CN203359759U - Double-row shoulder pole beam hoisting tool - Google Patents
Double-row shoulder pole beam hoisting tool Download PDFInfo
- Publication number
- CN203359759U CN203359759U CN 201320425951 CN201320425951U CN203359759U CN 203359759 U CN203359759 U CN 203359759U CN 201320425951 CN201320425951 CN 201320425951 CN 201320425951 U CN201320425951 U CN 201320425951U CN 203359759 U CN203359759 U CN 203359759U
- Authority
- CN
- China
- Prior art keywords
- shaped steel
- plate
- steel
- hanger
- shackle
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Abstract
A double-row shoulder pole beam hoisting tool is production line equipment used for hoisting devices similar to ERW steel pipes, and comprises two pieces of H-shaped steel (1) and two lifting lug plates. The double-row shoulder pole beam hoisting tool is characterized in that the two pieces of H-shaped steel (1) are arranged parallelly; a plurality of connecting plates are arranged between the two pieces of H-shaped steel; the two lifting lug plates are two steel plates, and are arranged at intervals with certain distance; the two pieces of steel penetrate through two holes in the lower parts of lifting lug holes of the two lifting lug plates to form an integral hoisting tool. The double-row shoulder pole beam hoisting tool, provided by the utility model has the advantages that the structure is simple, the manufacture is convenient, the hoisting is safe and reliable, the working efficiency is improved and the engineering cost is reduced.
Description
Technical field
The utility model relates to a kind of suspender, and specifically, a kind of double row flat spreader beam suspender, for lifting similar ERW pipe production line equipment.
Background technology
Along with China's rapid development of economy, the large quantities of constructions of ERW pipe production line.Usually ERW pipe production line factory building is narrow and small, and equipment component is overweight, and a driving can not meet unloading of equipment and installation requirement, and the traditional work mode causes operation labor intensity large without special hanger, and efficiency is low.If use large-scale crane operation, Construction Cost is large.
Therefore known for ERW equipment unload and the installation measure exists above-mentioned all inconvenience and problem.
Summary of the invention
The purpose of this utility model, be to propose a kind of double row flat spreader beam suspender, for lifting ERW pipe production line equipment.
For achieving the above object, technical solution of the present utility model is:
A kind of double row flat spreader beam suspender, for lifting similar ERW pipe production line equipment, comprise two H shaped steel and two shackle plates, it is characterized in that:
Described two H shaped steel are set in parallel, and are provided with some roads between two H shaped steel and are connected and fixed plate, are made into the double row flat spreader beam, and some roads stiffener and flange plate and web welding are set between every H shaped steel, and the specifications and models of described H shaped steel are HM588*300*12*20;
Described two shackle plates are two block plates, the space certain distance is set in parallel, the rectangular shape of every block plate, shackle plate adopts the thick steel plate of 40mm, and be provided with a hanger circular arc on its long limit, the radius of hanger circular arc is 600mm, is provided with the hanger hole below the hanger circular arc, the radius in hanger hole is 250mm, and the left and right sides below the hanger hole is parallel has two holes;
Wherein: described two shaped steel are through complete suspender of two hole formations of below, two shackle plate hanger holes.
Double row flat spreader beam suspender of the present utility model can also be further achieved by the following technical measures.
Aforesaid double row flat spreader beam suspender is characterized in that described shackle plate moves freely setting on H shaped steel, and the fixed form between shackle plate and H shaped steel is inclined sizing block.
Aforesaid double row flat spreader beam suspender, is characterized in that, the steel pipe of half sheet DN40 is welded in edges and corners, described shaped steel upper and lower flange plate edge, the stressed wearing and tearing of steel rope while preventing from lifting by crane.
