CN203583304U - Carbonate rock filling foundation stagnant water structure - Google Patents

Carbonate rock filling foundation stagnant water structure Download PDF

Info

Publication number
CN203583304U
CN203583304U CN201320726764.XU CN201320726764U CN203583304U CN 203583304 U CN203583304 U CN 203583304U CN 201320726764 U CN201320726764 U CN 201320726764U CN 203583304 U CN203583304 U CN 203583304U
Authority
CN
China
Prior art keywords
carbonate rock
stagnant water
rock filling
foundation
filling foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320726764.XU
Other languages
Chinese (zh)
Inventor
张建忠
张建磊
袁江文
朱军
罗会军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Zhengye Engineering & Investment Inc Ltd
Original Assignee
Guizhou Zhengye Engineering & Investment Inc Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Zhengye Engineering & Investment Inc Ltd filed Critical Guizhou Zhengye Engineering & Investment Inc Ltd
Priority to CN201320726764.XU priority Critical patent/CN203583304U/en
Application granted granted Critical
Publication of CN203583304U publication Critical patent/CN203583304U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

The utility model discloses a carbonate rock filling foundation stagnant water structure. The carbonate rock filling foundation stagnant water structure comprises a carbonate rock filling foundation (1), wherein the upper surface of the carbonate rock filling foundation (1) is provided with a stagnant water layer (2), the upper surface of the stagnant water layer (2) is provided with a hardened layer (3), the thickness of the stagnant water layer (2) is 0.5-3.0 meters, and the thickness of the hardened layer (3) is 0.3-0.5 meter. An arrangement method of the carbonate rock filling foundation stagnant water structure comprises the following steps: I, carrying out tamping and rolling treatment on the carbonate rock filling foundation (1); II, laying clay on the surface of the carbonate rock filling foundation (1) subjected to the tamping and rolling treatment in a layering manner, and after finishing the laying of each layer of clay, flatly rolling by adopting a road roller till the thickness of each layer of clay reaches 0.3-1.5 meters; and III, laying natural-grading hard rocks on the laid stagnant water layer (2), wherein the thickness of the natural-grading hard rocks is 0.3-0.5 meter, and forming the hardened layer (3) by rolling the natural-grading hard rocks. The carbonate rock filling foundation stagnant water structure is used for solving the problem that the instability of the carbonate rock filling foundation is caused by long-term immersion and erosion of the carbonate rock filling foundation in rainwater.

