CN203475788U - Decoration auxiliary scaffold - Google Patents

Decoration auxiliary scaffold Download PDF

Info

Publication number
CN203475788U
CN203475788U CN201320505461.5U CN201320505461U CN203475788U CN 203475788 U CN203475788 U CN 203475788U CN 201320505461 U CN201320505461 U CN 201320505461U CN 203475788 U CN203475788 U CN 203475788U
Authority
CN
China
Prior art keywords
loaded plate
working platform
scaffold
bearing plate
slide rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201320505461.5U
Other languages
Chinese (zh)
Inventor
黄正荣
刘燕
刘忠
曲建银
汤婷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHONGQING CONSTRUCTION NINTH ENGINEERING Co Ltd
Chongqing Construction Engineering Group Co Ltd
Original Assignee
CHONGQING CONSTRUCTION NINTH ENGINEERING Co Ltd
Chongqing Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHONGQING CONSTRUCTION NINTH ENGINEERING Co Ltd, Chongqing Construction Engineering Group Co Ltd filed Critical CHONGQING CONSTRUCTION NINTH ENGINEERING Co Ltd
Priority to CN201320505461.5U priority Critical patent/CN203475788U/en
Application granted granted Critical
Publication of CN203475788U publication Critical patent/CN203475788U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model relates to a scaffold, in particular to a decoration auxiliary scaffold. The decoration auxiliary scaffold comprises a supporting frame and a working platform, wherein the supporting frame is set up through vertical rods and transverse rods. Installation holes are evenly formed in each vertical rod of the supporting frame at intervals, and the working platform is connected with the supporting frame through the installation holes. An auxiliary frame is arranged on the side, close to the vertical rods, of the working platform. The auxiliary frame comprises vertical bars, a bearing plate and bearing plate slide rails. The vertical bars are hinged to the two sides of the working platform, one end of each bearing plate slide rail is hinged to the corresponding vertical rod, the other end of each bearing plate slide rail is connected with the corresponding vertical bar through a bolt, and the bearing plate is embedded into the bearing plate slide rails. The decoration auxiliary scaffold has the advantages that materials and tools are placed on the bearing plate in the decoration process, maintainers can be prevented from stumbling over objects or the tools, and therefore great convenience is brought to the maintainers.

