CN203160116U - Overturning prevention bridge pier mechanism - Google Patents
Overturning prevention bridge pier mechanism Download PDFInfo
- Publication number
- CN203160116U CN203160116U CN201320198198.XU CN201320198198U CN203160116U CN 203160116 U CN203160116 U CN 203160116U CN 201320198198 U CN201320198198 U CN 201320198198U CN 203160116 U CN203160116 U CN 203160116U
- Authority
- CN
- China
- Prior art keywords
- circular cylinder
- support
- cylinder body
- bridge pier
- overturning
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
- Y02A30/30—Adapting or protecting infrastructure or their operation in transportation, e.g. on roads, waterways or railways
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域technical field
本实用新型涉及一种抗倾覆桥墩机构。The utility model relates to an anti-overturning pier mechanism.
背景技术Background technique
近年来,独柱墩连续梁桥作为城市立交桥、高架桥普遍修建的桥型,由于其造型简洁流畅、建筑高度小、桥下通视性好、适应场合多、施工方便及工程造价较低等优点而得到了极大的发展。但由于独柱墩桥梁在横桥向采用单支撑座支承,在车道偏载作用下,可能发生整体横向失稳,近年来已发生多起倾覆事故,造成了重大的经济损失和恶劣的社会影响。事故调查结论多为车辆超载、超限所致。桥梁结构的倾覆倒塌是在极端事件作用下发生的,与结构本身的初始损伤规模不成比例。独柱墩单点支承的连续梁桥,抗倾覆力矩不足以抵抗桥梁极端事件作用下产生的倾覆力矩,从而导致支撑座脱空,甚至发生倾覆事故。这种小概率但后果严重的事故已受到了工程设计的广泛关注。既有独柱墩连续梁桥,若采用单点支承,抗倾覆安全系数小,在极端事件作用下,支撑座非常容易脱空,进而导致上部梁体发生倾覆。In recent years, continuous girder bridges with single-column piers have been widely used as urban overpasses and viaducts, because of their simple and smooth shape, small building height, good visibility under the bridge, adaptable to many occasions, convenient construction and low engineering cost, etc. And has been greatly developed. However, since the single column pier bridge is supported by a single support seat in the transverse bridge direction, the overall lateral instability may occur under the eccentric load of the lane. In recent years, many overturning accidents have occurred, causing major economic losses and adverse social impacts . Accident investigation conclusions are mostly caused by overloading and overrunning of vehicles. The overturning and collapse of bridge structures occurs under the action of extreme events, which is not proportional to the initial damage scale of the structure itself. For continuous girder bridges with single-point support on single-column piers, the anti-overturning moment is not enough to resist the overturning moment under the extreme events of the bridge, which will cause the support seat to fall out of the air, and even overturn accidents. This kind of accident with small probability but serious consequences has been widely concerned by engineering design. For the existing continuous girder bridge with single-column piers, if single-point support is used, the safety factor against overturning is small. Under the action of extreme events, the support seat is very easy to fall out, which will cause the upper girder body to overturn.
实用新型内容Utility model content
本实用新型为了解决现有技术中独柱墩桥梁采用单点支承容易导致支撑座脱空,甚至发生倾覆事故的问题,进而提供一种抗倾覆桥墩机构。The utility model provides an anti-overturning pier mechanism in order to solve the problem in the prior art that the single-point support of the single-column pier bridge is likely to cause the support seat to be empty, or even an overturning accident.
