Prior art keywords
control center
project
port com
processor
remote
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201320559245.9U
Other languages
Chinese (zh)
Inventor
关正文
万亨
冯图宏
朱金陵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Power And Environment Engineering Co ltd
Original Assignee
GCL ENGINEERING Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GCL ENGINEERING Ltd filed Critical GCL ENGINEERING Ltd
Priority to CN201320559245.9U priority Critical patent/CN203490517U/en
Application granted granted Critical
Publication of CN203490517U publication Critical patent/CN203490517U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Landscapes

  • Selective Calling Equipment (AREA)

Abstract

The utility model discloses a remote project control system for engineering. The remote project control system comprises a remote control center, an onsite control center and onsite monitoring equipment, wherein the remote control center and the onsite control center respectively comprise a processor, a display, a memory and a communication port; the onsite monitoring equipment comprises a processor, a memory, a communication port and a viewfinder; the remote control center and the onsite control center are remotely controlled; the remote control center and the onsite monitoring equipment are remotely controlled; and the onsite control center and the onsite monitoring equipment are remotely controlled. The utility model provides a more novel and effective project control system to break the time and space management barrier between a project headquarter, a site and a construction site so as to ensure safer and more efficient, convenient and advanced project management and achieve the target of reducing the cost, improving the efficiency and improving the overall competitiveness of an engineering company.

