
pile
steel bar
counter
bar column
bearing capacity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420031446.6U
Other languages
English (en)
Inventor
乔培松
林思军
孙淑欣
张凯
王昌柏
张鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Run Jia Construction Group Co Ltd
Original Assignee
Qingdao Run Jia Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Run Jia Construction Group Co Ltd filed Critical Qingdao Run Jia Construction Group Co Ltd
Priority to CN201420031446.6U priority Critical patent/CN203701158U/zh
Application granted granted Critical
Publication of CN203701158U publication Critical patent/CN203701158U/zh
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

本实用新型涉及一种桩基础竖向承载力检测装置,在地基下部设置有测试桩,测试桩上部连接有钢筋柱,钢筋柱上焊接有反力梁;反力梁的两侧位置下方的地基上设置有反力桩,反力桩上设置有千斤顶,千斤顶上设置有测力传感器;钢筋柱两侧位置上设置有位移传感器。位移传感器采用磁性基座固定在钢筋柱上。该实用新型装置能够有效地针对测试桩进行施工测试,以便更加安全地进行施工,且施工测试方式简单,提高了建筑施工桩的检测快捷性和安全性,有助于建筑施工打桩。

Description

桩基础竖向承载力检测装置
技术领域
本实用新型涉及一种桩基础竖向承载力检测装置,属于建筑施工技术领域。
背景技术
随着城市高层建筑的兴起和发展,桩基工程使用较多。一般桩基工程中,桩基承受上部压荷载的作用需要予以检测,一般这些检测方式是在试验室进行,因此需要提供一些检测装置,因而需要更加精确地进行。根据建筑施工的需要,需要采用合适的装置进行试验检测,以便能够提高建筑施工的安全性,提高其使用效率,为进行建筑施工提供较好的依据。
实用新型内容
本实用新型的目的在于提供一种桩基础竖向承载力检测装置,以便更好地进行建筑施工过程中,针对建筑桩的承载力进行检测,便于更好地施工。
为了实现上述目的,本实用新型的技术方案如下。
一种桩基础竖向承载力检测装置,在地基下部设置有测试桩,测试桩上部连接有钢筋柱,钢筋柱上焊接有反力梁;反力梁的两侧位置下方的地基上设置有反力桩,反力桩上设置有千斤顶,千斤顶上设置有测力传感器;钢筋柱两侧位置上设置有位移传感器。
进一步地,位移传感器采用磁性基座固定在钢筋柱上。
该实用新型装置中,利用反力桩给测试桩提供反力进行测试,在测试桩的两侧各打一根反力桩作为锚桩,测试桩的上部位置设置钢筋柱,而不灌注混凝土。固定负荷加载在反力梁上,反力梁两端支撑在反力桩桩顶。每根反力桩提供不低于5000kN的抗压承载力;从而使得反力桩7桩端进入卵石层800mm,桩长约25.50m,桩顶位于标高35.50m,桩径、桩身混凝相同。每级荷载施加后按第5min、15min、30min、45min、60min测读桩顶上拔量,以后每隔30min测试桩上拔稳定标准:每一小时内的桩顶上拔量不超过0.1mm,并连续出现两次(从分级荷载开始,按1.5h连续三次每30min上拔观测值计算)。当桩顶上拔速率达到相对稳定标准时,再施加下一级荷载。卸载时,每级荷载维持1h,按第15min、30min、60min测读桩顶上拔量后,即可卸下一级荷后,应测读桩顶残余上拔量,维持时间为3h,测读时间为第15min、30min,以后每隔30min测试。
该实用新型的有益效果在于:该实用新型装置能够有效地针对测试桩进行施工测试,以便更加安全地进行施工,且施工测试方式简单,提高了建筑施工桩的检测快捷性和安全性,有助于建筑施工打桩。
附图说明
图1是本实用新型实施例中所使用装置结构示意图。
图中标记说明:1、地基;2、位移传感器;3、钢筋柱;4、反力梁;5、测力传感器;6、千斤顶;7、反力桩;8、测试桩。
具体实施方式
下面结合附图对本实用新型的具体实施方式进行描述,以便更好的理解本实用新型。
如图1所示的桩基础竖向承载力检测装置,在地基1下部设置有测试桩8上部连接有钢筋柱3,钢筋柱3上焊接有反力梁4;反力梁4的两侧位置下方的地基1上设置有反力桩7,反力桩7上设置有千斤顶6,千斤顶6上设置有测力传感器5;钢筋柱3两侧位置上设置有位移传感器2。位移传感器2采用磁性基座固定在钢筋柱3上。
该实用新型装置中,利用反力桩7给测试桩8提供反力进行测试,在测试桩8的两侧各打一根反力桩7作为锚桩,测试桩8的上部的只设置钢筋柱3,而不灌注混凝土。固定负荷加载在反力梁4上,反力梁4两端支撑在反力桩7桩顶。每根反力桩7提供不低于5000kN的抗压承载力;从而使得反力桩7桩端进入卵石层800mm,桩长约25.50m,桩顶位于标高35.50m,桩径、桩身混凝相同。每级荷载施加后按第5min、15min、30min、45min、60min测读桩顶上拔量,以后每隔30min测试桩上拔稳定标准:每一小时内的桩顶上拔量不超过0.1mm,并连续出现两次(从分级荷载开始,按1.5h连续三次每30min上拔观测值计算)。当桩顶上拔速率达到相对稳定标准时,再施加下一级荷载。卸载时,每级荷载维持1h,按第15min、30min、60min测读桩顶上拔量后,即可卸下一级荷后,应测读桩顶残余上拔量,维持时间为3h,测读时间为第15min、30min,以后每隔30min测试。
以上所述是本实用新型的优选实施方式,应当指出,对于本技术领域的普通技术人员来说,在不脱离本实用新型原理的前提下,还可以做出若干改进和润饰,这些改进和润饰也视为本实用新型的保护范围。

