CN203188131U - 架设梁板施工独立扒杆设备 - Google Patents
架设梁板施工独立扒杆设备 Download PDFInfo
- Publication number
- CN203188131U CN203188131U CN 201320226617 CN201320226617U CN203188131U CN 203188131 U CN203188131 U CN 203188131U CN 201320226617 CN201320226617 CN 201320226617 CN 201320226617 U CN201320226617 U CN 201320226617U CN 203188131 U CN203188131 U CN 203188131U
- Authority
- CN
- China
- Prior art keywords
- wire rope
- truss rod
- derrick mast
- steel wire
- slab
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
本实用新型公开了一种架设梁板施工独立扒杆设备,包括支座、活动轴承、桁架杆、传动钢丝绳、吊钩、卷扬机、滑轮和固定钢丝绳,所述桁架杆经所述活动轴承安装在所述支座上,所述滑轮安设在所述桁架杆上,所述传动钢丝绳一端缠绕在所述卷扬机上,另一端经过所述滑轮与钩挂梁板的所述吊钩连接;所述固定钢丝绳用于固定所述桁架杆。设备简单、轻便,易于运输,不需导梁、龙门吊机等重型吊装设备即可架设30~40m以下跨径的桥梁;扒杆的安装移动简单,梁板在悬吊状态时横移容易且较安全,架设速度也较快。采用独立扒杆进行梁板架设施工,该方法操作简单,方法灵活,成本低,不受场地地形限制,而且工艺较成熟。
Description
技术领域
本实用新型涉及桥梁施工设备技术领域,尤其是一种架设梁板施工独立扒杆设备。
背景技术
在山区桥梁施工中,由于受到当地施工技术条件、人力资源、机械设备及现场地形的限制,采用独立扒杆进行梁板架设比较常见,受场地的限制,若采用架桥机或别的大型设备来架设,会造成设备的运输困难,并且如桥梁属于中小型桥梁,会使成本大幅度提高。
实用新型内容
本实用新型针对现有技术的不足,提出一种架设梁板施工独立扒杆设备,可在交通运输困难、大型机械设备无法进行梁板架设施工的地方来架设施工。
为了实现上述实用新型目的,本实用新型提供以下技术方案:一种架设梁板施工独立扒杆设备,包括支座、活动轴承、桁架杆、传动钢丝绳、吊钩、卷扬机、滑轮和固定钢丝绳,所述桁架杆经所述活动轴承安装在所述支座上,所述滑轮安设在所述桁架杆上,所述传动钢丝绳一端缠绕在所述卷扬机上,另一端经过所述滑轮与钩挂梁板的所述吊钩连接;所述固定钢丝绳用于固定所述桁架杆。
与现有技术相比,本实用新型具有以下优点:架设梁板不受架设孔墩台高度和桥孔下地基、河流水文状态等条件的限制;设备简单、轻便,易于运输,不需导梁、龙门吊机等重型吊装设备即可架设30~40m以下跨径的桥梁;扒杆的安装移动简单,梁板在悬吊状态时横移容易且较安全,架设速度也较快。采用独立扒杆进行梁板架设施工,该方法操作简单,方法灵活,成本低,不受场地地形限制,而且工艺较成熟。
附图说明
图1为本实用新型的结构示意图;
图2和图3为本实用新型使用状态过程图。
具体实施方式
下面结合附图对本实用新型进行详细描述,本部分的描述仅是示范性和解释性,不应对本实用新型的保护范围有任何的限制作用。
如图1所示的一种架设梁板施工独立扒杆设备,包括支座3、活动轴承2、桁架杆1、传动钢丝绳4、吊钩5、卷扬机6、滑轮7和固定钢丝绳8,所述桁架杆1经所述活动轴承2安装在所述支座3上,所述滑轮7安设在所述桁架杆1上,所述传动钢丝绳4一端缠绕在所述卷扬机6上,另一端经过所述滑轮7与钩挂梁板的所述吊钩5连接;所述固定钢丝绳8用于固定所述桁架杆1。
在实际应用中,一般是两幅本实用新型扒杆设备配合使用,用设在安装孔墩台上的两副独立扒杆设备,配合运梁设备,以绞车相互牵吊,在梁下无支架,无导梁支托的情况下,把梁悬空掉过桥孔,再横移、落梁,就位安装。
使用方法如图2和3所示:
1)、用设在安装孔墩台上的两副扒杆设备:前扒杆设备9及后扒杆设备10,配合运梁设备,以各自的卷扬机6相互牵吊,在梁板11下无支架、无导梁支托的情况下,把梁板11悬空吊过桥孔,再横移、落梁,就位安装。
2)、将前扒杆设备9及后扒杆设备10吊钩同系在梁板11前端吊耳处,当梁板11起吊后前端高约10厘米时,停止起吊,分别检查各扒杆设备,如卷扬机6、地锚,钢丝绳等,经确认无误后,再起动卷扬机6,前扒杆设备9的卷扬机6起吊,后扒杆设备10的卷扬机6回车,后扒杆设备10的卷扬机6配合梁前进速度。整个前进过程必须使梁前端低于后端,绝对禁止梁“昂头”。当梁吊运至前扒杆约1 米时,全部卷扬机停车,并将后扒杆吊点移至梁后端吊耳处,再由卷扬机配合起吊至支座上方。
3)、吊梁过程中为了确保安全,在起吊的前阶段,钢丝绳不是吊着梁前面的吊环,而是捆着梁体。当梁体运输到靠近前墩时,再取回后面的钢丝绳改换后面捆住梁体,然后再缓慢将梁移动前行,到盖梁的正上方时再下落到枕木上。这时再将前后钢丝绳改换到吊环上,将梁体精确定位。精确定位时前后方向由卷扬机带动一钢丝绳来调整,左右方向由两个链条葫芦来调整。架桥全过程中,吊绳拉力与梁体轴线方向几乎都保持垂直,不会对梁体产生较大的轴力。
4)、 梁就位时必须细致稳妥,使梁就位准确且与支座密贴,勿使支座产生变形,就位不准时,不得用撬杠移动梁。
5)、当第二块梁重复第一块梁安装程序完毕后,在此两块梁上将运梁轨道延至前扒杆处,再将边梁(中梁)牵至前后两扒杆下方,由前后扒杆起重机起吊梁且前后横移卷扬机配合放置于第一(二)块梁的左(右)侧,经盖梁上的滚动滑道,横移到位,再由杠杆千斤顶起梁,拆出滚动滑道,安装好支座就位。当一跨安装完毕后,将前扒杆过跨竖立,再重复上述吊装过程。
