CN203145959U - Movable trolley of tunnel arch bottom concrete lining bottom die - Google Patents

Movable trolley of tunnel arch bottom concrete lining bottom die Download PDF

Info

Publication number
CN203145959U
CN203145959U CN 201320110972 CN201320110972U CN203145959U CN 203145959 U CN203145959 U CN 203145959U CN 201320110972 CN201320110972 CN 201320110972 CN 201320110972 U CN201320110972 U CN 201320110972U CN 203145959 U CN203145959 U CN 203145959U
Authority
CN
China
Prior art keywords
bed die
concrete
carcel
lining cutting
cutting bed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201320110972
Other languages
Chinese (zh)
Inventor
汤晓辉
张松江
孙卫革
王文虎
路俊民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Construction Group Ltd
Original Assignee
Sinohydro Bureau 2 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 2 Co Ltd filed Critical Sinohydro Bureau 2 Co Ltd
Priority to CN 201320110972 priority Critical patent/CN203145959U/en
Application granted granted Critical
Publication of CN203145959U publication Critical patent/CN203145959U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses a movable trolley of a tunnel arch bottom concrete lining bottom die. The movable trolley comprises a portal frame beam (16), a concrete side support (15), a reinforced rib binding side support (19), walking devices (13), a cable clamping device (14) and a hoisting device (26), wherein the concrete side support (15) and the reinforced rib binding side support (19) are arranged at two ends of the portal frame beam (16) respectively, the walking devices (13) are located on the bottom of the concrete side support (15) and the bottom of the reinforced rib binding side support (19), the cable clamping device (14) is arranged on the concrete side support (15) and the reinforced rib binding side support (19), and the hoisting device (26) is arranged on the portal frame beam (16). The movable trolley can achieve quick and smooth construction of the lining bottom die and improves safety and quality during construction of a tunnel.

