Angle steel clamp for integral hoisting of iron tower Download PDF

Info

Publication number
CN203402807U
CN203402807U CN201320511969.6U CN201320511969U CN203402807U CN 203402807 U CN203402807 U CN 203402807U CN 201320511969 U CN201320511969 U CN 201320511969U CN 203402807 U CN203402807 U CN 203402807U
Authority
CN
China
Prior art keywords
angle steel
iron tower
integral hoisting
card assembly
hoisting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201320511969.6U
Other languages
Chinese (zh)
Inventor
韩学文
靳义奎
余孝勇
梁来先
薛基富
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
QINGHAI ELECTRIC POWER CO Ltd
Qinghai Transmission And Distribution Engineering Co Ltd
State Grid Corp of China SGCC
Original Assignee
QINGHAI ELECTRIC POWER CO Ltd
Qinghai Transmission And Distribution Engineering Co Ltd
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by QINGHAI ELECTRIC POWER CO Ltd, Qinghai Transmission And Distribution Engineering Co Ltd, State Grid Corp of China SGCC filed Critical QINGHAI ELECTRIC POWER CO Ltd
Priority to CN201320511969.6U priority Critical patent/CN203402807U/en
Application granted granted Critical
Publication of CN203402807U publication Critical patent/CN203402807U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model provides an angle steel clamp for integral hoisting of an iron tower. The angle steel clamp for integral hoisting of the iron tower mainly comprises an upper clamping assembly, a lower clamping assembly, movable bolts and a U-shaped ring, wherein the upper clamping assembly and the lower clamping assembly are partially welded, and are installed on main material angle steel of the iron tower when being used, and the upper clamping assembly and the lower clamping assembly are connected through the four movable bolts which are arranged symmetrically. The angle steel clamp for integral hoisting of the iron tower is mainly used for being clamped on the main material angle steel, arranged on the hoisting point, of the iron tower, a steel wire rope is directly connected to the angle steel clamp for integral hoisting of the iron tower through the U-shaped ring when hoisting is carried out, and the purpose of safe and stable hoisting is achieved on the premise that the angle steel is protected. When the angle steel clamp for integral hoisting of the iron tower is used, the number of potential safety hazards of integral hoisting of the iron tower is effectively reduced, labor intensity of constructors is reduced, installation quality of the iron tower can be improved, and due to the fact that the angle steel clamp for integral hoisting of the iron tower is simple and flexible in structure, convenient to use and rapid in use, the angle steel clamp for integral hoisting of the iron tower can serve as a tool for the emergency rescue task, and is economical and practical, and the construction period is shortened.

