CN203420297U - Hydraulic hammer-breaking type loader-digger with three sections of arms - Google Patents

Hydraulic hammer-breaking type loader-digger with three sections of arms Download PDF

Info

Publication number
CN203420297U
CN203420297U CN201320429341.1U CN201320429341U CN203420297U CN 203420297 U CN203420297 U CN 203420297U CN 201320429341 U CN201320429341 U CN 201320429341U CN 203420297 U CN203420297 U CN 203420297U
Authority
CN
China
Prior art keywords
assembly
arm assembly
arm
oil cylinder
bearing pin
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320429341.1U
Other languages
Chinese (zh)
Inventor
韩睿
马伯雨
蒋权
李磊
闵凡唐
孙正军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUAINAN LANXIANG HEAVY INDUSTRY Co Ltd
Original Assignee
HUAINAN LANXIANG HEAVY INDUSTRY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUAINAN LANXIANG HEAVY INDUSTRY Co Ltd filed Critical HUAINAN LANXIANG HEAVY INDUSTRY Co Ltd
Priority to CN201320429341.1U priority Critical patent/CN203420297U/en
Application granted granted Critical
Publication of CN203420297U publication Critical patent/CN203420297U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model relates to a hydraulic hammer-breaking type loader-digger with three sections of arms. The hydraulic hammer-breaking type loader-digger with the three sections of arms comprises a large arm assembly and a small arm assembly which are connected with each other in a hinged mode, wherein the small arm assembly is connected with an excavator bucket assembly, a large arm oil cylinder which drives the large arm assembly to act is arranged on the large arm assembly, a small arm oil cylinder which drives the small arm assembly to act is arranged on the small arm assembly, an excavator bucket oil cylinder which drives the excavator bucket assembly to act is arranged on the excavator bucket assembly, a medium arm assembly is arranged between the large arm assembly and the small arm assembly, a medium arm oil cylinder which drives the medium arm assembly to act is arranged on the medium arm assembly, and the medium arm assembly is connected with both the large arm assembly and the small arm assembly in a hinged mode. According to the hydraulic hammer-breaking type loader-digger with the three sections of arms, the length and height of a whole working arm can be adjusted by adjusting the large arm oil cylinder, the medium arm oil cylinder and the small arm oil cylinder according to the size of a roadway, and normal working is guaranteed without sacrificing the excavating distance; meanwhile, a breaking hammer assembly and the excavator bucket assembly are arranged on the small arm assembly, switching of the function of the breaking hammer assembly and the function of the excavator bucket assembly can be achieved through a driving device, and manual frequent replacement of an excavator and a breaking hammer is not needed in use.