Description

A kind of finishing is assisted scaffold
Technical field
The utility model relates to scaffold, particularly the auxiliary scaffold of a kind of finishing.
Background technology
Scaffold is building operations, one of indispensable instrument in fitting-out work, scaffold has highly versatile, installation is set up easy, disassembled for transport is convenient, the advantages such as bearing capacity is large, oneself becomes the bracing frame of the exterior wall finishing that current use amount is maximum, the small-sized finishing frame existing now, majority is the bracing frame of single working platform, in fitment process, generally that a small amount of material is put on the working platform of bracing frame, because this working platform is to provide, staff stands and walks, above material is put in, sometimes because staff is too absorbed, probably material is kicked under working platform, now need staff again to pick up, or make people again transmit up, reduced so beyond doubt operating efficiency, What is more, and staff can be tripped by material, causes life danger.
Utility model content
Problem to be solved in the utility model is that existing finishing causes the inconvenient problem of work with the material that scaffold work platform is placed.
In order to deal with problems, the utility model provides a kind of finishing to assist scaffold, comprise the bracing frame that vertical rod and cross bar are built, working platform, in the vertical rod of support frame as described above, be provided with the uniform installing hole in interval, described working platform is connected with bracing frame by installing hole, and wherein said working platform is provided with an auxiliary frame near vertical rod one side, described auxiliary frame comprise vertical bar, loaded plate and and loaded plate slide rail; Described vertical bar is hinged on the both sides of working platform, and described loaded plate slide rail one end is hinged in vertical rod, and the other end is connected with vertical bar by bolt, and described loaded plate embeds in loaded plate slide rail.
In exterior wall or ceiling finishing, use finishing of the present utility model to assist scaffold, first by articulated elements, assemble auxiliary frame and the loaded plate of placing articles, in finishing, material and instrument are placed on loaded plate, can prevent that service worker from being tripped by article or instrument; After the sets of containers dresses such as sometimes object or instrument are too scattered, can take off loaded plate along loaded plate slide rail, use casing, be placed in the space of auxiliary frame formation, bring very large facility will to like this installation and maintenance workman.
Preferably, for the convenient bucket of placing tubing and fluid being housed, on described loaded plate, be provided with the hole of shelving of placing for pipe fitting, can with the bucket of fluent material, put into and shelve hole packing mixed earth, paint or other finishings into like this, to play good fixation.
Preferably, in order to adapt to different weights and tubing, can be placed on auxiliary frame, the expansion link that described vertical bar is inside and outside pipe fitting sleeving, is provided with locating hole on inside and outside pipe fitting, and is equipped with alignment pin with locating hole; For different weights, put on auxiliary frame like this, just can highly directly regulate vertical bar according to container or the weight itself of dress weight, realize the constraint of auxiliary frame to the weight of differing heights or tubing.
Preferably, in order to make loaded plate surrounding have certain barrier effect, the article that prevent from being placed directly on loaded plate are toppled over, and described loaded plate slide rail from vertical bar upper extreme point 10mm, and is vertically hinged with lever between bar upper extreme point and vertical rod with vertical bar pin joint; Article are placed on bearing plate like this, can to article, have by lever the strong point of a side.
Accompanying drawing explanation
Fig. 1 is the structural representation of the auxiliary scaffold of finishing of the utility model embodiment.
The specific embodiment
Below in conjunction with drawings and Examples, technical solutions of the utility model are further illustrated:
As shown in Figure 1, a kind of finishing is assisted scaffold, comprise the bracing frame that vertical rod 1 and cross bar 2 are built, working platform 4, in the vertical rod 1 of bracing frame, be provided with the uniform installing hole 3 in interval, described working platform 4 is connected with bracing frame by installing hole 3, and described working platform 4 is provided with an auxiliary frame 5 near vertical rod 1 one sides, and described auxiliary frame 5 comprises vertical bar 6, loaded plate 9 and loaded plate slide rail 10; Described vertical bar 6 is hinged on the both sides of working platform 4, and described loaded plate slide rail 10 one end are hinged in vertical rod 6, and the other end is connected with vertical bar 6 by bolt, and described loaded plate 9 embeds in loaded plate slide rails 10.
In exterior wall or ceiling finishing, use finishing of the present utility model to assist scaffold, first by articulated elements, assemble auxiliary frame 5 and the loaded plate 9 of placing articles, in finishing, material and instrument are placed on loaded plate 9, can prevent that service worker from being tripped by article or instrument; After the sets of containers dresses such as sometimes object or instrument are too scattered, can take off loaded plate 9 along loaded plate slide rail 10, use casing, be placed in the space of auxiliary frame 5 formation, bring very large facility will to like this installation and maintenance workman.
For the convenient bucket of placing tubing and fluid being housed, described loaded plate 9 be provided with for pipe fitting, place shelve hole 8, can with barrel putting into of fluent material, shelve hole 8 by packing mixed earth, paint or other finishings into like this, to play good fixation.
In order to adapt to different weights and tubing, can be placed on auxiliary frame 5, the expansion link that described vertical bar 6 is inside and outside pipe fitting sleeving, on inside and outside pipe fitting, be provided with locating hole, and be equipped with alignment pin with locating hole, for different weights, put on auxiliary frame 5 like this, just can highly directly regulate vertical bar 6 according to container or the weight itself of dress weight, realize the constraint of weight and tubing.
In order to make loaded plate surrounding have certain barrier effect, prevent that the article that are placed directly on loaded plate 9 from toppling over, described loaded plate slide rail 10 from vertical bar 6 upper extreme point 10mm, and is vertically hinged with lever 7 between bar 6 upper extreme points and vertical rod 1 with vertical bar 6 pin joints; Article are placed on bearing plate 9 like this, can have by 7 pairs of article of lever the strong point of a side.
Above-described is only preferred embodiment of the present utility model; should be understood that; for a person skilled in the art; do not departing under the prerequisite of the utility model structure; can also make some distortion and improvement; these also should be considered as protection domain of the present utility model, and these can not affect effect and practical applicability that the utility model is implemented.

