CN203518645U - Dedusting system of intermediate frequency furnace - Google Patents
Dedusting system of intermediate frequency furnace Download PDFInfo
- Publication number
- CN203518645U CN203518645U CN201320613990.7U CN201320613990U CN203518645U CN 203518645 U CN203518645 U CN 203518645U CN 201320613990 U CN201320613990 U CN 201320613990U CN 203518645 U CN203518645 U CN 203518645U
- Authority
- CN
- China
- Prior art keywords
- gathering arrester
- intermediate frequency
- frequency furnace
- dust gathering
- dust
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P10/00—Technologies related to metal processing
- Y02P10/25—Process efficiency
Landscapes
- Filtering Of Dispersed Particles In Gases (AREA)
Abstract
The utility model relates to a dedusting system of an intermediate frequency furnace. The dedusting system comprises a dust collection hood, a branch airflow pipeline, a main airflow pipeline, an adsorption and spray barrel, a settling vat, a volute fan and a water film dedusting barrel set. The dust collection hood is installed on one side of the top of the intermediate frequency furnace, wherein a lower-end opening of the dust collection hood extends to the position over a furnace mouth and is larger than the furnace mouth, the inner diameter of the dust collection hood decreases gradually and smoothly from bottom to top, and the upper end of the dust collection hood is connected with the branch airflow pipeline through a rotary flange plate. The branch airflow pipeline is connected to the adsorption and spray barrel through the main airflow pipeline. The adsorption and spray barrel is connected to the settling vat. The settling vat is connected to the water film dedusting barrel set. The volute fan is installed between the settling vat and the water film dedusting barrel set. The dedusting system of the intermediate frequency furnace is simple in structure, good in dust suction effect, and wide in application range.
Description
Technical field
The utility model relates to a kind of intermediate frequency furnace dust pelletizing system.
Background technology
The intermediate frequency furnace of the general use of hot investment casting is all below 300KG, for small intermediate frequency stove, generally when Metal Melting, easily produce flue dust, the non-ferrous metal such as melting copper particularly, serious environment pollution, make plant operations environment very severe, dusty gas also causes certain injury to workman's health, therefore needs to utilize the method for collecting flue dust to eliminate these toxic and harmfuls of purification.The easiest method is on intermediate frequency furnace charge door, to add a vertical cover, utilizes blower fan that flue dust is taken away.But vertical inlet scoop is very inconvenient to field worker operation, and air port is too high, cannot effectively collect flue dust, and most of flue dust is escaped, and efficiency is not high; Air port is too low, and workman easily encounters head, and feeds in raw material and remove the gred very inconvenient.If intermediate frequency furnace is near window, while blowing so, stove cigarette can blow partially, is more unfavorable for collecting.
Summary of the invention
In order to solve above-mentioned technical problem, the purpose of this utility model is to provide a kind of intermediate frequency furnace dust pelletizing system, and this system can effectively be collected flue dust, facilitates again the reinforced slagging-off of workman simultaneously.
In order to realize above-mentioned object, the utility model has adopted following technical scheme:
A kind of intermediate frequency furnace dust pelletizing system, comprise dust gathering arrester, divide airflow pipeline, primary air pipeline, absorption spray bucket, settling vat, spiral case blower fan and water film dedusting bucket group, described dust gathering arrester is arranged on a side of intermediate frequency furnace top, the lower ending opening of dust gathering arrester extends to directly over fire door, and the lower ending opening of dust gathering arrester is greater than fire door, the internal diameter of described dust gathering arrester smoothly successively decreases from down to up, the upper end of described dust gathering arrester is connected by rotary flange dish with a minute airflow pipeline, within described minute, airflow pipeline is connected to absorption spray bucket by primary air pipeline, described spray bucket is connected to settling vat, settling vat is connected to water film dedusting bucket group, and described spiral case assembling is between settling vat and water film dedusting bucket group.
As preferred version: the position near rotary flange dish in described dust gathering arrester is also provided with air door, and described air door is connected with the pull bar that hangs over dust gathering arrester outside.Arranging of air door facilitates switching tube paths state, improve dust collection efficiency, and it is more convenient by pull bar, to control air door.
As preferred version: described dust gathering arrester is provided with handle, and the lower ending opening of dust gathering arrester is apart from fire door 25-30cm.Arranging and facilitating employee's rotary collecting dust hood of handle, adjusts optimum position, and dust gathering arrester both facilitated from the height of fire door that employee is reinforced to slag tap, and convenience and high-efficiency is collected flue dust again.
As preferred version: described minute airflow pipeline and primary air pipeline are the pipe that the iron sheet of thickness 2-3mm is made, and all scribble antirust paint on interior lateral wall.Effectively the corrosivity of opposing flue dust, extends the pipeline life-span.
As preferred version: a described absorption spray bucket internal upper part is provided with layer of active carbon filter course, on the madial wall of activated carbon filter layer below, a plurality of spray nozzles are installed, the bottom of described absorption spray bucket is also provided with the circulating pump of bottom of the barrel current being sent back to spray nozzle.
As preferred version: described absorption spray bucket, the bottom of settling vat and water film dedusting bucket group is equipped with firth outlet hole.Convenient in time to clearing up in bucket.