本实用新型为解决上述问题而采用的技术方案是:所述桥墩机构包括墩柱、所述桥墩机构还包括碳纤维布、钢抱箍组件、六个支撑柱和多个连接件,钢抱箍组件包括两个水平支撑板、两个半圆形筒体、四个连接板、多个半圆形肋板、多个支撑肋板和多个长方形肋板;每个支撑柱的上端面和下端面分别固定有一个固定板,且两个固定板通过多个连接件固定,每两个半圆形肋板组成一个圆形肋板,两个半圆形筒体通过四个连接板组成圆形筒体,每个水平支撑板的上表面分别各设有三个呈三角形设置的支撑柱,且每个支撑柱轴向的中心线与所述圆形筒体轴向中心线重合,两个水平支撑板呈一字型水平设置在所述圆形筒体的上表面上,多个所述圆形肋板均匀套装设置在所述圆形筒体的外侧壁上,多个长方形肋板均布设置在所述圆形筒体的外侧壁上,且每个长方形肋板沿长度方向的中心线与所述圆形筒体的轴向中心线重合,多个支撑肋板均布设置在所述圆形筒体的外侧壁上,每个支撑肋板的上端与相对应的水平支撑板的下表面连接,碳纤维布缠绕在墩柱的顶端,所述圆形筒体套装在墩柱外侧的碳纤维布上。The technical scheme adopted by the utility model to solve the above problems is: the bridge pier mechanism includes pier columns, the bridge pier mechanism also includes carbon fiber cloth, steel hoop components, six support columns and multiple connectors, steel hoop components Including two horizontal support plates, two semi-circular cylinders, four connecting plates, multiple semi-circular ribs, multiple support ribs and multiple rectangular ribs; the upper and lower end faces of each support column One fixed plate is fixed respectively, and the two fixed plates are fixed by multiple connecting pieces, every two semicircular ribs form a circular rib, and the two semicircular cylinders form a circular cylinder through four connecting plates The upper surface of each horizontal support plate is respectively provided with three triangular support columns, and the axial center line of each support column coincides with the axial center line of the circular cylinder, and the two horizontal support plates It is horizontally arranged in a line on the upper surface of the circular cylinder, and a plurality of circular ribs are evenly set on the outer wall of the circular cylinder, and a plurality of rectangular ribs are evenly arranged on the outer wall of the circular cylinder. On the outer wall of the circular cylinder, and the centerline of each rectangular rib along the length direction coincides with the axial centerline of the circular cylinder, a plurality of supporting ribs are evenly arranged on the circular On the outer wall of the cylinder, the upper end of each support rib is connected to the lower surface of the corresponding horizontal support plate, the carbon fiber cloth is wound on the top of the pier, and the circular cylinder is set on the carbon fiber cloth outside the pier .
本实用新型的有益效果是:在水平支撑板上安放支撑柱,改善桥梁后期运营过程中支座的受力状态,同时增强梁体的抗倾覆能力,防止主梁发生倾覆,本实用新型的钢抱箍组件不需要现场制作,可在工厂生产,加工质量高,可满足墩柱钻孔植栓和钢抱箍制作同时施工的要求,缩短施工时间,钢抱箍可以根据具体情况制作,结构简单,便于加工制作和安装使用。The beneficial effects of the utility model are: the support column is placed on the horizontal support plate to improve the stress state of the support in the later operation of the bridge, and at the same time enhance the anti-overturning ability of the beam body to prevent the main beam from overturning. The hoop assembly does not need to be fabricated on site, but can be produced in the factory with high processing quality, which can meet the simultaneous construction requirements of pier column drilling and bolting and steel hoop production, and shorten the construction time. The steel hoop can be made according to specific conditions, and the structure is simple and convenient Processing and installation and use.
附图说明Description of drawings
图1是本实用新型安装在主梁底部整体结构主视图,图2是本实用新型的俯视图。Fig. 1 is a front view of the overall structure of the utility model installed at the bottom of the girder, and Fig. 2 is a top view of the utility model.