Description

Hydraulic hammer hits the arm-type loader-digger of breaking three joint
Technical field
The utility model relates to a kind of loader-digger, is specifically related to a kind of hydraulic hammer and hits the arm-type loader-digger of breaking three joint.
Background technology
At present, the backhoe loader using is on the market two joint working arms, large arm, forearm and bucket, consists of.When the backhoe loader of existing two joint working arms is worked in highly lower tunnel, must sacrifice and excavate apart from using, while namely working, have to shorten the length of big and small arms in highly lower tunnel, cause like this and excavate apart from less, when large arm lifts, ceiling is easily encountered in large forearm junction, causes and delays work, mistakes simultaneously, and very dangerous, the adjustable range of loader working arm is limited, and working range is little, and efficiency is low.
Utility model content
The purpose of this utility model is to provide a kind of hydraulic hammer to hit the arm-type loader-digger of breaking three joint, and this loader can be worked and need not sacrifice excavation distance in highly lower tunnel.
For achieving the above object, the utility model has adopted following technical scheme: comprise the large arm assembly and the little arm assembly that are hinged, described little arm assembly is connected with bucket assembly, on described large arm assembly, little arm assembly and bucket assembly, be respectively equipped with the big arm cylinder, oil cylinder of small arm and the bucket cylinder that drive its action, between described large arm assembly and little arm assembly, be provided with middle arm assembly, described middle arm assembly is provided with the middle arm oil cylinder that drives its action, and described middle arm assembly is hinged and connected with large arm assembly and little arm assembly respectively.
One end of large arm assembly of the present utility model is connected by bearing pin with middle arm assembly, the other end of described large arm assembly fixes by bearing pin and large arm seat, one end of described big arm cylinder is connected by bearing pin with large arm seat, and the other end of big arm cylinder is connected by bearing pin with large arm assembly.
One end of middle arm oil cylinder of the present utility model is connected by bearing pin with middle arm assembly, and the other end of middle arm oil cylinder is connected by bearing pin with large arm assembly.
One end of oil cylinder of small arm of the present utility model is connected by bearing pin with little arm assembly, and the other end of oil cylinder of small arm is connected by bearing pin with middle arm assembly.
Little arm assembly of the present utility model is provided with quartering hammer assembly, and described quartering hammer assembly is provided with the push cylinder that drives its action.
One end of push cylinder of the present utility model is connected by bearing pin with little arm assembly, and the other end of described push cylinder is connected by bearing pin with quartering hammer assembly.
Quartering hammer assembly of the present utility model is connected with little arm assembly by first, second bent plate.
As shown from the above technical solution, the utility model by setting up a middle arm assembly between original large arm assembly and little arm assembly, while working in tunnel, can, according to tunnel size, regulate big arm cylinder, middle arm oil cylinder and oil cylinder of small arm to regulate length and the height of whole working arm.While working in highly lower tunnel, big arm cylinder can be shortened, reduce the height of whole working arm, by arm oil cylinder in regulating and oil cylinder of small arm, whole working arm is extended again, while meeting work, excavate the requirement of distance, in shorter tunnel, need not sacrifice and excavate apart from also working; Simultaneously little arm assembly is provided with quartering hammer assembly and bucket assembly, and both can practical function conversion under the effect of drive unit, with time do not need use back and forth manually to change bucket and quartering hammer.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
The specific embodiment
Below in conjunction with accompanying drawing, the utility model is described further:
A kind of hydraulic hammer as shown in Figure 1 hits the arm-type loader-digger of breaking three joint, comprise the large arm assembly 1 and the forearm assembly 2 that are hinged; forearm assembly 2 is connected with bucket assembly 3; on large arm assembly 1, forearm assembly 2 and bucket assembly 3, be respectively equipped with big arm cylinder 4, oil cylinder of small arm 5 and the bucket cylinder 6 that drives its action; between large arm assembly 1 and forearm assembly 2, be provided with middle arm assembly 7; middle arm assembly 7 is provided with the middle arm oil cylinder 8 that drives its action, and middle arm assembly 7 is hinged and connected with large arm assembly 1 and forearm assembly 2 respectively.
Further, one end of large arm assembly 1 is connected by bearing pin with middle arm assembly 7, the other end of large arm assembly 1 fixes by bearing pin and large arm seat 9, and one end of big arm cylinder 4 is connected by bearing pin with large arm seat 9, and the other end of big arm cylinder 4 is connected by bearing pin with large arm assembly 1.
Further, one end of middle arm oil cylinder 8 is connected by bearing pin with middle arm assembly 2, and the other end of middle arm oil cylinder 8 is connected by bearing pin with large arm assembly 1.
Further, one end of oil cylinder of small arm 5 is connected by bearing pin with forearm assembly 2, and the other end of oil cylinder of small arm 5 is connected by bearing pin with middle arm assembly 7.
Further, forearm assembly 2 is provided with quartering hammer assembly 13, and quartering hammer assembly 13 is provided with the push cylinder 10 that drives its action.
Further, one end of push cylinder 10 is connected by bearing pin with forearm assembly 2, and the other end of push cylinder 10 is connected by bearing pin with quartering hammer assembly 13.
Further, quartering hammer assembly 13 is connected with forearm assembly 2 by first, second bent plate 11,12.
In sum, when the utility model is worked in tunnel, can be according to tunnel size, by regulating big arm cylinder, middle arm oil cylinder and oil cylinder of small arm to regulate length and the height of whole working arm.While working in highly lower tunnel, big arm cylinder can be shortened, reduce the height of whole working arm, by arm oil cylinder in regulating and oil cylinder of small arm, whole working arm is extended again, while meeting work, excavate the requirement of distance, in shorter tunnel, need not sacrifice and excavate apart from also working.The structure of three joint working arms increases the adjustable range of the working arm of this backhoe loader, has improved production efficiency.Meanwhile, forearm is provided with quartering hammer assembly and bucket assembly, can realize by the driving of push cylinder the function of the two and change, and in use, does not need use back and forth manually to change bucket and quartering hammer.
Above embodiment is described preferred embodiment of the present utility model; not scope of the present utility model is limited; do not departing under the prerequisite of the utility model design spirit; various distortion and improvement that those of ordinary skills make the technical solution of the utility model, all should fall in the definite protection domain of the utility model claims.

Claims (7)