Description

A kind of engineering remote items control system
Technical field
The utility model relates to a kind of engineering remote items control system, specifically a kind of remote items control system that remote control center, field control center and project building site three are combined together.
Background technology
Along with the stable development of China's economy, the scope of business of engineering corporation constantly expands, its number of entry also constantly increases.In this process, how to utilize limited resource to manage efficiently distant place project, entry, become the problem that each engineering corporation is more and more concerned about.
Under the guidance of the Scientific Outlook on Development, we find by practice, can utilize project management theory and more powerful computing machine and the network technology of function of science, reach the object that reduces project management cost, raising project management efficiency, promotes engineering corporation's whole competitiveness.
The utility model is just based on above-mentioned guiding theory and current conditions, developed aly for distant place project, entry, to carry out long-range and project control system integrated management specially.
Utility model content
Problem to be solved in the utility model is: for the deficiency of existing engineering projects control system, and provide a kind of collection remote control center, field control center and project building site Trinitarian remote items control system, can realize distant place project, entry are carried out to long-range and integrated management, can bring into play the project control functions such as project planning, engineering design, project commander.
The technical solution adopted in the utility model:
An engineering remote items control system, is characterized in that, comprising:
One remote control center, comprises first processor, the first display, first memory and the first PORT COM, and described the first display, first memory and first processor is connected with described the first PORT COM respectively;
One field control center, comprises the second processor, second display, second memory and the second PORT COM, and described second display, second memory and the second processor are connected with described the second PORT COM respectively;
One on-site monitoring equipment, comprises that the 3rd processor, the 3rd storer, the 3rd PORT COM and view-finder, described the 3rd storer, the 3rd processor and view-finder are connected with described the 3rd PORT COM;
Between described remote control center and field control center, by described the first PORT COM and the second PORT COM, realize Long-distance Control; Between described remote control center and on-site monitoring equipment, by described the first PORT COM and the 3rd PORT COM, realize Long-distance Control; Between described field control Center-to-Field watch-dog, by described the second PORT COM and the 3rd PORT COM, realize Long-distance Control.
Described on-site monitoring equipment also comprises a wireless signal base station and with the view-finder of wireless communication function, view-finder is connected with described the 3rd processor and the 3rd PORT COM by wireless signal base station.
Control system of the present invention comprises remote control center, field control center and on-site monitoring equipment three parts, each part comprises a set of Project Management Software, and described software has long-distance video voice communication program, remote computer control program, database program, project office application program, video monitoring program etc.
By the utility model, remote control center and field control center can be carried out direct video/audio communication, be carried out real-time project office, and the project of live formula instructs.
By the utility model, field control center can observe directly the actual working state of field apparatus, thereby carries out safely, efficiently, easily project guidance and operation supervision.
By the utility model, remote control center can be watched with field control central synchronous the video pictures of field apparatus, thereby carries out remote engineering design and project guidance; On-site monitoring equipment history image information be can also transfer, analysis of engineering and scheme optimization carried out.
In addition, even if field control center logs off, remote control center also can be directly and on-site monitoring equipment set up and contact, thereby process in time the difficult problems such as contingent projects, design, construction.
Use the utility model, can allow project planning more gear to actual circumstances; Allow engineering design more press close to engineering site; Allow project instruct and more fulfill, thereby make project management more safe, efficient, convenient and advanced, finally reach the object that reduces costs, raises the efficiency, promotes engineering corporation's whole competitiveness.
Beneficial effect: the utility model provides a kind of more novel and effective project control system, broken the space-time management " barrier " between engineering project general headquarters, scene and building site, allow project management become more safe, efficient, convenient and advanced, and can reach the object that reduces costs, raises the efficiency, promotes engineering corporation's whole competitiveness.
Accompanying drawing explanation
Fig. 1 is the connection diagram of the utility model system.
In figure: desulfuration absorbing tower 1, GGH(gas-gas heat exchanger) 2, chimney 3, gas baffle door 4, circulation slurry pump 5, scrambler 6, the 3rd processor (containing the 3rd storer and Project Management Software) 7, wireless signal base station 8, the 3rd PORT COM 9, the first display (projector equipment) 10, first processor (containing Project Management Software) 11, first memory 12, the first PORT COM 13, the second PORT COM 14, second memory 15, the second processor (containing Project Management Software) 16, second display 17, and with view-finder A ~ E of wireless communication function etc.
Embodiment
Below in conjunction with accompanying drawing, the utility model is described further.
As shown in Figure 1, between remote control center " project general headquarters " and field control center " site office ", first by included the first display (projector equipment) 10 of the utility model, first processor 11, first memory 12, the first PORT COM 13, the second PORT COM 14, second memory 15, the second processor 16, second display 17, LAN, and by the Internet, build hardware corridor; By comprised Project Management Software 11,16(, there is again the functions such as long-distance video voice communication) software application support is provided; Then both sides can carry out telecommunication, carry out direct video/audio contact, carry out real-time project office, and the project of live formula instructs.
As Fig. 1, between " site office " and on-site monitoring equipment " project building site ", by the included view-finder A ~ E of the utility model, scrambler 6, the 3rd processor (containing the 3rd storer) 7, the 3rd PORT COM 9, the second PORT COM 14, second memory 15, the second processor 16, LAN, or by the Internet, build hardware corridor; By comprised Project Management Software 7,16(, there is again the functions such as video monitoring program) software application support is provided." site office " just can observe directly the absorption tower 1 in " project building site " like this, GGH(gas-gas heat exchanger) 2, chimney 3, gas baffle door 4, circulation slurry pump 5 actual working states such as grade, thus carry out safely, efficiently, easily project guidance and operation supervision.
In addition, view-finder A ~ E is also with wireless communication function, and " project building site ", if do not possessed wire communication condition, can directly pass through wireless signal base station 8, scrambler 6, the 3rd processor (containing the 3rd storer and Project Management Software) 7, the three PORT COM 9 signal transmissions.
As Fig. 1, Project Management Software 7,11,16(that " project general headquarters " can comprise by the utility model have remote computer control program), watch in real time the video pictures in " project building site " together with " site office ", thereby carry out remote engineering design and project guidance; Can also pass through comprised Project Management Software 7,11,16(database program), transfer " project building site " history image information, carry out design analysis and optimization.
In addition, even if " site office " logs off, the Project Management Software 7 that " project general headquarters " also can comprise by the utility model, 11(video monitoring program) and view-finder A ~ E, directly set up contact with " project building site ", thereby process in time the difficult problems such as contingent projects, design, construction.