Claims (1)
1.一种架设梁板施工独立扒杆设备,其特征在于:包括支座、活动轴承、桁架杆、传动钢丝绳、吊钩、卷扬机、滑轮和固定钢丝绳,所述桁架杆经所述活动轴承安装在所述支座上,所述滑轮安设在所述桁架杆上,所述传动钢丝绳一端缠绕在所述卷扬机上,另一端经过所述滑轮与钩挂梁板的所述吊钩连接;所述固定钢丝绳用于固定所述桁架杆。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201320226617 CN203188131U (zh) | 2013-04-28 | 2013-04-28 | 架设梁板施工独立扒杆设备 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201320226617 CN203188131U (zh) | 2013-04-28 | 2013-04-28 | 架设梁板施工独立扒杆设备 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203188131U true CN203188131U (zh) | 2013-09-11 |
Family
ID=49105001
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201320226617 Expired - Lifetime CN203188131U (zh) | 2013-04-28 | 2013-04-28 | 架设梁板施工独立扒杆设备 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203188131U (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105568862A (zh) * | 2016-01-20 | 2016-05-11 | 湖南省第五工程有限公司 | 一种架梁装置及架梁方法 |
CN106245530A (zh) * | 2016-08-24 | 2016-12-21 | 广西长长路桥建设有限公司 | 一种万能杆件缆索吊装系统拆除工法 |
-
2013
- 2013-04-28 CN CN 201320226617 patent/CN203188131U/zh not_active Expired - Lifetime
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105568862A (zh) * | 2016-01-20 | 2016-05-11 | 湖南省第五工程有限公司 | 一种架梁装置及架梁方法 |
CN106245530A (zh) * | 2016-08-24 | 2016-12-21 | 广西长长路桥建设有限公司 | 一种万能杆件缆索吊装系统拆除工法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8622744B2 (en) | Mobile Training trailer for electric transmission lines | |
CN203377546U (zh) | 跨越高速铁路施工装置 | |
CN107792790A (zh) | 用于山地施工材料运输的架空索道的安装使用方法 | |
CN105529648A (zh) | 液压装配式跨越架 | |
CN207792533U (zh) | 应用于山地施工的索道 | |
CN104695752B (zh) | 快速抢修塔系统及其架设方法 | |
CN201635020U (zh) | 用于大中型混凝土桥梁的拆除桥面吊机 | |
CN204316007U (zh) | 一种输电线路跨越施工装置 | |
CN106368493B (zh) | 一种双臂液压推进型硬封顶格构式跨越架 | |
CN102587284B (zh) | 独立扒杆梁板安装施工工法 | |
CN105905815B (zh) | 座地自平衡抱杆的工作方法 | |
CN203188131U (zh) | 架设梁板施工独立扒杆设备 | |
CN105003738B (zh) | 山区复杂地形运用索道安装大管径管道施工工法 | |
CN110172919A (zh) | 一种矮塔斜拉桥穿索方法及系统 | |
CN105829203B (zh) | 桩翻转系统、船舶和用于翻转桩的方法 | |
CN204342257U (zh) | 一种大型构件翻转装置 | |
CN102061681B (zh) | 固定双吊点悬臂轨道式桁吊安装方法 | |
CN202545121U (zh) | 自带吊车的风力发电机组 | |
CN101966823A (zh) | 一种承力索跨越架及其架设方法 | |
CN202390116U (zh) | 一种高强度小吨位起吊机 | |
CN110820555A (zh) | 一种桥梁检修车及检修平台避让桥墩的方法 | |
CN216235734U (zh) | 幕墙单元板块垂直运输吊装结构 | |
CN106025923B (zh) | 一种张力式电力线路保护网的施工方法 | |
CN105887701B (zh) | 悬索桥上部结构拆除与更换安装方法 | |
CN211689934U (zh) | T梁吊篮系统 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CX01 | Expiry of patent term |
Granted publication date: 20130911 |
|
CX01 | Expiry of patent term |