CN203655331U - Hydraulic support for coal mine paste mining with filling - Google Patents
Hydraulic support for coal mine paste mining with filling Download PDFInfo
- Publication number
- CN203655331U CN203655331U CN201320857856.1U CN201320857856U CN203655331U CN 203655331 U CN203655331 U CN 203655331U CN 201320857856 U CN201320857856 U CN 201320857856U CN 203655331 U CN203655331 U CN 203655331U
- Authority
- CN
- China
- Prior art keywords
- hinged
- filling
- jack
- tail boom
- support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 239000003245 coal Substances 0.000 title claims abstract description 23
- 238000005065 mining Methods 0.000 title abstract description 8
- 230000000087 stabilizing effect Effects 0.000 claims abstract description 25
- 230000000630 rising effect Effects 0.000 claims description 17
- 238000010276 construction Methods 0.000 claims description 9
- 238000002360 preparation method Methods 0.000 abstract description 15
- 238000000034 method Methods 0.000 abstract description 3
- 230000001174 ascending effect Effects 0.000 abstract 2
- 238000005204 segregation Methods 0.000 abstract 1
- 230000000694 effects Effects 0.000 description 9
- 238000002955 isolation Methods 0.000 description 6
- 230000006870 function Effects 0.000 description 4
- 238000012856 packing Methods 0.000 description 3
- TVEXGJYMHHTVKP-UHFFFAOYSA-N 6-oxabicyclo[3.2.1]oct-3-en-7-one Chemical compound C1C2C(=O)OC1C=CC2 TVEXGJYMHHTVKP-UHFFFAOYSA-N 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 230000009993 protective function Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 239000006210 lotion Substances 0.000 description 1
- 239000000178 monomer Substances 0.000 description 1
- 239000002023 wood Substances 0.000 description 1
Images
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The utility model discloses a hydraulic support for coal mine paste mining with filling, and belongs to the support equipment of a coal mining working surface. The top beam of a filling support is supported through uprights, and is connected with a base through a stabilizing mechanism; the top beam and a hinged tail beam are connected through a hinge pin, one end of a tail beam jack is hinged with the top beam, and the other end of the tail beam jack is hinged with a hinged tail beam; the uprights are placed on the base; a separating mechanism is arranged on the tail of the base; the stabilizing mechanism consists of an oblique beam, a front connecting rod and a rear connecting rod; the front row of uprights are located in front of the stabilizing mechanism so as to support the front part of the top beam, and the rear rows of uprights are located behind the stabilizing mechanism so as to support the rear part of the top beam; one end of an ascending jack is hinged with the base, and the other end of the ascending jack is hinged with a segregation board. The hydraulic support has the advantages of being applicable to filling various pastes into the working surface; furthermore, in the process of mining coal with filling, a support to-be-filled area can be conveniently and quickly obtained so as to set a filling separator; meanwhile, under the premise of guaranteeing to effectively seal the separator and prevent the filling paste from flowing into the working surface, the working time for filling preparation can be shortened, the manual labor can be reduced, and the paste filling working efficiency can be improved.
Description
Technical field
The utility model relates to a kind of support apparatus of coal-face, particularly a kind of hydraulic support for coal mine paste filling exploitation.
Background technology
Conventional hydraulic support major function is supporting roof of coal face, and in paste body filling coal mining process, carries out filling isolation preparation in the goaf that workman need form after support moves frame.This requires paste filling hydraulic bracket having outside the function of supported face top board, also needs to carry out supporting management to moving the filling area for the treatment of producing after frame, thereby provides safe working space for filling preparation.Apply existing support apparatus and can not meet filling coal mining supporting requirement, also need to take in addition artificial measures, carry out supporting management as manually set up the measures such as wood point post or supporting monomer column to treat filling area.After filling preparation completes, need reclaim the support apparatus of having set up.The too much manual work of whole filling isolation set-up procedure causes filling coal mining mechanization degree low, and whole work efficiency is difficult to improve.
Patent CN 102042026A discloses a kind of filling hydraulic support with tail boom.This support is after moving frame, and when workman carries out filling preparation, support tail boom can overturn and lift supporting roof.After filling preparation completes, tail boom is regained vertical with back timber, and now tail boom can be used as division board.But tail boom top is to take filling quarantine measures key position.Described in this patent, the problem of support is, it is only after tail boom upset is regained, and workman could isolate preparation to this tail boom top.Roof timbering measure now still must be manually set, and workman just can carry out the isolation preparation work of tail boom top.Therefore, above-mentioned this hydraulic support could not solve the filling area supporting problem for the treatment of.