The utility model, owing to having adopted above-mentioned technical scheme, is arranged on dust gathering arrester the side of intermediate frequency furnace, and the opening of dust gathering arrester is greater than to fire door, can under the prerequisite that does not affect operation, better collect flue dust; Dust gathering arrester is connected with a minute airflow pipeline by rotary flange dish, dust gathering arrester can be take and divide an airflow pipeline to be rotated as axle center, and then make the position-adjustable of dust gathering arrester, has improved the pick-up performance of dust gathering arrester; The utility model is simple in structure, and pick-up performance is good, applied widely.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
The specific embodiment
Below in conjunction with accompanying drawing, the specific embodiment of the present utility model is made a detailed explanation.
A kind of intermediate frequency furnace dust pelletizing system as shown in Figure 1, comprise dust gathering arrester 2, divide airflow pipeline 5, primary air pipeline 6, absorption spray bucket 7, settling vat 8, spiral case blower fan 9 and water film dedusting bucket group 10, described dust gathering arrester 2 is arranged on a side of intermediate frequency furnace 1 top, the lower ending opening of dust gathering arrester 2 extends to directly over fire door, and the lower ending opening of dust gathering arrester 2 is greater than fire door, the internal diameter of described dust gathering arrester 2 smoothly successively decreases from down to up, the upper end of described dust gathering arrester 2 is connected by rotary flange dish 4 with a minute airflow pipeline 5, during use, dust gathering arrester 2 can rotate and depart from a little fire door, position along with wind direction decision cover, within described minute, airflow pipeline 5 is connected to absorption spray bucket 7 by primary air pipeline 6, and described spray bucket 7 is connected to settling vat 8, and settling vat 8 is connected to water film dedusting bucket group 10, and described spiral case blower fan 9 is arranged between settling vat 8 and water film dedusting bucket group 10.
The interior position near rotary flange dish 4 of described dust gathering arrester 2 is also provided with air door 3, and described air door 3 is connected with the pull bar that hangs over dust gathering arrester 2 outsides.Described dust gathering arrester 2 is provided with handle, and the lower ending opening of dust gathering arrester 2 is apart from fire door 25-30cm.
Described minute airflow pipeline 5 and primary air pipeline 6 are the pipe that the iron sheet of thickness 2-3mm is made, and on interior lateral wall, all scribble antirust paint.Simultaneously on minute airflow pipeline 5 and primary air pipeline 6, do insulation material, the flue dust that has like this temperature to workshop release heat seldom, keeps the nice and cool of workshop in summer in pipeline.
Described absorption spray bucket 7 internal upper parts are provided with layer of active carbon filter course 71, and a plurality of spray nozzles 72 are installed on the madial wall of activated carbon filter layer 71 belows, and the bottom of described absorption spray bucket 7 is also provided with the circulating pump of bottom of the barrel current being sent back to spray nozzle 72.Described absorption spray bucket 7, the bottom of settling vat 8 and water film dedusting bucket group 10 is equipped with firth outlet hole 12.
The course of work: a set of stove is generally comprised of two intermediate frequency furnaces 1 and a switch board, general only with an intermediate frequency furnace 1 and switch board during blow-on, another intermediate frequency furnace 1 is standby, also interchangeable blow-on.Because dust gathering arrester 2 has adopted two stove central rotation structures, to be so no matter which stove work, dust gathering arrester 2 can be rotated to this stove top and operate.
From primary air pipeline 6 the insides flue dust out, enter through absorption spray bucket 7, after activated carbon filter layer 71 absorption, through the spray of bottom spray nozzle 72, in flue dust, most particle and nuisances is adsorbed and precipitates so again, circulating pump reciprocation cycle spray.Remaining gas is in settling vat 8, and with a small amount of aqueous vapor, after the interior sedimentation of settling vat 8, dry a little gas is sent in water film dedusting bucket group 10 through spiral case blower fan 9, so just can not corrode blower fan.In water film dedusting bucket group 10, water adsorbs remaining nuisance and is precipitated again, then improves chimney 11 and be discharged in atmosphere, has been relatively cleaner pure air, is conducive to environmental protection.
Can the supporting a set of dust pelletizing system of independent a set of stove, also can consider multiple muffle furnace and use a set of dust pelletizing system together, but stove has also lacked waste pipeline and blower fan apparatus, stove is also many, pipeline is oversize, exhausting weak effect, at present most suitable is that two cover stoves are also used a set of dust pelletizing system together.
Claims (6)
1. an intermediate frequency furnace dust pelletizing system, it is characterized in that: comprise dust gathering arrester (2), divide airflow pipeline (5), primary air pipeline (6), absorption spray bucket (7), settling vat (8), spiral case blower fan (9) and water film dedusting bucket group (10), described dust gathering arrester (2) is arranged on a side of intermediate frequency furnace (1) top, the lower ending opening of dust gathering arrester (2) extends to directly over fire door, and the lower ending opening of dust gathering arrester (2) is greater than fire door, the internal diameter of described dust gathering arrester (2) smoothly successively decreases from down to up, the upper end of described dust gathering arrester (2) is connected by rotary flange dish (4) with a minute airflow pipeline (5), described minute airflow pipeline (5) by primary air pipeline (6), be connected to absorption spray bucket (7), described spray bucket (7) is connected to settling vat (8), settling vat (8) is connected to water film dedusting bucket group (10), and described spiral case blower fan (9) is arranged between settling vat (8) and water film dedusting bucket group (10).
