CN203174746U - Wavy tailing dam slope drainage ditches for coping with rainstorm - Google Patents

Wavy tailing dam slope drainage ditches for coping with rainstorm Download PDF

Info

Publication number
CN203174746U
CN203174746U CN 201320146030 CN201320146030U CN203174746U CN 203174746 U CN203174746 U CN 203174746U CN 201320146030 CN201320146030 CN 201320146030 CN 201320146030 U CN201320146030 U CN 201320146030U CN 203174746 U CN203174746 U CN 203174746U
Authority
CN
China
Prior art keywords
dam
slope
drainage ditches
face
rainstorm
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201320146030
Other languages
Chinese (zh)
Inventor
张磊
杨兰兰
赖豪杰
贾凡
谭箐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hohai University HHU
Original Assignee
Hohai University HHU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hohai University HHU filed Critical Hohai University HHU
Priority to CN 201320146030 priority Critical patent/CN203174746U/en
Application granted granted Critical
Publication of CN203174746U publication Critical patent/CN203174746U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The utility model discloses wavy tailing dam slope drainage ditches for coping with a rainstorm. The wavy tailing dam slope drainage ditches for coping with the rainstorm are characterized in that dam face troughs (3) and dam face crests (4) are formed in an original dam face (2) of a dam body (1) at certain width intervals in a digging and filling mode, bituminous concrete is poured on the surfaces of the dam face troughs (3) to form the dam slope drainage ditches, and vegetation is paved on the surfaces of the dam face crests (4) to form protective slopes (6). Due to the fact that the gradient of the slope face drainage ditches is large and waterproof materials such as the bituminous concrete is poured, a large amount of rainwater can be carried away, a seepage line is prevented from increasing sharply, and stability of the dam body is guaranteed.

Description

A kind of waveform tailing dam dam slope gutter of tackling heavy rain
Technical field
The utility model relates to a kind of tailing dam dam slope dewatering installation, specifically relate to a kind of adopt pitch mix the earth small pieces of cloth used for patches in order to tackle the tailing dam dam slope gutter of heavy rain.
Background technology
The mine tailing storehouse mainly is made up of tailing dam, the facility that drains off floodwaters, dam facing drainage and other supporting facility, wherein the dam facing drainage be only second to tailing dam, the system of drainning off floodwaters influence one of key factor of dam stability.The purpose of dam facing drainage setting is to wash away dam abutment or rainwater and be trapped in dam facing and cause dam facing to draw ditch in order to prevent that the hillside heavy rain from confluxing, and for reaching this purpose, the dam slope gutter is set normally.
There are two classes in the dam slope gutter at present: a class is along hillside and dam slope joint portion the cemented rock catchwater to be set, and washes away dam abutment to prevent that the hillside heavy rain from confluxing; Another kind of is in the domatic setting in dam body downstream gutter in length and breadth, and the rainwater water conservancy diversion of dam facing is discharged outside the dam, causes dam facing to draw ditch in order to avoid rainwater is trapped in dam facing, influences the safety of dam body.
Traditional dam slope gutter generally is to pile up placed rockfill and cemented rock at the bottom of concrete, be subjected to the construction technology condition restriction, after building by laying bricks or stones, also will wipe one's face with the M5 cement paste at the ditch inner surface usually, to prevent that current are along the furrow bank seepage in the ditch, working procedure complexity in a word, consume material; In addition, the dam body of tailing dam is constantly to raise, its side slope belongs to unstable geology district, and branch traverse furrow, longitudinal furrow and crisscross ditch are just moved towards according to the plane of arranging in existing dam facing gutter, less change at the domatic soil body stress gutter is set, to such an extent as to the crack appears in gutter easily.
Summary of the invention
The purpose of this utility model is to have overcome deficiency of the prior art, and a kind of dam slope gutter simple and easy and that can effectively prevent heavy rain erosion damage dam stability of constructing is provided.
In order to solve the problems of the technologies described above, the utility model is to be achieved through the following technical solutions:
A kind of waveform tailing dam dam slope gutter of tackling heavy rain, it is characterized in that: on the former dam facing of dam body, form dam facing trough and dam facing crest every certain width shoveling embankment, build bituminous concrete on dam facing trough surface and form the dam slope gutter, lay slope vegetation protection on dam facing crest surface.
Compared with prior art, the beneficial effects of the utility model are:
Be the waveform dam facing with original plane dam facing in-situ reformation, it is simple and easy to construct, and has saved earth and stone material.Dam slope gutter trend has been strengthened drainage effect along domatic gradient than general orientation, has guaranteed the stability of dam body.And bituminous concrete is built in the gutter, namely waterproofly can adapt to the unlikely destruction of changeable stress again.The slope vegetation protection stability of not only having strengthened side slope has played the effect of environmental protection again in addition.
Description of drawings
Fig. 1 is structural representation of the present utility model.
The specific embodiment
Below in conjunction with accompanying drawing the utility model is described in further detail:
As shown in Figure 1, the utility model just along domatic gradient than general orientation excavation forms dam facing trough 3 every certain width dam body 1 on former dam facing 2, shoveling is filled in dam facing trough 3 both sides form dam facing crest 4.Build bituminous concrete on dam facing trough 3 surfaces and form the dam slope gutter, lay slope vegetation protection 6 on dam facing crest 4 surfaces.This had both reduced bank protection face permeability and had prevented heavy rain destruction, had effectively stoped the soil erosion of bank protection face again.
Place, the dam slope gutter gradient is bigger, and bituminous concrete is built in the gutter, i.e. the waterproof unlikely destruction of variation that can adapt to stress again, so a large amount of rainwater can be taken away in the dam facing gutter, reduce the degree of raising of tailing dam saturation line under the heavy rain situation effectively, guaranteed the stability of dam body.
The undeclared part that relates in the utility model is same as the prior art or adopt prior art to be realized.