Description

A kind of carbonate rock fill foundation backwater structure
Technical field
The utility model belongs to carbonate rock fill foundation backwater waterproof technique, relates in particular to a kind of carbonate rock fill foundation backwater structure.
Background technology
Carbonate rock is distributed widely in western China, this area important feature be that landforms height fluctuations is large, urban construction, industrial land are all restricted to a great extent, therefore there will be large-scale earthwork evacuation and backfill, form boulder high fill foundation, these foundations very major part are comprised of soluble carbonate salt rock; West area is throughout the year in heavy showers period in addition, rainwater is very harmful to soluble carbonate salt rock, under carbonate rock ground maceration under long-term rain steeps and corrodes, foundation stability can be affected, in order to prevent that carbonate ground is subject to rainwater invade bubble and corrode, conventionally adopt that french drain is set under carbonate rock ground carries out draining, but the geotextiles that lay on french drain top layer is adhered to by fine particle easily, affect the worry water effect of geotextiles, cause blind drainage effect bad.
Summary of the invention
The technical problems to be solved in the utility model: a kind of carbonate rock fill foundation backwater structure is provided, invades for a long time bubble and corrode in rainwater to solve carbonate rock fill foundation, cause the problems such as carbonate rock fill foundation stability is bad.
Utility model technical scheme:
A kind of carbonate rock fill foundation backwater structure, it comprises carbonate rock fill foundation, and carbonate rock fill foundation upper surface is aquitard, and aquitard upper surface is hardened layer, and the thickness of aquitard is 0.3m ~ 1.5m rice, the thickness of hardened layer is 0.3-0.5 rice.
The raw material of aquitard are clay.
Hardened layer raw material are natural grading hard rock, and rock particle diameter is not more than 300 millimeters, and clay content is not more than 5%, and compressive strength is not less than 30Mpa.
The utility model beneficial effect:
Clay has the advantages such as water permeability is weak, compacting rear stability is good, intensity is higher, capillarity is little, the utility model utility model is utilized this feature of clay, at rammer, grind on carbonate rock boulder fill foundation after treatment and lay such one deck clay as aquitard, for intercepting surface water and immersion and the erosion of natural rainfall to deep foundation, to reduce the impact of surface water on foundation stability; On aquitard top, be separately equipped with one deck boulder after treatment and ram stone roller body, this is hardened layer, and its effect is not from brush, run off by rainwater for protection aquitard clay on the one hand; On the other hand, clay there will be under external force muddy phenomenon, thereby affects the attractive in appearance of road surface after soaked by rainwater; Aquitard raw material clay is the natural soil body, can gather materials on the spot, and aboundresources, small investment, aquitard arranges simply, easy construction, and effectively backwater, greatly extend the application life of carbonate rock fill foundation, solved carbonate rock fill foundation and in rainwater, invaded for a long time bubble and corrode, caused the problems such as carbonate rock fill foundation stability is bad.
accompanying drawing explanation:
Fig. 1 is the utility model structural representation.
the specific embodiment:
A kind of carbonate rock fill foundation backwater structure, it comprises carbonate rock fill foundation 1, and carbonate rock fill foundation 1 upper surface is aquitard 2, and aquitard 2 upper surfaces are hardened layers 3, the thickness of aquitard 2 is 0.3m ~ 1.5m rice, and the thickness of hardened layer 3 is 0.3-0.5 rice.
The raw material of aquitard 2 are clay.
Hardened layer 3 raw material are natural grading hard rock, and rock particle diameter is not more than 300 millimeters, and clay content is not more than 5%, and compressive strength is not less than 30Mpa.
The method to set up of described carbonate rock fill foundation backwater structure, it comprises the steps:
Step 1, to carbonate rock fill foundation 1 ram grind process,
Step 2, ramming stone roller carbonate rock fill foundation 1 after treatment when laying to design height, on its surface, lay clay, clay adopts layering to lay, after every layer of laying, adopt the flat stone roller of road roller, its road roller is 25t, construction travel speed is no more than 2m/h, while rolling, take the superimposed overlap joint of itemize, each overlapping 1/4 ~ 1/2 muller, coefficient of consolidation is not less than 0.94, to guarantee effective backwater, until thickness reaches 0.3-1.5 rice, become aquitard 2, through aquitard after treatment like this, can effectively intercept surface water and immersion and the erosion of natural rainfall to deep foundation, to reduce the impact of surface water on foundation stability.
Step 3, on the aquitard 2 of laying completion, lay natural grading hard rock, rock particle diameter is not more than 300 millimeters, clay content is not more than 5%, compressive strength is not less than 30Mpa, laying depth is at 0.3-0.5 rice, after rolling processing, be hardened layer 3, roll to process and adopt 25t, construction travel speed is no more than 2m/h road roller vibroroller cmpacting, while rolling, take the superimposed overlap joint of itemize, each overlapping 1/4 ~ 1/2 muller, rolling number of times is not less than 8 times, the last average settlement amount that rolls for twice is not more than 10mm, through the utility model hardened layer 3 after treatment, playing protection aquitard clay not from brush, run off by rainwater, having solved clay is subject to, after rainwater immersion, to there will be under external force muddy phenomenon, thereby affect the problem attractive in appearance on road surface.