Claims (4)

1. a finishing is assisted scaffold, comprise the bracing frame that vertical rod and cross bar are built, working platform, in the vertical rod of support frame as described above, be provided with the uniform installing hole in interval, described working platform is connected with bracing frame by installing hole, it is characterized in that: described working platform is provided with an auxiliary frame near vertical rod one side, described auxiliary frame comprise vertical bar, loaded plate and and loaded plate slide rail; Described vertical bar is hinged on the both sides of working platform, and described loaded plate slide rail one end is hinged in vertical rod, and the other end is connected with vertical bar by bolt, and described loaded plate embeds in loaded plate slide rail.
2. according to the auxiliary scaffold of the finishing described in right 1, it is characterized in that: on described loaded plate, be provided with the hole of shelving of placing for pipe fitting.
3. according to the auxiliary scaffold of the finishing described in right 2, it is characterized in that: the expansion link that described vertical bar is inside and outside pipe fitting sleeving, is provided with locating hole on inside and outside pipe fitting, and is equipped with alignment pin with locating hole.
4. according to the auxiliary scaffold of the finishing described in right 3, it is characterized in that: described loaded plate slide rail from vertical bar upper extreme point 10mm, and is vertically hinged with lever between bar upper extreme point and vertical rod with vertical bar pin joint.
CN201320505461.5U 2013-08-19 2013-08-19 Decoration auxiliary scaffold Expired - Lifetime CN203475788U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320505461.5U CN203475788U (en) 2013-08-19 2013-08-19 Decoration auxiliary scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320505461.5U CN203475788U (en) 2013-08-19 2013-08-19 Decoration auxiliary scaffold

Publications (1)

Publication Number Publication Date
CN203475788U true CN203475788U (en) 2014-03-12

Family

ID=50224142

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320505461.5U Expired - Lifetime CN203475788U (en) 2013-08-19 2013-08-19 Decoration auxiliary scaffold

Country Status (1)

Country Link
CN (1) CN203475788U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108518055A (en) * 2018-05-11 2018-09-11 桐城市永锦建筑工程有限公司 A kind of special constructing device of paint

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108518055A (en) * 2018-05-11 2018-09-11 桐城市永锦建筑工程有限公司 A kind of special constructing device of paint

Similar Documents

Publication Publication Date Title
CN204311719U (en) External hanging type scaffold
CN207944694U (en) Anti-dumping inclined architectural engineering scaffold
CN204310752U (en) Swing door transports equipment in place
CN203475788U (en) Decoration auxiliary scaffold
CN205046827U (en) Mobilizable slope operation construction platform
CN202866261U (en) Operation hanging rack for civil construction
CN205531248U (en) Construction scaffolding component
CN103016843B (en) Pipeline mounting machine and construction method thereof
CN204059901U (en) A kind of high-altitude construction operation platform
CN205875168U (en) A prevent structure of falling for foundation ditch steel shotcrete
CN201771169U (en) Horizontal diagonal rod for bracing frame or scaffold
CN205296892U (en) A merogenesis stair and up -downgoing passageway for deep foundation pit construction is current from top to bottom
CN203022327U (en) Elevator shaft high-altitude construction platform device
CN204139950U (en) Box-type folding lift
CN207160532U (en) Scaffolding scope of operation guard rail
CN207017620U (en) A kind of constructing tunnel scaffold
CN206720632U (en) A kind of indoor Liftable type movement hanging apparatus
CN206976945U (en) Cable synchronizing conveyer Combined fixing device
CN205154108U (en) Debugging platform of beam -pumping unit
CN205259554U (en) A mount for installation of light steel joist gypsum -lath furred ceiling
CN204997107U (en) Device of free angle drilling carries out
CN215927413U (en) Detachable and assembled trolley for pumped storage construction site
CN203452356U (en) Combined frame type scaffold
CN203903793U (en) Gantry hoisting frame applied to heavy equipment
CN203160725U (en) Shaped type protective barrier

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20140312

CX01 Expiry of patent term