After adopting technique scheme, double row flat spreader beam suspender of the present utility model has the following advantages:
1, simple in structure, easy to make, service free is safeguarded, applied range;
2, Hoisting Security reliable, increase work efficiency, guarantee the duration, the utilization of this suspender has guaranteed that equipment unloads in time, installs in time to field energy, has saved and has waited for that large-scale crane marches into the arena time of installation;
3, reduce engineering cost, save 15 machine-teams of 200 tons-300 tons cranes, 300,000 (machine-team and the labour costs etc.) of reducing expenses altogether.
The accompanying drawing explanation
The hanger structure schematic diagram that Fig. 1 is the utility model embodiment;
Fig. 2 is the A-A cutaway view in Fig. 1;
The force analysis schematic diagram of the suspender that Fig. 3 is the utility model embodiment;
The stressed sketch of the shackle plate of the suspender that Fig. 4 is the utility model embodiment.
In figure: 1 shaped steel, 2 the 1st shackle plates, 3 the 2nd shackle plates, 4 the 1st are connected and fixed plate, and 5 the 2nd are connected and fixed plate, 6 stiffeners, 7 hanger circular arcs, 8 hanger holes.
The specific embodiment
Below in conjunction with embodiment and accompanying drawing thereof, the utility model is illustrated further.
In sky, Tianjin pipe Taiyuan Iron and Steel Co. ERW welded tube projects, be this condition of 32t according to two overhead traveling crane biggest lifting capacities in factory building, two length of linking up with while driving a vehicle side by side are between 9 meters-10 meters, for meeting 2 overhead traveling crane work compounds, need realize by a special carrying pole type beam handling and the installation of equipment, considering the weight of self, is 60 tons according to maximum weight-lifting equipment weight, selects 2 H section steel manufactures of HM588*300*12*20 to become the double row flat spreader beam.
Now refer to Fig. 1 and Fig. 2, the hanger structure schematic diagram that Fig. 1 is the utility model embodiment, the cutaway view that Fig. 2 is A-A in Fig. 1.As shown in the figure, described two H shaped steel 1 are and are arranged in parallel, be provided with two roads between two H shaped steel and be connected and fixed plate, the 1st be connected and fixed plate 4 and the 2nd and be connected and fixed plate 5, two road connecting panels all adopt the 20mm steel plate, and two H shaped steel center-to-center distances are 1 meter, and stiffener 6 adopts the 20mm steel plate to arrange at interval of 300mm, be made into the double row flat spreader beam, the specifications and models of described H shaped steel are HM588*300*12*20;
Described two shackle plates are two block plates, i.e. the 1st shackle plate 2 and the 2nd shackle plate 3, the space certain distance is and is arranged in parallel, the rectangular shape of every block plate, shackle plate adopts the thick steel plate of 40mm, and is provided with a hanger circular arc 7 on its long limit, the radius of hanger circular arc is 600mm, be provided with hanger hole 8 below hanger circular arc 7, the radius in hanger hole is 250mm, in the left and right sides in hanger hole, according to the distance of H shaped steel is parallel, has two holes;
Wherein: described two shaped steel are through complete suspender of two hole formations of below, two shackle plate hanger holes.Described shackle plate can move freely setting on H shaped steel 1, and the fixed form between shackle plate and H shaped steel is inclined sizing block.Edges and corners, described shaped steel upper and lower flange plate edge are welded and fixed the steel pipe of half sheet DN40, the stressed wearing and tearing of steel rope while preventing from lifting by crane.
Force analysis for the suspender that lifts ERW equipment of the present utility model:
The force analysis schematic diagram of the suspender that Fig. 3 is the utility model embodiment.According to the maximum deadweight of equipment, 60t calculates, and according to on-site actual situations, need be lifted with the double row flat spreader beam, and four suspension centres are set, because shoulder pole girder is welded as a whole, twin beams is checked and can be reduced to the single-beam check, and force analysis as shown in Figure 3.