2. a kind of intermediate frequency furnace dust pelletizing system according to claim 1, it is characterized in that: the position near rotary flange dish (4) in described dust gathering arrester (2) is also provided with air door (3), described air door (3) pull bar outside with hanging over dust gathering arrester (2) is connected.
3. a kind of intermediate frequency furnace dust pelletizing system according to claim 2, is characterized in that: described dust gathering arrester (2) is provided with handle, and the lower ending opening of dust gathering arrester (2) is apart from fire door 25-30cm.
4. a kind of intermediate frequency furnace dust pelletizing system according to claim 1, is characterized in that: described minute airflow pipeline (5) and primary air pipeline (6) are the pipe that the iron sheet of thickness 2-3mm is made, and on interior lateral wall, all scribble antirust paint.
5. a kind of intermediate frequency furnace dust pelletizing system according to claim 1, it is characterized in that: described absorption spray bucket (7) internal upper part is provided with layer of active carbon filter course (71), on the madial wall of activated carbon filter layer (71) below, a plurality of spray nozzles (72) are installed, the bottom of described absorption spray bucket (7) is also provided with the circulating pump of bottom of the barrel current being sent back to spray nozzle (72).
6. a kind of intermediate frequency furnace dust pelletizing system according to claim 1, is characterized in that: described absorption spray bucket (7), the bottom of settling vat (8) and water film dedusting bucket group (10) is equipped with firth outlet hole (12).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320613990.7U CN203518645U (en) | 2013-09-29 | 2013-09-29 | Dedusting system of intermediate frequency furnace |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320613990.7U CN203518645U (en) | 2013-09-29 | 2013-09-29 | Dedusting system of intermediate frequency furnace |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203518645U true CN203518645U (en) | 2014-04-02 |
Family
ID=50377568
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201320613990.7U Expired - Fee Related CN203518645U (en) | 2013-09-29 | 2013-09-29 | Dedusting system of intermediate frequency furnace |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203518645U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103499217A (en) * | 2013-09-29 | 2014-01-08 | 湖州南丰机械制造有限公司 | Dust removing system of intermediate frequency furnace |
-
2013
- 2013-09-29 CN CN201320613990.7U patent/CN203518645U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103499217A (en) * | 2013-09-29 | 2014-01-08 | 湖州南丰机械制造有限公司 | Dust removing system of intermediate frequency furnace |
CN103499217B (en) * | 2013-09-29 | 2015-05-20 | 湖州南丰机械制造有限公司 | Dust removing system of intermediate frequency furnace |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103499217B (en) | Dust removing system of intermediate frequency furnace | |
CN201049353Y (en) | Weld fume ventilating and purifying installation | |
CN201485480U (en) | Converter flue gas waste heat recovery and purifying dedusting device | |
CN201899951U (en) | Combined dust removal and environment protection equipment for flue gas of smelting furnace | |
CN205019865U (en) | Energy -concerving and environment -protective dust collector based on remote control | |
CN201406439Y (en) | Blast furnace fume gas shunting collecting and parallel dedusting device | |
CN203518640U (en) | Smoke collection and prevention and dust removal device for AOD smelting furnace and medium frequency smelting furnace | |
CN203518645U (en) | Dedusting system of intermediate frequency furnace | |
CN206817999U (en) | Intermediate frequency furnace dust arrester | |
CN101559305B (en) | Blast furnace flue gas shunting trapping parallel dust-removing technology | |
CN203464361U (en) | Kitchen waste heat recycling and oil smoke purifying all-in-one machine | |
CN202032902U (en) | Dust removing and residual heat utilizing system for argon oxygen decarburizing furnace | |
CN205019904U (en) | Aluminium casting shop's dust pelletizing system | |
CN113941196A (en) | Movable electric furnace smelting secondary smoke dust collecting and purifying device for casting | |
CN204438072U (en) | A kind of biomass boiler with residue cleaning plant | |
CN204438827U (en) | A kind of rotary kiln exhaust gas treating apparatus | |
CN103981325B (en) | Blowing and drawing type converter secondary flue gas capturing device | |
CN102580416A (en) | Method for preventing filter bag of bag type collector from blockage | |
CN102052856A (en) | Dust collecting and waste heat utilizing system for argon oxygen decarburization furnace | |
CN206935021U (en) | A kind of electric furnace of hot tail gas dust arrester | |
CN204723910U (en) | Secondary aluminium alloy stove cleanse system for soot | |
CN205182423U (en) | Environment -friendly waste incinerator spray dedusting case | |
CN204933181U (en) | Automatic temperature-control tier-framework building smoke eliminator | |
CN2405644Y (en) | Electric stone-ash collecting device | |
CN218740797U (en) | Ash discharging and dust removing system for calcium carbide furnace |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |