CN203249552U CN 201320176243 CN201320176243U CN203249552U CN 203249552 U CN203249552 U CN 203249552U CN 201320176243 CN201320176243 CN 201320176243 CN 201320176243 U CN201320176243 U CN 201320176243U CN 203249552 U CN203249552 U CN 203249552U
Authority
CN
China
Prior art keywords
suspension type
blasting charge
lifting rope
blaster
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201320176243
Other languages
Chinese (zh)
Inventor
罗勤
滕世宇
贾晓非
何庆鸿
周良
王飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Gezhouba Group Co Ltd
Original Assignee
China Gezhouba Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group Co Ltd filed Critical China Gezhouba Group Co Ltd
Priority to CN 201320176243 priority Critical patent/CN203249552U/en
Application granted granted Critical
Publication of CN203249552U publication Critical patent/CN203249552U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Drilling And Exploitation, And Mining Machines And Methods (AREA)

Abstract

A suspension type blaster comprises a blasting charge and igniters of the suspension type blaster. The upper portion of the blasting charge is connected with a first lifting rope, and each igniter comprises a detonator arranged in the blasting charge and a detonating cord connected with the detonator. A guide pipe is further arranged on one side of the blasting charge, and the first lifting rope is a steel wire rope. At least two set of igniters are arranged to guarantee successful detonation. The suspension type blaster is simple in structure, convenient to operate and capable of avoiding the situation that construction personnel carries out blasting operation construction in a pioneer well, guarantees construction safety, can greatly reduce construction cost, meanwhile, improves working efficiency and is very suitable for being used in the grotto of a vertical shaft structure.

Description

A kind of suspension type blaster
Technical field
The utility model relates to a kind of blaster, particularly a kind of suspension type blaster for underground cavern excavation.
Background technology
In the underground excavation engineering construction, usually run into the shaft structure cavern, such as gate shaft, pressure regulation vertical shaft, diversion vertical shaft etc.For this class vertical shaft cavern, the pilot shaft excavation is carried out first in general employing, carries out the construction method that vertical shaft digs again, and wherein the effect of pilot shaft is mainly as the slide slag passage that digs.And the construction method of pilot shaft has two classes usually, and namely anti-well bores method and drilling and blasting method.Because anti-well brill method adopts the raise boring machine drilling and forming hole, construction cost is higher, and success rate is lower, therefore adopt drilling and blasting methods, and in the drill bursting construction process, workmen's operation such as must in pilot shaft, hole, slag tap more, potential safety hazard is very outstanding, and operating efficiency is also low.
Summary of the invention
The purpose of this utility model provides a kind of suspension type blaster, can avoid workmen's security hidden trouble that operation exists in pilot shaft, and also greatly raising of operating efficiency, and construction cost is also low.
In order to solve the problems of the technologies described above, the technical solution of the utility model is: a kind of suspension type blaster, comprise the blasting charge and apparatus to cause bursting thereof, the top of the blasting charge is connected with the first lifting rope, and described apparatus to cause bursting comprises the detonator of being located at blasting charge inside and the primacord that is connected with detonator.
One side of the described blasting charge also is provided with guide pipe.
Described the first lifting rope is seizing wire.
Described apparatus to cause bursting is at least 2 covers, with the ignition that assures success.
The suspension type blaster that the utility model provides, simple in structure, easy to operate, be highly suitable in the shaft structure cavern and use, and rock ballast will directly be scattering into the shaft bottom after the explosion, so that the workmen needn't slag tap, be conducive to construction safety in well.
Description of drawings
The utility model is described in further detail below in conjunction with drawings and Examples.
Fig. 1 is structural representation of the present utility model.
Fig. 2 is blast hole plane of arrangement schematic diagram in the pilot shaft.
Fig. 3 is that the utility model is installed and used schematic diagram.
The specific embodiment
As shown in Figure 1, the utility model comprises the blasting charge 2 and apparatus to cause bursting thereof, and the top of the blasting charge 2 is connected with the first lifting rope 1, and described apparatus to cause bursting comprises the detonator 3 of being located at blasting charge inside and the primacord 4 that is connected with detonator.
One side of the described blasting charge 2 also is provided with guide pipe 5.
Described the first lifting rope 1 is seizing wire.
Described apparatus to cause bursting is at least 2 covers.
It is of the present utility model that to install and use process as follows:
1) finishes first as shown in Figure 2, the boring work of pilot shaft 7 interior all blast holes 6 in the vertical shaft 8 according to designing requirement.
2) by the hole suspension type blaster is installed: as shown in Figure 3, adopt the second lifting rope 9 to pierce in the sleeve pipe 5 of the present utility model, afterwards transfer bottom, hole to blast hole 6 together with the utility model, then continue to transfer one section second lifting rope 9, prop up workmen in the hole is tethered in slightly larger in diameter the second lifting rope 9 in the stopper 10 of blast hole end in the construction of pilot shaft, the staff of blast hole 6 tops second lifting rope 9 of pulling back, stopper 10 is blocked at the bottom of blast hole 6 holes, poured into sandstone 11 from blast hole 6 at last blast hole is stopped up.
3) explosion: after the blaster installation of all blast holes, all primacords are connected with firing switch outside the aperture, can carry out explosion.Rock ballast will directly be scattering into the shaft bottom after the explosion, so the workmen needn't slag tap in well, and this also is conducive to construction safety.