Description

A kind of steel tower integral hoisting angle steel jig
Technical field
The utility model relates to transmission line construction technical field, particularly relates to a kind of iron tower of power transmission line integral hoisting angle steel jig.
Background technology
Universal along with large tonnage crane, widely applies crane integral assembly steel tower during iron tower of power transmission line group is vertical, and steel tower is that V-type Guywire tower etc. all adopts integral hoisting.During integral hoisting, adopt steel rope to be connected with iron tower main material take-up strap, steel rope colligation difficulty, easily slides and causes the problems such as the damage of steel tower zinc layer, iron tower main material distortion.
Utility model content
In order to overcome above-mentioned the deficiencies in the prior art; the utility model provides a kind of steel tower integral hoisting angle steel jig; be mainly used to be stuck on the iron tower main material angle steel of hoisting point position; lifting is directly connected on jig with clevis eye with steel rope, is issued to the object of safety and stability lifting in the prerequisite of protection angle steel.
The utility model adopts following technical scheme for achieving the above object: a kind of steel tower integral hoisting angle steel jig, it is characterized in that: this steel tower integral hoisting angle steel jig is comprised of upper card assembly, lower card assembly, movable bolt, clevis eye, upper card assembly, lower card components adopt welding to form, and are provided with 4 movable bolts that are arranged symmetrically with; Be fixed by bolts on card assembly, on upper and lower card assembly, correspondence position is open slot, by movable bolt, connects upper and lower card assembly; On upper card assembly, be provided with a rotating shaft, can, at flexible rotating within the scope of 180 ° of levels, a bolt hole be set in the middle of rotating shaft and connect clevis eye.
Described a kind of steel tower integral hoisting angle steel jig, is characterized in that: described upper and lower card assembly surface arranges respectively MC nylon lining, zinc-plated for the protection of steel tower.
The beneficial effects of the utility model: effectively reduce sling cable and use, avoid the potential safety hazard of answering repeated usage wire rope sling to produce; Alleviated workmen's labour intensity; Avoided due to accidents such as the not firm hanging piece causing of colligation fall, be beneficial to the Occupational Health and Safety that ensures workmen; Reduce steel rope and contact with the direct of iron tower main material, can effectively prevent that steel rope from making the quality problems such as main material distortion, the scuffing of zinc layer after stressed, can improve steel tower installation quality; Due to simple in structure flexible, convenient to use, can be used as the Work tool of emergency repair task, economical and practical, save the duration.
Accompanying drawing explanation
Fig. 1 is the main TV structure schematic diagram of steel tower integral hoisting angle steel jig;
Fig. 2 is the left TV structure schematic diagram of Fig. 1;
Fig. 3 is the plan structure schematic diagram of Fig. 1.
Wherein: on 1, block assembly, 2 movable bolts, 3 times card assemblies, 4U shape ring, 5 rotating shafts.
[0010] specific embodiment
A kind of steel tower integral hoisting angle steel jig of the present utility model, this steel tower integral hoisting angle steel jig is comprised of upper card assembly 1, lower card assembly 3, movable bolt 2, clevis eye 4, upper card assembly 1, lower card assembly 3 parts adopt welding to form, and are provided with 4 movable bolts that are arranged symmetrically with 2; Be fixed by bolts on card assembly 1, on upper and lower card assembly, correspondence position is open slot, by movable bolt 2, connects upper and lower card assembly; On upper card assembly, be provided with a rotating shaft 5, can, at flexible rotating within the scope of 180 ° of levels, a bolt hole be set in the middle of rotating shaft 5 and connect clevis eye 4.
The upper and lower card assembly surface of described a kind of steel tower integral hoisting angle steel jig arranges respectively MC nylon lining, zinc-plated for the protection of steel tower.
During use, be arranged on iron tower main material angle steel, utilize 4 movable bolts that are arranged symmetrically with to connect upper and lower card assembly.
For guaranteeing to swing in steel tower integral lifting process, cause steel tower integral hoisting angle steel jig to be subject to force direction inconsistent with design, it on, block on assembly a rotating shaft is set, can be at flexible rotating within the scope of 180 ° of levels.In the middle of rotating shaft, a bolt hole is set, is used for connecting clevis eye.Clevis eye is flexible rotating in the vertical direction, thereby has realized freely rotating between upper and lower, left and right.
For the zinc coating of protection iron tower main material, the upper and lower card assembly surface of steel tower integral hoisting angle steel jig arranges respectively MC nylon lining.Not only can protect zinc layer but also can play to sliding effect.
Convenient when applying at the scene, avoid repeated disassembled and assembled bolt, steel tower integral hoisting angle steel jig is to be fixed by bolts on upper card assembly with 4 movable bolts, on upper and lower card assembly, correspondence position is open slot.
Above-mentioned a kind of steel tower integral hoisting angle steel jig, is all to adopt steel material to make, and safety factor is more than 2.5 times.Can according to circuit, lift weight and the main material specification size of steel tower, be processed into the steel tower integral hoisting angle steel jig of different operating load.
The utility model is being used four symmetrical steel tower integral hoisting angle steel jigs of the reliable installation of main angle iron position inside principal post and crosspiece hinge-point.Clevis eye is towards crane direction in place, less if cross-arm angle steel Hoisting Position intersects iron, and during the stressed demand that can not meet integral hoisting, cross-arm is taked reinforcement measure.During installation, upper card assembly 1 is placed on to angle steel outside, lower card assembly 3 is placed on angle steel inner side, with movable bolt 2, connects upper and lower card assembly, and fastening nut above it, is connected firmly upper and lower card assembly.Lifting steel rope is connected in rotating shaft to 5 with clevis eye 4.
In actual field application, the workload of steel tower integral hoisting angle steel jig requires to make according to the maximum of engineering demand, and safety factor requires to be more than or equal to 2.5 times.Generally Ke electric armour clamp manufacturing company processes and tests.
The utility model usage range is to be subject to force direction to rotate up and down 120 °, and must not be lateral stressed, when not meeting this and require, should adjust crane position, guarantees that usage condition meets above-mentioned requirements.