Patent CN102269010A discloses a kind of integrated paste filling hydraulic bracket.This support comprises side arm and after-frame.After-frame back timber afterbody is provided with back bar, and this back bar is fixed, in the time carrying out paste body filling, cannot regain, and certainly will have influence on paste body filling and connect top effect.
In sum, under the prerequisite of assurance filling effect, combine and adopt in technology at paste body filling at present, still exist and treat filling area roof timbering problem of management.
Utility model content
The purpose of this utility model is that a kind of hydraulic support for coal mine paste filling exploitation will be provided, and solution preparation time before coal mine filling is longer, and hand labor intensity is large, the problem that efficiency is lower.
The technical scheme that realizes the purpose of this utility model employing is as follows:
This coal mine filling support comprises: back timber, stabilizing mechanism, column, hinged tail boom, tail boom jack, interrupter, rising jack and base; Back timber is by upright supports; Back timber is connected with base by stabilizing mechanism; Between back timber and hinged tail boom for bearing pin is connected; Tail boom jack one end and back timber are hinged, and the tail boom jack other end and hinged tail boom are hinged; Base is used for laying described column; Base afterbody is equipped with interrupter; Stabilizing mechanism is made up of cant beam, front rod and back link; Totally four, column, two is that a component is two groups, is respectively front-seat column and rear row's column; Front-seat column is positioned at stabilizing mechanism front, supporting top beam front portion, and rear row's column is positioned at stabilizing mechanism rear, supporting top beam rear portion; Interrupter comprises division board and lower division board, and rising jack one end and base are hinged, and on the rising jack other end, division board is hinged.
Described hinged tail boom is box-structure, or frame construction.
Described upper division board is box-structure, or frame construction.
Described lower division board is box-structure, or frame construction.
Described stabilizing mechanism is quadric chain.
Beneficial effect, owing to adopting such scheme, in the time carrying out filling isolation preparation, only hinged tail boom 4 need be routed up to supporting treats filling area, workman can carry out filling isolation preparation in the scope that has supporting, manually treats filling area support work without workman.Before paste body filling, hinged tail boom 4 rotations are regained, and do not affect support afterbody packing job, and have guaranteed paste body filling effect.It is longer to have solved before coal mine filling the preparation time, and hand labor intensity is large, and the problem that efficiency is lower has reached the utility model object.
Advantage: in filling coal mining, quick-setting is treated filling area supporting, is guaranteeing to treat filling area roof timbering, under the prerequisite that prevents from treating to fall filling area cash hurts sb.'s feelings, cancels the artificial support work of workman, reduces hand labor, improves filling integral operating efficiency.
Accompanying drawing explanation
Fig. 1 side-looking structure chart of the present utility model.
In figure: 1, back timber; 2, quadric chain; 201, cant beam; 202, front rod; 203, back link; 3, column; 301, front-seat column; 302, rear row's column; 4, hinged tail boom; 5, tail boom jack; 6, division board; 601, upper division board; 602, lower division board; 7, rising jack; 8, base.
The specific embodiment
Embodiment 1: this coal mine filling support, comprises back timber 1, stabilizing mechanism 2, column 3, hinged tail boom 4, tail boom jack 5, interrupter 6, rising jack 7 and base 8; Back timber 1 is supported by column 3; Back timber 1 is connected with base 8 by stabilizing mechanism 2; Between back timber 1 and hinged tail boom 4 for bearing pin is connected; Tail boom jack 5 one end and back timber 1 are hinged, and tail boom jack 5 other ends and hinged tail boom 4 are hinged; Base 8 is for laying described column 3; Base 8 afterbodys are equipped with interrupter 6; Stabilizing mechanism 2 is made up of cant beam 201, front rod 202 and back link 203; Totally four, column 3, two is that a component is two groups, is respectively front-seat column 301 and rear row's column 302; Front-seat column 301 is positioned at stabilizing mechanism 2 fronts, supporting top beam 1 front portion, and rear row's column 302 is positioned at stabilizing mechanism 2 rears, supporting top beam 1 rear portion;
Hinged tail boom 4, under 5 effects of tail boom jack, can be routed up completely until parallel with back timber 1, and under this duty, hinged tail boom 4 can supporting be treated filling area, provides space for workman carries out filling preparation;
Hinged tail boom 4, under tail boom jack 5 effect, can rotate withdrawal, until be less than or equal to 90 ° with back timber 1 angle, under this duty, hinged tail boom 4 is regained, and prepares support afterbody to treat that filling area carries out packing job;
Interrupter 6 comprises division board 601 and lower division board 602, rising jack 7 one end and base 8 are hinged, on rising jack 7 other ends, division board 601 is hinged, and upper division board 601 can stretch out under 7 effects of rising jack in lower division board 602, and the height of realizing interrupter 6 with this regulates.