Claims (2)

1. an engineering remote items control system, is characterized in that, comprising:
One remote control center, comprises first processor, the first display, first memory and the first PORT COM, and described the first display, first memory and first processor is connected with described the first PORT COM respectively;
One field control center, comprises the second processor, second display, second memory and the second PORT COM, and described second display, second memory and the second processor are connected with described the second PORT COM respectively;
One on-site monitoring equipment, comprises that the 3rd processor, the 3rd storer, the 3rd PORT COM and view-finder, described the 3rd storer, the 3rd processor and view-finder are connected with described the 3rd PORT COM;
Between described remote control center and field control center, by described the first PORT COM and the second PORT COM, realize Long-distance Control; Between described remote control center and on-site monitoring equipment, by described the first PORT COM and the 3rd PORT COM, realize Long-distance Control; Between described field control Center-to-Field watch-dog, by described the second PORT COM and the 3rd PORT COM, realize Long-distance Control.
2. engineering according to claim 1 remote items control system, it is characterized in that: described on-site monitoring equipment also comprises a wireless signal base station and with the view-finder of wireless communication function, view-finder is connected with described the 3rd processor and the 3rd PORT COM by wireless signal base station.
CN201320559245.9U 2013-09-10 2013-09-10 Remote project control system for engineering Expired - Lifetime CN203490517U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320559245.9U CN203490517U (en) 2013-09-10 2013-09-10 Remote project control system for engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320559245.9U CN203490517U (en) 2013-09-10 2013-09-10 Remote project control system for engineering

Publications (1)

Publication Number Publication Date
CN203490517U true CN203490517U (en) 2014-03-19

Family

ID=50261338

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320559245.9U Expired - Lifetime CN203490517U (en) 2013-09-10 2013-09-10 Remote project control system for engineering

Country Status (1)

Country Link
CN (1) CN203490517U (en)

Similar Documents

Publication Publication Date Title
CN211043537U (en) Substation equipment state monitoring system based on ubiquitous power internet of things
CN202261389U (en) Power transmission line operation and maintenance routing inspection management information system
CN102063111A (en) Mobile terminal-based remote robot control system
CN102404553A (en) Method for integrating image monitoring with an integration automation background of electric power system
CN202906983U (en) Network total station with network remote control
CN103488160A (en) Real-time monitoring system of transformer substation
CN104469314A (en) Video monitoring system and method of electric power construction field
CN201426053Y (en) Intelligent visual remote control operating system for substation equipment
CN201830020U (en) Remote video monitoring system of intelligent transformer substation based on electric power data network
CN203588043U (en) Remote wireless monitoring system for equipment of coal preparation plant
CN203490517U (en) Remote project control system for engineering
CN103279116A (en) ZigBee network remote information acquisition and survey system for construction site
CN203366105U (en) A concentration optimization monitor system applicable to distributed-type access wind power generation
CN203657148U (en) Remote maintenance system for air conditioner in machine room
CN203340109U (en) Real time wireless receive-transmit system based on Internet of Things
CN202454974U (en) Device for electric power production inspection tour
CN206023378U (en) A kind of large-sized photovoltaic power station and its monitoring system of O&M
CN204740470U (en) Energy consumption monitoring management system
CN105323273B (en) For controlling the methods, devices and systems of energy consumption monitoring system
CN205091610U (en) Monitoring system
Liu et al. Design of coal Mine monitoring system based on Internet of things
CN202002913U (en) Wireless transmission acoustic emission monitoring system
CN210534844U (en) Subway construction scheduling management system
CN205946004U (en) On --spot data monitoring device of electric power engineering
CN205427550U (en) Gas -combustion generator communication system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20171114

Address after: Shuige road Changsheng street in Jiangning District of Nanjing City, Jiangsu Province, No. 2 211100

Patentee after: NANJING DINGHUAN NEW ENERGY SCIENCE AND TECHNOLOGY CO.,LTD.

Address before: Dong Village Road, Jiangning Development Zone, Nanjing City, Jiangsu Province, No. 87 210008

Patentee before: CHINA CONSTRUCTION POWER AND ENVIRONMENT ENGINEERING CO.,LTD.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190319

Address after: No. 87 Dongcun Road, Jiangning Development Zone, Nanjing City, Jiangsu Province, 210008

Patentee after: CHINA CONSTRUCTION POWER AND ENVIRONMENT ENGINEERING CO.,LTD.

Address before: 211100 No. 2 Changsheng Street, Shuige Road, Jiangning District, Nanjing City, Jiangsu Province

Patentee before: NANJING DINGHUAN NEW ENERGY SCIENCE AND TECHNOLOGY CO.,LTD.

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20140319