Claims (2)

1. a steel tower integral hoisting angle steel jig, it is characterized in that: this steel tower integral hoisting angle steel jig is comprised of upper card assembly (1), lower card assembly (3), movable bolt (2), clevis eye (4), upper card assembly (1), lower card assembly (3) part adopt welding to form, and are provided with 4 movable bolts that are arranged symmetrically with (2); Be fixed by bolts to card assembly (1) upper, on upper and lower card assembly, correspondence position is open slot, by movable bolt (2), connects upper and lower card assembly; On upper card assembly, be provided with a rotating shaft (5), can, at flexible rotating within the scope of 180 ° of levels, a bolt hole be set in the middle of rotating shaft (5) and connect clevis eye (4).
2. a kind of steel tower integral hoisting angle steel jig according to claim 1, is characterized in that: described upper and lower card assembly surface arranges respectively MC nylon lining, zinc-plated for the protection of steel tower.
CN201320511969.6U 2013-08-21 2013-08-21 Angle steel clamp for integral hoisting of iron tower Expired - Lifetime CN203402807U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320511969.6U CN203402807U (en) 2013-08-21 2013-08-21 Angle steel clamp for integral hoisting of iron tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320511969.6U CN203402807U (en) 2013-08-21 2013-08-21 Angle steel clamp for integral hoisting of iron tower

Publications (1)

Publication Number Publication Date
CN203402807U true CN203402807U (en) 2014-01-22

Family

ID=49938746

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320511969.6U Expired - Lifetime CN203402807U (en) 2013-08-21 2013-08-21 Angle steel clamp for integral hoisting of iron tower

Country Status (1)

Country Link
CN (1) CN203402807U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105401779A (en) * 2015-11-27 2016-03-16 浙江省送变电工程公司 Special lifting device for main tube of steel tube tower
CN108840222A (en) * 2018-08-15 2018-11-20 国网冀北电力有限公司秦皇岛供电公司 Angle bar lifts fixed device
KR20190006652A (en) * 2017-07-11 2019-01-21 삼성중공업 주식회사 Transport assisting apparatus
AU2019216676B2 (en) * 2017-12-21 2020-10-29 Alexander Rose Solar panel mounting system for towers
CN115924779A (en) * 2022-11-22 2023-04-07 国网宁夏电力有限公司电力科学研究院 Portable heavy object hoisting method for electric power iron tower
CN116715137A (en) * 2023-08-09 2023-09-08 国网山西省电力公司晋中供电公司 Transmission line pole tower traction fixture and crane

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105401779A (en) * 2015-11-27 2016-03-16 浙江省送变电工程公司 Special lifting device for main tube of steel tube tower
KR20190006652A (en) * 2017-07-11 2019-01-21 삼성중공업 주식회사 Transport assisting apparatus
KR102505797B1 (en) 2017-07-11 2023-03-06 삼성중공업 주식회사 Transport assisting apparatus
AU2019216676B2 (en) * 2017-12-21 2020-10-29 Alexander Rose Solar panel mounting system for towers
CN108840222A (en) * 2018-08-15 2018-11-20 国网冀北电力有限公司秦皇岛供电公司 Angle bar lifts fixed device
CN108840222B (en) * 2018-08-15 2023-09-01 国网冀北电力有限公司秦皇岛供电公司 Angle iron hoisting and fixing device
CN115924779A (en) * 2022-11-22 2023-04-07 国网宁夏电力有限公司电力科学研究院 Portable heavy object hoisting method for electric power iron tower
CN116715137A (en) * 2023-08-09 2023-09-08 国网山西省电力公司晋中供电公司 Transmission line pole tower traction fixture and crane
CN116715137B (en) * 2023-08-09 2023-11-21 国网山西省电力公司晋中供电公司 Transmission line pole tower traction fixture and crane

Similar Documents

Publication Publication Date Title
CN203402807U (en) Angle steel clamp for integral hoisting of iron tower
CN109882065B (en) General type steel frame cat ladder climbing device
CN204847918U (en) Wire rope plastic guider
CN204847923U (en) Hoist anti -swing puts device
CN202178529U (en) Jack-up fixture for tower
CN203903813U (en) Clamping slot type hoisting protective device
CN201367332Y (en) Variable hoisting pulley block
CN202927423U (en) Hanging and fixing device universally used for overhead line structure cross arm angle iron
CN202917897U (en) Cable hoisting horizontal pulley
CN201932774U (en) Electric cable collecting and releasing system on gantry crane
CN204715858U (en) A kind of tower erection protection instrument
CN204897249U (en) Swing arm tower crane
CN204702399U (en) A kind of Steel plate hoisting implement
CN202912549U (en) Hydraulic motor replacing device
CN204096916U (en) Coil grab and clamping piece thereof
CN103213899A (en) Auxiliary grinding wheel hoisting device
CN203151001U (en) A power cable lifting device
CN202787930U (en) Hanging basket for high-place operations
CN205114838U (en) A mousing -hook structure for electric block
CN204689375U (en) A kind of load hook bearing assembly
CN204778336U (en) Crane hook device
CN220223307U (en) Four-bar linkage counterweight structure for limiting heavy hammer of bridge crane
CN203632119U (en) Tightener
CN203295025U (en) Clamping tool for hoisting single H beam
CN203474247U (en) Flat-bulb steel handling instrument

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20140122

CX01 Expiry of patent term