CN203321543U - 高水压隧道分区防水构造 - Google Patents
高水压隧道分区防水构造 Download PDFInfo
- Publication number
- CN203321543U CN203321543U CN2013200443369U CN201320044336U CN203321543U CN 203321543 U CN203321543 U CN 203321543U CN 2013200443369 U CN2013200443369 U CN 2013200443369U CN 201320044336 U CN201320044336 U CN 201320044336U CN 203321543 U CN203321543 U CN 203321543U
- Authority
- CN
- China
- Prior art keywords
- isolation
- totally
- section
- changeover portion
- hydraulic pressure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
高水压隧道分区防水构造,以使隧道二次衬砌结构更加安全、可靠、经济,并有效保护地表水环境。它包括穿越不良地质构造的全封闭段(L1)及所对应的全封闭二次衬砌结构(10),以及设置在全封闭段(L1)两侧的排放段(L3)及所对应的排放段二次衬砌结构(30)。所述全封闭段(L1)与排放段(L3)之间设置隔离过渡段(L2)及所对应的隔离过渡段二次衬砌结构(20),仅在排放段二次衬砌结构(30)背后设置排水系统(31)。
Description
技术领域
本实用新型涉及铁路隧道、公路隧道、市政隧道工程,特别涉及一种高水压隧道分区防水构造。
背景技术
随着交通事业的蓬勃发展,越来越多的铁路隧道、公路隧道建设将成为必要。长期以来,为了避免或减弱地下水对隧道结构的作用,保证隧道主体结构安全,我国山岭隧道大多按照“以排为主”的原则设计和建造,忽视了隧道建设对环境产生的负面影响。由于大量地下水流失,造成地表泉井干枯、地表开裂沉降、岩溶塌陷、土壤砂化等环境影响问题。随着国家可持续发展战略的深化,如何保护自然生态环境成为隧道设计、施工关键技术之一。
一座隧道纵向各段地层岩性、地质构造、地下水发育程度及地下水压分布均有所不同。隧道设计中为了保护环境,经常需要根据地质情况设置穿越不良地质构造的全封闭段,在全封闭段的两侧设置排放段(以排为主或限量排放)。如此就带来了一个问题,地下水在通过围岩内注浆封堵后沿纵向串流,通过注浆堵水的全封闭段的长度将无法确定或者大幅度延长,如何进行“分区防水”是隧道设计和建造中的一个难点。目前,国内针对高水压隧道铁路隧道、公路隧道的分区防水设计尚属空白,一般情况下都是根据地质情况适当延长全封闭衬砌段的设计长度,随意性较大,且无科学依据,同时是否能够达到保护环境和结构安全可靠的设计目的也是未知之数。
实用新型内容
本实用新型所要解决的技术问题是提供一种高水压隧道分区防水构造,以使隧道二次衬砌结构更加安全、可靠、经济,并有效保护地表水环 境。
本实用新型解决其技术问题所采用的技术方案如下:
本实用新型的高水压隧道分区防水构造,包括穿越不良地质构造的全封闭段及所对应的全封闭二次衬砌结构,以及设置在全封闭段两侧的排放段及所对应的排放段二次衬砌结构,其特征是:所述全封闭段与排放段之间设置隔离过渡段及所对应的隔离过渡段二次衬砌结构,仅在排放段二次衬砌结构背后设置排水系统。
本实用新型的有益效果是,在全封闭段与排放段之间设置隔离过渡段,且能够准确确定隔离过渡段二次衬砌结构外水压力分布,根据外水压力分布按相关设计规范确定的二次衬砌结构更加安全、可靠、经济,同时也能够有效保护地表水环境。
附图说明
本说明书包括如下一幅附图:
图1是本实用新型高水压隧道分区防水构造的结构示意图。
图中示出部位、构造及所对应的标记:全封闭段L1、隔离过渡段L2、排放段L3;全封闭二次衬砌结构10、隔离过渡段二次衬砌结构20、排放段二次衬砌结构30、排水系统31。
具体实施方式
下面结合附图和实施例对本实用新型进一步说明。
参照图1,图中A为隧道不良地质构造。本实用新型的高水压隧道分区防水构造,包括穿越不良地质构造的全封闭段L1及所对应的全封闭二次衬砌结构10,以及设置在全封闭段L1两侧的排放段L3及所对应的排放段二次衬砌结构30,所述全封闭段L1与排放段L3之间设置隔离过渡段L2及所对应的隔离过渡段二次衬砌结构20,仅在排放段二次衬砌结构30背后设置排水系统31。
全封闭二次衬砌结构10所承受的外水压力为P1=γH1。
排放段二次衬砌结构30所承受的外水压力为P2=γH2。
隔离过渡段二次衬砌结构20的抗水压能力按隔离过渡段L2水压分布 确定,其水压分布为:
当排放段二次衬砌结构30端头排水通畅时,隔离过渡段L2水压分布为:
当排放段二次衬砌结构30端头排水通畅,且隔离过渡段L2地下水渗流主要由全封闭二次衬砌结构10端补给,隔离过渡段L2范围补给强度较小时,隔离过渡段L2水压分布为
上述各计算式中:
x——计算点距离全封堵段长度
Px——距离全封闭段(L1)的长度为x处的水压
γ——水的容重
H1——全封闭段(L1)端头水头高度
H2——排放段(L3)端头水头高度
l——隔离过渡段(L2)长度
w——隔离过渡段(L2)地下水补给强度,即盲管间单位面积、单位时间补给地下水水量
能够准确计算出隔离过渡段二次衬砌结构外水压力分布,使本领域技 术人员根据外水压力分布按相关设计规范可设计出更加安全、可靠、经济的二次衬砌结构,同时也能够有效保护地表水环境。
Claims (4)
1.高水压隧道分区防水构造,包括穿越不良地质构造的全封闭段(L1)及所对应的全封闭二次衬砌结构(10),以及设置在全封闭段(L1)两侧的排放段(L3)及所对应的排放段二次衬砌结构(30),其特征是:所述全封闭段(L1)与排放段(L3)之间设置隔离过渡段(L2)及所对应的隔离过渡段二次衬砌结构(20),仅在排放段二次衬砌结构(30)背后设置排水系统(31)。
2.如权利要求1所述的高水压隧道分区防水构造,其特征是:所述全封闭二次衬砌结构(10)所承受的外水压力为P1=γH1,式中γ为水的容重,H1为全封闭段(L1)端头水头高度。
3.如权利要求2所述的高水压隧道分区防水构造,其特征是:所述排放段二次衬砌结构(30)所承受的外水压力为P2=γH2,式中γ为水的容重,H2为排放段(L3)端头水头高度。