Described hinged tail boom 4 is box-structures, or frame construction.
Described upper division board 601 is box-structures, or frame construction.
Described lower division board 602 is box-structures, or frame construction.
Described stabilizing mechanism 2 is quadric chains.
Its preferably the specific embodiment be:
This coal mine filling support, totally four of its central posts 3, two is that a component is two groups, is respectively front-seat column 301 and rear row's column 302; Stabilizing mechanism 2 is made up of cant beam 201, front rod 202 and back link 203; Back timber 1 is hinged with column 3; Back timber 1 is hinged with cant beam 201; Between back timber 1 and hinged tail boom 4 for bearing pin is connected; Tail boom jack 5 one end and back timber 1 are hinged, and tail boom jack 5 other ends and hinged tail boom 4 are hinged; Base 8 is hinged with column 3; Base 8 afterbodys are equipped with interrupter 6; Front-seat column 301 is positioned at stabilizing mechanism 2 fronts, supporting top beam 1 front portion, and rear row's column 302 is positioned at stabilizing mechanism 2 rears, supporting top beam 1 rear portion; Interrupter 6 comprises division board 601 and lower division board 602, rising jack 7 one end and base 8 are hinged, on rising jack 7 other ends, division board 601 is hinged, and upper division board 601 can stretch out under 7 effects of rising jack in lower division board 602, and the height of realizing interrupter 6 with this regulates.
The concrete enforcement of practical function:
Treat that filling area props up the realization of protective function.Before support moves frame, rising jack 7 should be regained, under 7 effects of rising jack, upper division board 601 is regained completely, shows and abdicates space for hinged tail boom 4.After support moves frame and completes, tail boom jack 5 is stretched out, hinged tail boom 4 is turn to and back timber 1 parastate, full face support is routed up hinged tail boom 4 successively by this step, full face can be realized and be treated that filling area props up protective function, and workman can screen and in region, isolate filling preparation at hinged tail boom 4.
The realization of support isolation filling function.After filling preparation completes, tail boom jack 5 is regained, hinged tail boom 4 is returned back to and back timber 1 plumbness, now go up division board 601 and under rising jack 7 effect, stretch out until contact top board, at support afterbody formation lotion envelope wall.Upper division board 601 is stretched out successively by this step in full face, forms the airtight filling area for the treatment of at support afterbody, to carry out packing job.
Obviously, above-described embodiment is only for example is clearly described, and the not restriction to embodiment.For those of ordinary skill in the field, can also make other changes in different forms on the basis of the above description.Here without also giving exhaustive to all embodiments.And the apparent variation of being extended out thus or variation are still among protection domain of the present utility model.
Claims (5)
1. for a hydraulic support for coal mine paste filling exploitation, it is characterized in that: this coal mine filling support comprises: back timber, stabilizing mechanism, column, hinged tail boom, tail boom jack, interrupter, rising jack and base; Back timber is by upright supports; Back timber is connected with base by stabilizing mechanism; Between back timber and hinged tail boom for bearing pin is connected; Tail boom jack one end and back timber are hinged, and the tail boom jack other end and hinged tail boom are hinged; Base is used for laying described column; Base afterbody is equipped with interrupter; Stabilizing mechanism is made up of cant beam, front rod and back link; Totally four, column, two is that a component is two groups, is respectively front-seat column and rear row's column; Front-seat column is positioned at stabilizing mechanism front, supporting top beam front portion, and rear row's column is positioned at stabilizing mechanism rear, supporting top beam rear portion; Interrupter comprises division board and lower division board, and rising jack one end and base are hinged, and on the rising jack other end, division board is hinged.
2. a kind of hydraulic support for coal mine paste filling exploitation according to claim 1, is characterized in that: described hinged tail boom is box-structure, or frame construction.
3. a kind of hydraulic support for coal mine paste filling exploitation according to claim 1, is characterized in that: described upper division board is box-structure, or frame construction.
4. a kind of hydraulic support for coal mine paste filling exploitation according to claim 1, is characterized in that: described lower division board is box-structure, or frame construction.