具体实施方式Detailed ways
具体实施方式一:结合图1-图2说明本实施方式一种抗倾覆桥墩机构,所述桥墩机构包括墩柱1、所述桥墩机构还包括碳纤维布2、钢抱箍组件4、六个支撑柱3和多个连接件6,钢抱箍组件4包括两个水平支撑板4-2、两个半圆形筒体4-4、四个连接板4-5、多个半圆形肋板4-1、多个支撑肋板4-3和多个长方形肋板4-6;每个支撑柱3的上端面和下端面分别固定有一个固定板,且两个固定板通过多个连接件6固定,每两个半圆形肋板4-1组成一个圆形肋板,两个半圆形筒体4-4通过四个连接板4-5组成圆形筒体,每个水平支撑板4-2的上表面分别各设有三个呈三角形设置的支撑柱3,且每个支撑柱3轴向的中心线与所述圆形筒体轴向中心线重合,两个水平支撑板4-2呈一字型水平设置在所述圆形筒体的上表面上,多个所述圆形肋板均匀套装设置在所述圆形筒体的外侧壁上,多个长方形肋板4-6均布设置在所述圆形筒体的外侧壁上,且每个长方形肋板4-6沿长度方向的中心线与所述圆形筒体的轴向中心线重合,多个支撑肋板4-3均布设置在所述圆形筒体的外侧壁上,每个支撑肋板4-3的上端与相对应的水平支撑板4-2的下表面连接,碳纤维布2缠绕在墩柱1的顶端,所述圆形筒体套装在墩柱1外侧的碳纤维布2上。Specific Embodiment 1: An anti-overturning bridge pier mechanism in this embodiment is described in conjunction with Fig. 1-Fig.
具体实施方式二:结合图1-图2说明本实施方式一种抗倾覆桥墩机构,所述桥墩机构还包括多个高强螺栓5,所述两个相对扣合的半圆形筒体4-4上的连接板4-5通过多个高强螺栓5均匀固定,所述圆形筒体通过多个高强螺栓5固定在墩柱1上,其它与具体实施方式一相同。Specific Embodiment 2: An anti-overturning bridge pier mechanism in this embodiment is described in conjunction with Fig. 1-Fig. The connecting plates 4-5 on the top are evenly fixed by a plurality of high-
具体实施方式三:结合图1-图2说明本实施方式一种抗倾覆桥墩机构,所述位于每个水平支撑板4-2上的三个支撑柱3呈等边三角形设置,其它与具体实施方式一相同。Specific Embodiment Three: An anti-overturning bridge pier mechanism in this embodiment is described in conjunction with Fig. 1-Fig.
具体实施方式四:结合图1-图2说明本实施方式一种抗倾覆桥墩机构,所述连接件6为双向固定螺栓,其它与具体实施方式一相同。Embodiment 4: An anti-overturning bridge pier mechanism in this embodiment will be described with reference to FIGS. 1-2 . The
工作原理working principle
将本实用新型设置在主梁底部中间位置,先在墩柱1顶部钻孔,注意要避开墩柱1钢筋的位置,然后在钻孔处粉刷界面剂(胶),安装钢抱箍组件4,通过高强螺栓5将墩柱1、碳纤维布2和钢抱箍组件4连接形成整体,将多个千斤顶均匀设置在墩柱1的顶端,同时调整多个千斤顶将主梁顶升一定高度,将本发明的两个支撑柱3分别设置在水平支撑板4-2上,之后将千斤顶撤掉,将现有技术中的支撑座设置在墩柱1的顶端。Set the utility model at the middle position of the bottom of the main beam, first drill a hole at the top of the
Claims (4)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201320198198.XU CN203160116U (en) | 2013-04-18 | 2013-04-18 | Overturning prevention bridge pier mechanism |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201320198198.XU CN203160116U (en) | 2013-04-18 | 2013-04-18 | Overturning prevention bridge pier mechanism |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN203160116U true CN203160116U (en) | 2013-08-28 |
Family
ID=49021312
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201320198198.XU Expired - Fee Related CN203160116U (en) | 2013-04-18 | 2013-04-18 | Overturning prevention bridge pier mechanism |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN203160116U (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103850183A (en) * | 2014-03-12 | 2014-06-11 | 中交二航局第四工程有限公司 | Support structure for realizing no-cushion cap approach viaduct concrete box girder less-support cast-in-place |
| CN105970799A (en) * | 2016-05-18 | 2016-09-28 | 清华大学 | Structure for preventing bridge from overturning transversely and construction method of structure |
| CN106087707A (en) * | 2016-07-27 | 2016-11-09 | 清华大学 | A kind of accessory configurations preventing existing bridge lateral from toppling and construction method thereof |
| CN108532474A (en) * | 2018-03-29 | 2018-09-14 | 中冶华天工程技术有限公司 | A kind of the overturn-preventing bracing means and installation method of Single column pier bridge |
-
2013
- 2013-04-18 CN CN201320198198.XU patent/CN203160116U/en not_active Expired - Fee Related