Claims (3)

1. a carbonate rock fill foundation backwater structure, it comprises carbonate rock fill foundation (1), it is characterized in that: carbonate rock fill foundation (1) upper surface is aquitard (2), aquitard (2) upper surface is hardened layer (3), the thickness of aquitard (2) is 0.3m ~ 1.5m rice, and the thickness of hardened layer (3) is 0.3-0.5 rice.
2. a kind of carbonate rock fill foundation backwater structure according to claim 1, is characterized in that: the raw material of aquitard (2) are clay.
3. a kind of carbonate rock fill foundation backwater structure according to claim 1, is characterized in that: hardened layer (3) raw material are natural grading hard rock, and rock particle diameter is not more than 300 millimeters, and clay content is not more than 5%, and compressive strength is not less than 30Mpa.
CN201320726764.XU 2013-11-18 2013-11-18 Carbonate rock filling foundation stagnant water structure Expired - Fee Related CN203583304U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320726764.XU CN203583304U (en) 2013-11-18 2013-11-18 Carbonate rock filling foundation stagnant water structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320726764.XU CN203583304U (en) 2013-11-18 2013-11-18 Carbonate rock filling foundation stagnant water structure

Publications (1)

Publication Number Publication Date
CN203583304U true CN203583304U (en) 2014-05-07

Family

ID=50581249

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320726764.XU Expired - Fee Related CN203583304U (en) 2013-11-18 2013-11-18 Carbonate rock filling foundation stagnant water structure

Country Status (1)

Country Link
CN (1) CN203583304U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103556556A (en) * 2013-11-18 2014-02-05 贵州正业工程技术投资有限公司 Backwater structure of carbonate rock fill foundation and setting method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103556556A (en) * 2013-11-18 2014-02-05 贵州正业工程技术投资有限公司 Backwater structure of carbonate rock fill foundation and setting method thereof
CN103556556B (en) * 2013-11-18 2015-12-02 贵州正业工程技术投资有限公司 A kind of carbonate rock fill foundation backwater structure and method to set up thereof

Similar Documents

Publication Publication Date Title
CN103031836B (en) A kind of method of building road on new hydraulically filled sludge ground fast
CN102660936A (en) Method for realizing seepage prevention of bridge wall by means of polyvinyl chloride film
CN206828898U (en) A kind of roadbed for filling high liquid limit soil
CN103061225A (en) Rock salt railroad bed structure of section parallel to existing line and construction method of structure
CN108193648A (en) Plasticity panel homogeneous dam
CN113445396A (en) High-fill road foundation filling construction method for high liquid limit soil road section
CN106638545B (en) The Treatment of Expansive Soil Embankment structure and construction method that the improvement of cored method is reinforced
CN201502019U (en) Permeable ground structure
CN203583304U (en) Carbonate rock filling foundation stagnant water structure
CN206385525U (en) A kind of timber structure for preventing the high backfill earthwork from sinking
CN205223770U (en) Crowded close stake of rubble adds muscle roadbed structure
CN103556556B (en) A kind of carbonate rock fill foundation backwater structure and method to set up thereof
CN202850013U (en) Whole composite foundation structure for lime soil and anti-seepage membrane
CN203625741U (en) Roadbed filled with tailing sand
CN203514330U (en) Environment-friendly ecological reconstruction and restoration structure
CN206529659U (en) The Treatment of Expansive Soil Embankment structure that sandwich method improvement is reinforced
CN103132487A (en) Method of reducing horizontal displacement of concrete faced rockfill dam and concrete faced rockfill dam
CN103233447B (en) High concrete face rockfill dam seismic strengthening structure and construction method thereof
CN205000298U (en) Embankment dam dam facing slope protection structure
CN205369167U (en) Back -up sand gravel material weir dam body is thrown to aquatic
CN101003973A (en) Method for treating quasi-prepressing groundwork of artificial island
CN202850012U (en) Partial composite foundation structure for lime soil and anti-seepage membrane
CN204898645U (en) Building rubbish regeneration drainage CFG stake ground
CN203113358U (en) Clay sandstone cofferdam structure
CN203530994U (en) Stone slag field side slope ecological protection structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Shen Zhiping

Inventor after: Zhang Jianlei

Inventor after: Yuan Jiangwen

Inventor after: Zhu Jun

Inventor after: Luo Huijun

Inventor before: Zhang Jianzhong

Inventor before: Zhang Jianlei

Inventor before: Yuan Jiangwen

Inventor before: Zhu Jun

Inventor before: Luo Huijun

COR Change of bibliographic data
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140507

Termination date: 20181118