5. a kind of hydraulic support for coal mine paste filling exploitation according to claim 1, is characterized in that: described stabilizing mechanism is quadric chain.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320857856.1U CN203655331U (en) | 2013-12-24 | 2013-12-24 | Hydraulic support for coal mine paste mining with filling |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320857856.1U CN203655331U (en) | 2013-12-24 | 2013-12-24 | Hydraulic support for coal mine paste mining with filling |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203655331U true CN203655331U (en) | 2014-06-18 |
Family
ID=50921730
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201320857856.1U Expired - Lifetime CN203655331U (en) | 2013-12-24 | 2013-12-24 | Hydraulic support for coal mine paste mining with filling |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203655331U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105626117A (en) * | 2016-02-25 | 2016-06-01 | 郑州四维矿业机械有限责任公司 | Hydraulic support and jacking beam for hydraulic support |
CN105626115A (en) * | 2016-02-25 | 2016-06-01 | 郑州四维矿业机械有限责任公司 | Backfilling hydraulic support |
CN109252891A (en) * | 2018-11-05 | 2019-01-22 | 徐州中矿大贝克福尔科技股份有限公司 | A kind of paste body filling continuous flexible sealing device and partition method |
-
2013
- 2013-12-24 CN CN201320857856.1U patent/CN203655331U/en not_active Expired - Lifetime
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105626117A (en) * | 2016-02-25 | 2016-06-01 | 郑州四维矿业机械有限责任公司 | Hydraulic support and jacking beam for hydraulic support |
CN105626115A (en) * | 2016-02-25 | 2016-06-01 | 郑州四维矿业机械有限责任公司 | Backfilling hydraulic support |
CN109252891A (en) * | 2018-11-05 | 2019-01-22 | 徐州中矿大贝克福尔科技股份有限公司 | A kind of paste body filling continuous flexible sealing device and partition method |
CN109252891B (en) * | 2018-11-05 | 2023-09-19 | 徐州中矿大贝克福尔科技股份有限公司 | Paste filling continuous flexible sealing device and isolation method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105221177B (en) | Four columns are floating to shake formula hydraulic support | |
CN205047241U (en) | Tunnel quick travel formula advance support support | |
CN106351679A (en) | Soil similar coal working face fully sealed shield support device | |
CN206625858U (en) | A kind of automatic moving type forepoling hydraulic support with side guard plate | |
CN101440711A (en) | Large extraction high caving roof coal hydraulic support | |
CN203655331U (en) | Hydraulic support for coal mine paste mining with filling | |
CN201554481U (en) | Filling supporting hydraulic support | |
CN106761874A (en) | A kind of automatic moving type forepoling hydraulic support with side guard plate | |
CN203412606U (en) | Spider type hydraulic bracket in parallel working of coal mining and filling | |
CN203362199U (en) | End-head hydraulic support for fully mechanized mining face | |
CN206419050U (en) | A kind of alley hydraulic support of supporting variable-width | |
CN101509388B (en) | Tunnel ahead support stent | |
CN203008944U (en) | Comprehensive fore support for excavation head | |
CN106703853A (en) | Repeated-free-support temporary support equipment | |
CN201460938U (en) | Forward supporting type end hydraulic support | |
CN201381864Y (en) | Split-type front and rear end head hydraulic support | |
CN209040871U (en) | A kind of compound lift bottom passage advanced stand device | |
CN202300450U (en) | Transition hydraulic support for gob-side entry retaining | |
CN204283455U (en) | Novel thin coal seam filling hydraulic support | |
CN207647534U (en) | A kind of face end hydraulic support | |
CN202215273U (en) | Front-arranged single oscillating bar type end hydraulic support | |
CN202645610U (en) | Hydraulic support and engineering machinery | |
CN207420611U (en) | A kind of end hydraulic support of achievable Sub-Level Caving function | |
CN109139073A (en) | A kind of compound lift bottom passage advanced stand device | |
CN201314238Y (en) | Great mining height hydraulic bracket for top coal caving |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C56 | Change in the name or address of the patentee | ||
CP03 | Change of name, title or address |
Address after: 221008 Jiangsu, Xuzhou Jinshan Road, north side of Xuzhou Software Park, room 11, No. 1213 Patentee after: XUZHOU CUMT BACKFILL TECHNOLOGY Co.,Ltd. Address before: 221008 Jiangsu city in Xuzhou Province, the liberation of South Park Mine Technology Pioneering Park Room 216 Patentee before: Xuzhou CUMT Backfill Technology Co.,Ltd. |
|
CX01 | Expiry of patent term |
Granted publication date: 20140618 |
|
CX01 | Expiry of patent term |