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103850183A (en) * | 2014-03-12 | 2014-06-11 | 中交二航局第四工程有限公司 | Support structure for realizing no-cushion cap approach viaduct concrete box girder less-support cast-in-place |
| CN105970799A (en) * | 2016-05-18 | 2016-09-28 | 清华大学 | Structure for preventing bridge from overturning transversely and construction method of structure |
| CN105970799B (en) * | 2016-05-18 | 2018-04-10 | 清华大学 | A kind of construction for preventing bridge lateral from toppling and its construction method |
| CN106087707A (en) * | 2016-07-27 | 2016-11-09 | 清华大学 | A kind of accessory configurations preventing existing bridge lateral from toppling and construction method thereof |
| CN108532474A (en) * | 2018-03-29 | 2018-09-14 | 中冶华天工程技术有限公司 | A kind of the overturn-preventing bracing means and installation method of Single column pier bridge |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106939707B (en) | A kind of restricted clearance large-scale steel structure supporting platform from method for improving | |
| CN102661054B (en) | Lateral reinforcing structure in whole lifting of plane steel truss and whole lifting method | |
| CN205443958U (en) | Composite truss support of big cantilever bent cap | |
| CN203188589U (en) | Rigid-frame continuous beam zero block construction bracket supporting system | |
| CN103205927A (en) | Anti-overturning bridge pier supporting mechanism | |
| CN105839516B (en) | A kind of bridge lateral anti-fall girder apparatus and its construction method | |
| CN101503908B (en) | Construction method for spacing suspension cable structural template support platform | |
| CN204510005U (en) | A kind of Coping Construction operating platform | |
| CN203383221U (en) | Foundation pit support structure formed by armoured concrete and steel structure | |
| CN101858139A (en) | Concrete casting platform | |
| CN203270461U (en) | Bailey beam support without buttress in soft foundation | |
| CN206385463U (en) | A kind of anchor ear construction auxiliary hanging basket instrument | |
| CN111691300A (en) | A concrete placement support device for steel-concrete composite beam | |
| CN101633483B (en) | Integral lifting apparatus for steel structure net rack | |
| CN204475182U (en) | Installation frock of railway pier mound top hanging flower basket | |
| CN204662929U (en) | A kind of cross-line walking fence operation device | |
| CN202131600U (en) | Dual cross fixing end | |
| CN204492133U (en) | A kind of easy insulated column construction tool frame | |
| CN212247894U (en) | A concrete placement support device for steel-concrete composite beam | |
| CN206828969U (en) | A kind of high pier stud bearing platform counter-force prepressing device | |
| CN102322134A (en) | Method for determining difference in bearing capacities of fastener-type full space support frame and full space scaffold | |
| CN205329549U (en) | Corbel frame device is deposited to steel case roof beam temporarily | |
| CN206467579U (en) | A kind of support meanss of bridge coping | |
| CN206267033U (en) | A kind of Hanging Basket prepressing device | |
| CN212866793U (en) | A prefabricated construction elevator parking platform |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20130828 Termination date: 20170418 |