Claims (2)

1.一种桩基础竖向承载力检测装置,在地基下部设置有测试桩,其特征在于:所述测试桩上部连接有钢筋柱,所述钢筋柱上焊接有反力梁;所述反力梁的两侧位置下方的地基上设置有反力桩,所述反力桩上设置有千斤顶,所述千斤顶上设置有测力传感器;所述钢筋柱两侧位置上设置有位移传感器。
2.根据权利要求1所述的桩基础竖向承载力检测装置,其特征在于:所述位移传感器采用磁性基座固定在钢筋柱上。
CN201420031446.6U 2014-01-20 2014-01-20 桩基础竖向承载力检测装置 Expired - Fee Related CN203701158U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420031446.6U CN203701158U (zh) 2014-01-20 2014-01-20 桩基础竖向承载力检测装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420031446.6U CN203701158U (zh) 2014-01-20 2014-01-20 桩基础竖向承载力检测装置

Publications (1)

Publication Number Publication Date
CN203701158U true CN203701158U (zh) 2014-07-09

Family

ID=51051614

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420031446.6U Expired - Fee Related CN203701158U (zh) 2014-01-20 2014-01-20 桩基础竖向承载力检测装置

Country Status (1)

Country Link
CN (1) CN203701158U (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104674857A (zh) * 2015-02-11 2015-06-03 王继忠 一种即打即压的桩基承载力检测方法
CN105040753A (zh) * 2015-08-06 2015-11-11 南昌永祺科技发展有限公司 预埋式位移数据采集系统
CN106677230A (zh) * 2016-11-17 2017-05-17 长安大学 一种桩土复合地基承载力检测装置
CN107975075A (zh) * 2017-11-08 2018-05-01 浙江理工大学 一种用于既有受荷工程基桩检测结构措施的施工工艺
CN108252337A (zh) * 2018-02-09 2018-07-06 重庆三峡学院 一种桩基拖换的多功能应力测试装置

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104674857A (zh) * 2015-02-11 2015-06-03 王继忠 一种即打即压的桩基承载力检测方法
CN105040753A (zh) * 2015-08-06 2015-11-11 南昌永祺科技发展有限公司 预埋式位移数据采集系统
CN106677230A (zh) * 2016-11-17 2017-05-17 长安大学 一种桩土复合地基承载力检测装置
CN106677230B (zh) * 2016-11-17 2019-04-23 长安大学 一种桩土复合地基承载力检测装置
CN107975075A (zh) * 2017-11-08 2018-05-01 浙江理工大学 一种用于既有受荷工程基桩检测结构措施的施工工艺
CN107975075B (zh) * 2017-11-08 2020-05-12 浙江理工大学 一种用于既有受荷工程基桩检测结构措施的施工工艺
CN108252337A (zh) * 2018-02-09 2018-07-06 重庆三峡学院 一种桩基拖换的多功能应力测试装置

Similar Documents

Publication Publication Date Title
CN203701158U (zh) 桩基础竖向承载力检测装置
CN202644541U (zh) 一种狭窄场地超深基坑施工的钢支撑结构
CN204255832U (zh) 锚栓抗拔试验加载装置
CN107012896A (zh) 一种多功能桩基模型试验系统及其组装和试验方法
CN101761090A (zh) 海上风电机组的空间桁架式多桶基础
CN202865828U (zh) 一种快速排水管桩
CN101851923B (zh) 一种支撑柱施工安装方法
CN204212177U (zh) 一种兼做立柱桩的坑中坑连续墙结构
CN204825999U (zh) 单桩竖向抗拔静载试验装置
CN104563170B (zh) 海上风电单桩基础水平承载力试验反力装置及其施工方法
CN202969387U (zh) 桩孔格构柱定位装置
CN206486912U (zh) 预制混凝土构件沉降调整装置
CN203782760U (zh) 一种u型槽结构自调节抗浮构造
CN205000351U (zh) 一种施工效率高的钢管桩
CN203834492U (zh) 一种水中大直径圆形钢板桩围堰
CN203821248U (zh) 一种钢管拱主拱拼装支撑体系
CN103835319B (zh) 混凝土扩盘半面桩受压状态下现场可观测实桩试验方法
CN203846494U (zh) 腰梁土锚杆分段连接结构
CN107664602A (zh) 一种机械加载式力学实验系统及使用方法
CN202247830U (zh) 新型水中钢平台
CN103362123A (zh) 倒y形灌注桩及其施工方法
CN203569600U (zh) 一种桩底基岩载荷试验装置
CN102322052B (zh) 自平衡式地基载荷试验装置
CN201896319U (zh) 塔吊基础节与钢格构柱连接的转换平台
CN203684259U (zh) 一种用于500kV变电站出线构架的翼缘式基础

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140709

Termination date: 20150120

EXPY Termination of patent right or utility model