1. a hydraulic hammer hits the arm-type loader-digger of breaking three joint, comprise the large arm assembly (1) and the little arm assembly (2) that are hinged, described little arm assembly (2) is connected with bucket assembly (3), described large arm assembly (1), on little arm assembly (2) and bucket assembly (3), be respectively equipped with the big arm cylinder (4) that drives its action, oil cylinder of small arm (5) and bucket cylinder (6), it is characterized in that: between described large arm assembly (1) and little arm assembly (2), be provided with middle arm assembly (7), described middle arm assembly (7) is provided with the middle arm oil cylinder (8) that drives its action, described middle arm assembly (7) is hinged and connected with large arm assembly (1) and little arm assembly (2) respectively.
2. loader-digger according to claim 1, it is characterized in that: one end of described large arm assembly (1) is connected by bearing pin with middle arm assembly (7), the other end of described large arm assembly (1) fixes by bearing pin and large arm seat (9), one end of described big arm cylinder (4) is connected by bearing pin with large arm seat (9), and the other end of big arm cylinder (4) is connected by bearing pin with large arm assembly (1).
3. loader-digger according to claim 1, is characterized in that: one end of described middle arm oil cylinder (8) is connected by bearing pin with middle arm assembly (2), and the other end of middle arm oil cylinder (8) is connected by bearing pin with large arm assembly (1).
4. loader-digger according to claim 1, is characterized in that: one end of described oil cylinder of small arm (5) is connected by bearing pin with little arm assembly (2), and the other end of oil cylinder of small arm (5) is connected by bearing pin with middle arm assembly (7).
5. loader-digger according to claim 1, is characterized in that: described little arm assembly (2) is provided with quartering hammer assembly (13), and described quartering hammer assembly (13) is provided with the push cylinder (10) that drives its action.
6. loader-digger according to claim 5, is characterized in that: one end of described push cylinder (10) is connected by bearing pin with little arm assembly (2), and the other end of described push cylinder (10) is connected by bearing pin with quartering hammer assembly (13).
7. loader-digger according to claim 6, is characterized in that: described quartering hammer assembly (13) is connected with little arm assembly (2) by first, second bent plate (11,12).
CN201320429341.1U 2013-07-18 2013-07-18 Hydraulic hammer-breaking type loader-digger with three sections of arms Expired - Fee Related CN203420297U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320429341.1U CN203420297U (en) 2013-07-18 2013-07-18 Hydraulic hammer-breaking type loader-digger with three sections of arms

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320429341.1U CN203420297U (en) 2013-07-18 2013-07-18 Hydraulic hammer-breaking type loader-digger with three sections of arms

Publications (1)

Publication Number Publication Date
CN203420297U true CN203420297U (en) 2014-02-05

Family

ID=50019397

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320429341.1U Expired - Fee Related CN203420297U (en) 2013-07-18 2013-07-18 Hydraulic hammer-breaking type loader-digger with three sections of arms

Country Status (1)

Country Link
CN (1) CN203420297U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106609531A (en) * 2016-06-16 2017-05-03 襄阳忠良工程机械有限责任公司 Breaking and digging integrated stripping attachment
CN107288636A (en) * 2017-06-20 2017-10-24 常州骏铎机械制造有限公司 A kind of sled hair based on driving drill jumbo, excavation, broken equipment
WO2019227469A1 (en) * 2018-06-01 2019-12-05 Guangxi Liugong Machinery Co., Ltd. Multiple tool construction machine

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106609531A (en) * 2016-06-16 2017-05-03 襄阳忠良工程机械有限责任公司 Breaking and digging integrated stripping attachment
CN106609531B (en) * 2016-06-16 2019-06-11 襄阳忠良工程机械有限责任公司 It is broken to dig integral type drive hoeing machine
CN107288636A (en) * 2017-06-20 2017-10-24 常州骏铎机械制造有限公司 A kind of sled hair based on driving drill jumbo, excavation, broken equipment
WO2019227469A1 (en) * 2018-06-01 2019-12-05 Guangxi Liugong Machinery Co., Ltd. Multiple tool construction machine
US10648155B2 (en) 2018-06-01 2020-05-12 Guangxi Liugong Machinery Co., Ltd. Multiple tool construction machine

Similar Documents

Publication Publication Date Title
CN102720230B (en) Motion redundancy face shovel excavating mechanism capable of reducing lifting energy consumption
CN203420297U (en) Hydraulic hammer-breaking type loader-digger with three sections of arms
CN102720226B (en) Face shovel spadework device with movement redundancy
CN202706074U (en) Motion redundancy face-shovel excavation mechanism
CN102720229A (en) Motion redundancy face shovel excavating mechanism capable of optimizing lifting force
CN103382730A (en) Face shovel excavating and loading device capable of optimizing drive and stroke of bucket rod
CN205242472U (en) Excavator with folding arm
CN204023657U (en) A kind of positive backhoe switching mechanism
CN103046586B (en) Optimize the excavation loading attachment of digging force
CN203383729U (en) Translation arm of drill jambo
CN103046587B (en) Excavating and loading device with extension jib
CN202247980U (en) Excavating device with rotatable small arm
CN204059449U (en) A kind of broken excavating gear
CN204530811U (en) The control system that working device of loader can arbitrarily angledly be set level automatically
CN203701172U (en) Direction changeable bulldozer scraper
CN203488179U (en) Multifunctional coal winning machine
CN202132039U (en) Excavating device of bucket loading machine for mine roadway
CN205822307U (en) A kind of excavator repacking hydraulic breaking hammer worked continuously forward in restricted clearance
CN202706076U (en) Motion redundant face shovel excavation mechanism capable of reducing hoisting energy consumption
CN202337990U (en) Novel slide telescopic arm
CN202164632U (en) Three-segment type lengthened arm of excavator
CN204225181U (en) A kind of special-shaped ridge buster forearm structure
CN103046588B (en) Crowd shovel excavation mechanism for optimizing driving of bucket rod
CN203924156U (en) A kind of Shovel Bucket Attachment and excavator
CN204225183U (en) A kind of ridge buster forearm structure of adjustable force moment

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140205

Termination date: 20140718

EXPY Termination of patent right or utility model