4.如权利要求3所述的高水压隧道分区防水构造,其特征是:
所述隔离过渡段二次衬砌结构(20)的抗水压能力按隔离过渡段(L2)水压分布确定,其水压分布为
当排放段二次衬砌结构(30)端头排水通畅时,隔离过渡段(L2)水压分布为
当排放段二次衬砌结构(30)端头排水通畅,且隔离过渡段(L2)地下水渗流主要由全封闭二次衬砌结构(10)端补给,隔离过渡段(L2)范围补给强度较小时,隔离过渡段(L2)水压分布为
式中x——计算点距离全封堵段长度
Px——距离全封闭段(L1)的长度为x处的水压
γ——水的容重
H1——全封闭段(L1)端头水头高度
H2——排放段(L3)端头水头高度
l——隔离过渡段(L2)长度
w——隔离过渡段(L2)地下水补给强度,即盲管间单位面积、单位时间补给地下水水量
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2013200443369U CN203321543U (zh) | 2013-01-28 | 2013-01-28 | 高水压隧道分区防水构造 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2013200443369U CN203321543U (zh) | 2013-01-28 | 2013-01-28 | 高水压隧道分区防水构造 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203321543U true CN203321543U (zh) | 2013-12-04 |
Family
ID=49660905
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2013200443369U Expired - Fee Related CN203321543U (zh) | 2013-01-28 | 2013-01-28 | 高水压隧道分区防水构造 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203321543U (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103061789A (zh) * | 2013-01-28 | 2013-04-24 | 中铁二院工程集团有限责任公司 | 高水压隧道分区防水构造 |
CN107178392A (zh) * | 2017-06-28 | 2017-09-19 | 中铁第四勘察设计院集团有限公司 | 一种控制矿山法隧道二次衬砌水压力的方法 |
CN109667607A (zh) * | 2018-12-24 | 2019-04-23 | 中铁十八局集团有限公司 | 一种隧道分区防水施工工艺 |
-
2013
- 2013-01-28 CN CN2013200443369U patent/CN203321543U/zh not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103061789A (zh) * | 2013-01-28 | 2013-04-24 | 中铁二院工程集团有限责任公司 | 高水压隧道分区防水构造 |
CN107178392A (zh) * | 2017-06-28 | 2017-09-19 | 中铁第四勘察设计院集团有限公司 | 一种控制矿山法隧道二次衬砌水压力的方法 |
CN109667607A (zh) * | 2018-12-24 | 2019-04-23 | 中铁十八局集团有限公司 | 一种隧道分区防水施工工艺 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102900441B (zh) | 基于围岩完全变形控制的中国隧道修建方法 | |
CN103306680B (zh) | 既有单线隧道扩建为多线隧道的施工方法 | |
CN104278993B (zh) | 一种偏压隧道斜交进洞的施工方法 | |
CN104265307A (zh) | 软硬不均地层土压平衡盾构隧道下穿铁路既有线施工方法 | |
CN204312099U (zh) | 基于环境保护的隧道涌水防治系统 | |
CN101070759A (zh) | 一种薄基岩浅埋煤层保水开采适用条件分类方法 | |
CN103184871B (zh) | 一种保护重要水体的煤柱留设开采方法 | |
CN203321543U (zh) | 高水压隧道分区防水构造 | |
CN102182464A (zh) | 通道结构的施工结构及施工方法 | |
CN101793154A (zh) | 利用隧道围岩地质参数和设置分流孔的注浆堵水方法 | |
CN102996135A (zh) | 超深覆土盾构穿越复杂地层施工方法 | |
CN103291312B (zh) | 能够实现三维注浆的盾构机 | |
CN202132053U (zh) | Ⅵ级围岩双线隧道衬砌支护结构 | |
CN105528492A (zh) | 一种基于折算转化渗透系数的隧道排水量分区控制方法 | |
CN202991051U (zh) | 无止水帘布盾构接收加固结构 | |
CN103061789A (zh) | 高水压隧道分区防水构造 | |
CN201828353U (zh) | 人工冻土的温度场测试装置 | |
CN103198218A (zh) | 近接隧道对高速铁路路基的风险评估方法和装置 | |
CN205049133U (zh) | 一种隧道围岩变形动态监测系统 | |
CN112282849A (zh) | 一种测量深埋隧洞衬砌外水压力的监测装置及方法 | |
CN203347799U (zh) | 能够实现三维注浆的盾构机 | |
CN103132487A (zh) | 一种减小面板堆石坝水平位移的方法及该面板堆石坝 | |
CN202693189U (zh) | 一种测量超高压大流量岩溶裂隙水压力的封堵结构 | |
CN204825934U (zh) | 一种边坡排水系统 | |
CN103556999B (zh) | 一种富水软弱地层盾构掘进土压确定方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20131204 Termination date: 20220128 |
|