Claims (1)

1. waveform tailing dam dam slope gutter of tackling heavy rain, it is characterized in that: go up every certain width shoveling embankment at the former dam facing (2) of dam body (1) and form dam facing trough (3) and dam facing crest (4), build bituminous concrete on dam facing trough (3) surface and form the dam slope gutter, lay slope vegetation protection (6) on dam facing crest (4) surface.
CN 201320146030 2013-03-28 2013-03-28 Wavy tailing dam slope drainage ditches for coping with rainstorm Expired - Fee Related CN203174746U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201320146030 CN203174746U (en) 2013-03-28 2013-03-28 Wavy tailing dam slope drainage ditches for coping with rainstorm

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201320146030 CN203174746U (en) 2013-03-28 2013-03-28 Wavy tailing dam slope drainage ditches for coping with rainstorm

Publications (1)

Publication Number Publication Date
CN203174746U true CN203174746U (en) 2013-09-04

Family

ID=49071470

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201320146030 Expired - Fee Related CN203174746U (en) 2013-03-28 2013-03-28 Wavy tailing dam slope drainage ditches for coping with rainstorm

Country Status (1)

Country Link
CN (1) CN203174746U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104264694A (en) * 2014-09-29 2015-01-07 南京赛伯通建筑工程有限公司 Expansive soil slope and construction method
CN105155555A (en) * 2015-06-20 2015-12-16 广东安元矿业勘察设计有限公司 Method for preventing water and soil loss in refuse dump
CN106592730A (en) * 2016-11-07 2017-04-26 陈祖全 Rainwater recycling system

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104264694A (en) * 2014-09-29 2015-01-07 南京赛伯通建筑工程有限公司 Expansive soil slope and construction method
CN104264694B (en) * 2014-09-29 2016-08-17 南京赛伯通建筑工程有限公司 A kind of expansive soil slope and construction method
CN105155555A (en) * 2015-06-20 2015-12-16 广东安元矿业勘察设计有限公司 Method for preventing water and soil loss in refuse dump
CN106592730A (en) * 2016-11-07 2017-04-26 陈祖全 Rainwater recycling system
CN106592730B (en) * 2016-11-07 2019-06-18 江苏帝井环保科技有限公司 System for reclaiming rainwater

Similar Documents

Publication Publication Date Title
CN203403426U (en) Supporting structure of expensive earth road cutting side slope
CN103953008B (en) A kind of modified mixed dam being applicable to Tailings Dam
CN102644288B (en) A kind of construction method saving the anhydrous Tailings Dam of clean and safe
CN201835198U (en) Drainage roadbed for high underground water level
CN208309312U (en) Reinforced earth retaining wall embankment drainage system
CN103334450B (en) Construction method of pile precast slab retaining wall with drainage ditch
CN102535408B (en) Semi-assembly type ecological debris flow check dam, and construction method thereof
CN104074166B (en) A kind of method recovering withered river
CN108193648A (en) Plasticity panel homogeneous dam
CN207469269U (en) A kind of hydraulic engineering High strength geogrid structure class ecological revetment
CN102425175B (en) Reinforcement protective structure of large spoil disposal area in mountainous area
CN105155555A (en) Method for preventing water and soil loss in refuse dump
CN203174746U (en) Wavy tailing dam slope drainage ditches for coping with rainstorm
CN102518052A (en) Hidden flexible drainage structure of highway side slope
CN206016853U (en) Base plate anchors restricted type tunnel lining structure
CN205035768U (en) Enrockment concrete permeable dike
CN203716064U (en) Roadbed sewer convenient for dredging
CN205116094U (en) Slope protection ecological brick for reducing water and soil loss of side slope
CN107761668B (en) Coastal shore reservoir land-building type revetment structure and construction method thereof
CN106703053A (en) Construction method for reinforced soil drainage composite revetment structure
CN103046536B (en) A kind of refuse dump integral harness measure being suitable for soft foundation
CN209456974U (en) A kind of articulated hinge concrete block system
CN205224055U (en) Side slope
CN208266797U (en) Ecological embankment for stabilizing river bank slope
CN104818734B (en) Control completely decomposed granite side slope damage by water waterproof and water drainage system and construction method thereof

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130904

Termination date: 20140328