Claims (1)

1. a suspension type blaster comprises the blasting charge and apparatus to cause bursting thereof, it is characterized in that: the top of the blasting charge is connected with the first lifting rope, and described apparatus to cause bursting comprises the detonator of being located at blasting charge inside and the primacord that is connected with detonator; One side of the described blasting charge also is provided with guide pipe; Described the first lifting rope is seizing wire; Described apparatus to cause bursting is at least 2 covers.
CN 201320176243 2013-04-10 2013-04-10 Suspension type blaster Expired - Fee Related CN203249552U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201320176243 CN203249552U (en) 2013-04-10 2013-04-10 Suspension type blaster

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201320176243 CN203249552U (en) 2013-04-10 2013-04-10 Suspension type blaster

Publications (1)

Publication Number Publication Date
CN203249552U true CN203249552U (en) 2013-10-23

Family

ID=49375985

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201320176243 Expired - Fee Related CN203249552U (en) 2013-04-10 2013-04-10 Suspension type blaster

Country Status (1)

Country Link
CN (1) CN203249552U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112729034A (en) * 2020-12-14 2021-04-30 湖南黄金洞矿业有限责任公司 Blasting method for treating ore pass blockage in ascending mode
CN115014140A (en) * 2022-06-25 2022-09-06 天津矿山工程有限公司 Method for blasting and drifting section by section in hole by drilling casing method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112729034A (en) * 2020-12-14 2021-04-30 湖南黄金洞矿业有限责任公司 Blasting method for treating ore pass blockage in ascending mode
CN115014140A (en) * 2022-06-25 2022-09-06 天津矿山工程有限公司 Method for blasting and drifting section by section in hole by drilling casing method

Similar Documents

Publication Publication Date Title
CN113294134B (en) Hydraulic fracturing and methane in-situ blasting synergistic fracturing permeability-increasing method
CN104314606B (en) Hydraulic slotted liner technique and the combined reinforced pumping method of gas explosion fracturing coal body in a kind of boring
WO2016165396A1 (en) Downhole coal seam pulse detonation wave directional fracturing permeability-increasing method
CN104278978B (en) Soluble bridge plug fracturing technology pipe string and fracturing method thereof
CN102997764B (en) Method for effectively removing ore-pass blockage and blockage removal device
CN205047207U (en) Colliery binary channels segmentation in pit hydraulic fracturing device
CN104329113B (en) A kind of method of surface drilling standing seat earth release mash gas extraction
CN115522905B (en) Methane explosion fracturing device for shale gas reservoir and control method thereof
CN109372508A (en) The hydraulic orientation of underground coal mine cuts top equipment and its construction method
CN104278979A (en) Coiled tubing perforation bridge plug sealing, separating and fracturing method
CN203249552U (en) Suspension type blaster
CN102817633A (en) Device for draining gas by deep hole crack control blasting and precracking method
CN102877824A (en) Horizontal well staged and multi-cluster fracturing method by hydraulic jetting
CN103868419A (en) Smooth surface blasting construction method used in tunnel excavation process in hydraulic engineering
CN104110261A (en) Construction method for expanding excavation of shaft at one time in reverse mode
CN105201435A (en) Cable transmission clustering perforation operation explosion jam release method
CN113338873B (en) Shale gas reservoir multilateral well detonation pressure enhanced extraction method
CN204663509U (en) Anti-reflection system is shaken in carbon dioxide coal seam
CN207004498U (en) Infinite stages switching sliding sleeve fracturing tool
CN109209325A (en) A method of uncovering coal in vertical shaft is carried out using radial technology
CN106089173A (en) A kind of completion mode with protection reservoir packing function
CN107575164A (en) A kind of high-pressure hydraulic with the conditions of brill radially creeps into guider and method
CN116696342A (en) Front cabin type secondary explosion composite perforation method for coal-bed gas well
CN202900204U (en) Downhole throttle device for coiled tubing
CN203066956U (en) Oil and gas well perforating ground monitoring device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20131023

Termination date: 20210410