According to the needs of engineering reality, the maximum defluxion of beam and hard-over are no more than a certain specified value.The rigidity condition of beam is thus:
|y|
max≤[y]
|θ|
max≤[θ]
Figure 3 shows that a crane girder, 10 meter two suspension centre spacing of span length is 9 meters, biggest lifting capacity F
w=300KN, beam is the I-beam section cross section, permissible stress [σ]=140MPa(is according to using the steel plate model), the license amount of deflection
elastic modulus E=200GP
a(according to using the steel plate model to check in).
The selecting and checking of material
Select 2 H shaped steel of 588*300*12*20, when hoisting heavy, during at suspender mid point C, the C cross section will produce maximal bending moment and maximum defluxion.Maximal bending moment is
According to strength condition, obtain
Table look-up this H shaped steel cross section property, W
z=600.52 cm
3, I
z=113283cm
4.
Rigidity is checked
Therefore meet the demands.
The stressed sketch of the shackle plate of the suspender that Fig. 4 is the utility model embodiment.When hanger bears maximum load, by Fig. 3 and Fig. 4, can be found out, main strength weak point position b, a, a place, if this three place meets requirement of strength, other positions are no problem.
Known: Fmax=30T
Yield strength: σ s=235N/ ㎜ 2 (thickness of slab is greater than 16mm<=40mm)
Tensile strength: σ b=205N/ ㎜ 2 (thickness of slab is greater than 16mm<=40mm)
At first check a district:
A0=Fmax/σs=30T/235N/㎜ 2=1276㎜ 2
Steel plate thickness δ=40mm
a‘=A0/δ=1276/40mm=32mm
Safety factor is made as 1.25
A>=1.25a ', a, a place meets requirement of strength; On-the-spot processing a gets 150mm
B district strength check, be pulling force because it is stressed, and whole steel plate bears shearing, so select: tensile strength: σ b=205N/ ㎜ 2 (thickness of slab is greater than 16mm<=40mm) is checked:
Tmax=2Fmax=60T
σb=Tmax/A0
Ab=Tmax/σb=60T/205N/㎜ 2=2967㎜ 2
Steel plate thickness δ=40mm
b’=Ab/δ=2967㎜ 2/40mm=73mm
Safety factor is made as 1.25
If b>=1.25b ', the b place meets requirement of strength; This beam b is in to add and gets 200mm man-hour
Illustrate: in general check process, as without specific (special) requirements (essential environmental factors as strong wind, at a high speed), safety factor can not got.
Meet construction requirement through calculating and adjusting this suspender.
ERW welded tube engineering of constructing at sky, Tianjin pipe Taiyuan Iron and Steel Co. for the suspender that lifts ERW equipment of the present utility model is used, stability, the reliability of on-the-spot actual verification suspender, effect is remarkable, can not only be applied in the ERW Welded Pipe Plant and carry out equipment hoisting, and also can apply in corresponding equipment installation project, for saving cost, improve work efficiency and crudy and all have very important significance.
Above embodiment is only for illustration of the utility model, but not, to restriction of the present utility model, person skilled in the relevant technique, in the situation that do not break away from spirit and scope of the present utility model, can also make various conversion or variation.Therefore, all technical schemes that are equal to also should belong to category of the present utility model, should be limited by each claim.
Claims (3)
1. a double row flat spreader beam suspender, for lifting ERW pipe production line equipment, comprise two H shaped steel (1) and two shackle plates, it is characterized in that:
Described two H shaped steel (1) are set in parallel, be provided with some roads between two H shaped steel and be connected and fixed plate, be made into the double row flat spreader beam, some roads stiffener and flange plate and web welding are set between every H shaped steel, the specifications and models of described H shaped steel are HM588*300*12*20;
Described two shackle plates are two block plates, the space certain distance is set in parallel, the rectangular shape of every block plate, shackle plate adopts the thick steel plate of 40mm, and be provided with a hanger circular arc (7) on its long limit, the radius of hanger circular arc is 600mm, in the below of hanger circular arc (7), is provided with hanger hole (8), the radius in hanger hole is 250mm, and the left and right sides below the hanger hole is parallel has two holes;
Wherein: described two shaped steel are through complete suspender of two hole formations of below, two shackle plate hanger holes.
2. double row flat spreader beam suspender as claimed in claim 1, is characterized in that, described shackle plate moves freely setting on H shaped steel (1), and the fixed form between shackle plate and H shaped steel is inclined sizing block.
3. double row flat spreader beam suspender as claimed in claim 1, is characterized in that, the steel pipe of half sheet DN40 is welded in edges and corners, described shaped steel upper and lower flange plate edge, the stressed wearing and tearing of steel rope while preventing from lifting by crane.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201320425951 CN203359759U (en) | 2013-07-17 | 2013-07-17 | Double-row shoulder pole beam hoisting tool |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201320425951 CN203359759U (en) | 2013-07-17 | 2013-07-17 | Double-row shoulder pole beam hoisting tool |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203359759U true CN203359759U (en) | 2013-12-25 |
Family
ID=49807552
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201320425951 Expired - Lifetime CN203359759U (en) | 2013-07-17 | 2013-07-17 | Double-row shoulder pole beam hoisting tool |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203359759U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105484502A (en) * | 2014-10-10 | 2016-04-13 | 五冶集团上海有限公司 | Combination installation method for steel structure roofing purlins and support bars of industrial factory building |
-
2013
- 2013-07-17 CN CN 201320425951 patent/CN203359759U/en not_active Expired - Lifetime
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105484502A (en) * | 2014-10-10 | 2016-04-13 | 五冶集团上海有限公司 | Combination installation method for steel structure roofing purlins and support bars of industrial factory building |
CN105484502B (en) * | 2014-10-10 | 2017-11-07 | 五冶集团上海有限公司 | A kind of industrial premises steel structural roof purlin and support bar combined installation method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201089696Y (en) | Spar boom of explosion-proof suspension crane | |
CN202913337U (en) | Prestress combination box girder composed of concrete frange plates and corrugated steel webs | |
CN203359759U (en) | Double-row shoulder pole beam hoisting tool | |
CN202766101U (en) | Trapezoid-shaped corrugated web box type main beam for crane | |
CN207738316U (en) | Large scale single wall bottom board steel lifting box integral hoisting suspender | |
CN204418000U (en) | A kind of Long span steel-concrete composite beam cable-stayed bridge ballast system | |
CN203213637U (en) | Roadbed box for walking on floor of larger crawler crane | |
CN207812836U (en) | A kind of L-type steel structural elements | |
CN215925647U (en) | Arch rib buckle cable anchoring beam for tower buckle integration | |
CN207844882U (en) | Steel column and crane girder connecting structure | |
CN205935199U (en) | Can improve P type beam -column connecting joint of bolt atress under static load | |
CN106677051B (en) | A kind of steel boxboard beam mixing beam bridge suitable for mountain area condition | |
CN205973445U (en) | Equipment hoist and mount anchor roof beam device | |
CN201024038Y (en) | Suspension girder for two trolleys synchronous hoisting | |
CN202766100U (en) | Sine-corrugation web box type main beam for crane | |
CN201052944Y (en) | Combined truss type steel crane beam | |
CN101875474A (en) | Gantry crane frame in wind-resisting structure | |
CN202023299U (en) | Variable cross-section box type steel beam | |
CN213011524U (en) | Steel construction lifting hoisting point device | |
CN210263517U (en) | Frame-combined steel plate shear wall structure | |
CN211034920U (en) | Reinforced combined bolt lifting lug | |
CN213358184U (en) | Roadbed box for large crawler crane | |
CN215706756U (en) | Track shoe convenient to install | |
CN215053059U (en) | Steel encloses purlin underground structure supporting device | |
CN215977848U (en) | Steel pipe shear wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CX01 | Expiry of patent term | ||
CX01 | Expiry of patent term |
Granted publication date: 20131225 |