Description

Tunnel invert concrete lining bed die is mobile trolley used
Technical field
The utility model belongs to the constructing tunnel apparatus field, and it is mobile trolley used to relate in particular to a kind of tunnel invert concrete lining bed die.
Background technology
The diversion tunnel in power station is circular configuration, and diameter is general more than 5 meters, tens meters even bigger in the footpath, hole that has.Adopt New Austrian Tunneling Method to carry out the excavation construction of underground chamber mostly, for the stability of assurance diversion tunnel and the fluency of water flowing, need carry out reinforced concrete lining layer to the tunnel after ending.
The full section of lining concrete is generally built at twice and is finished, and encircles the part of 120 °~150 ° at central angle at the bottom of the lining cutting for the first time, and the second time is remaining side of lining cutting, crown part again.The curvature of lining cutting bed die conforms to the design section size.Arc length is general more than 6 meters, and lining cutting length is more than 6 meters, and the lining cutting bed die is conventional makes whole one section.More than the heavily about 5000kg of lining cutting bed die that forms.
The power station diversion tunnel is generally longer, is subjected to the restriction in space in the hole, and building of steel concrete carried out in the work plane segmentation one by one.A work plane concreting is pulled down the lining cutting bed die after solidifying and reaching certain intensity, moves on to next work plane.The move mode of lining cutting bed die is: at the top in hole several anchor poles being set, is the movement that Chain block is realized template at anchor pole; Or a small amount of anchor pole is set, and wire rope is set between anchor pole, dispose pulley at wire rope, be Chain block under the pulley, realize the movement of lining cutting bed die by mobile pulley.The cavitation speed of this form of construction work is relatively low, and if when running into the bad rock stratum of geological conditions, usually can increase difficulty of construction because anchor pole arranges problem, be unfavorable for safety and quality during the tunnel construction.
The utility model content
In order to improve above-mentioned defective of the prior art, the utility model provides a kind of the mobile trolley used of tunnel invert concrete lining bed die that can be used for, and can realize quick, smooth construction to the lining cutting bed die.
The technical solution adopted in the utility model is:
Provide a kind of tunnel invert concrete lining bed die mobile trolley used, comprise: gantry beam (16), concrete side stand (15), reinforcing bar binding side stand (19), running gear (13), Carcel device (14), hanging apparatus (26), it is characterized in that: concrete side stand (15) and reinforcing bar binding side stand (19) are separately positioned on gantry beam (16) two ends, are used for supporting gantry beam (16); Bottom, the concrete skidding that running gear (13) is positioned at concrete side stand (15) and reinforcing bar binding side stand (19) walked the top that track (12) and reinforcing bar binding skidding are walked track (10), is made up of running wheel (23), running wheel axle (24), walking wheel carrier (25); Concrete side stand (15) and reinforcing bar binding side stand (19) are provided with Carcel device (14), described Carcel device (14) is made up of Carcel spanner (20), Carcel nut (21), Carcel bolt (22), is used for stoping the mobile trolley used mobile inertia that produces of lining cutting bed die to the collision of support; Hanging apparatus (26) is arranged on the gantry beam (16), is made up of lifting rope (17) and Chain block (18), and pulling Chain block (18) is realized the lifting of lining cutting bed die (1).
Further, described lining cutting bed die (1) comprises crossbeam (2) and welding hanger (3).
Further, described Chain block (18) is provided with four groups at least.
The mobile trolley used operating principle of described tunnel invert concrete lining bed die is:
The movement of lining cutting bed die in tunnel is along moving axially in the hole, the lining cutting bed die is mobile trolley used to possess the function that lifting lining cutting bed die is arranged and move along axis direction in the hole, select for use the means of transportation of portal frame to transport, at portal frame Chain block is set, the lining cutting bed die is sling, running gear also is set on the portal frame, and running gear realizes that portal frame moves and drives moving axially of lining cutting bed die at axial direction.After the concrete cast finished, concrete to be cast had reached intensity.Torn the lining cutting bed die open, the lining cutting bed die is sling with at least 4 group Chain blocks on the queues of stationary traffic door frame of lining cutting bed die travelling carriage, use the Carcel device with the lining cutting bed die be locked in the lining cutting bed die mobile trolley used on.With the support jack-up of jack with the mobile trolley used concrete side of lining cutting bed die, the concrete side bottom is laid the walking track, falls jack, and the running gear of support drops on the track; The reinforcing bar binding side is laid the walking track.The hole arranges hoist engine and drags chassis, and mobile lining cutting bed die is mobile trolley used, to next work plane, realizes that whole lining cutting bed die moves to next work plane.Extract the walking of the channel-section steel on reinforcing bar track under the bed die out, unclamp the Carcel device, the pulling Chain block realizes that the lining cutting bed die is radially in place.
Description of drawings
Below in conjunction with drawings and Examples the utility model is further specified.
Fig. 1 is lining cutting bed die schematic diagram of the present utility model;
Fig. 2 is reinforcing bar binding schematic diagram of the present utility model;
Fig. 3 is the mobile trolley used lateral view of lining cutting bed die of the present utility model;
Fig. 4 is the mobile trolley used front view of lining cutting bed die of the present utility model;
Fig. 5 is buckling and locking device schematic diagram of the present utility model;
Fig. 6 is running gear schematic diagram of the present utility model.
1; the lining cutting bed die, 2; crossbeam, 3; hanger; 4; top reinforcement, 5; lower floor's reinforcing bar, 6; steel concrete; 7; the concrete cover cushion block, 8; lacing wire, 9; track colligation skidding is walked rail support; 10; the reinforcing bar binding skidding is walked track, and 11; track connects support, 12; the concrete skidding is walked track; 13; running gear, 14; the Carcel device, 15; the concrete side stand; 16; gantry beam, 17; lifting rope, 18; Chain block; 19; the reinforcing bar binding side stand; 20; the Carcel spanner, 21; the Carcel nut, 22; the Carcel bolt; 23; running wheel; 24; the running wheel axle, 25; the walking wheel carrier, 26; hanging apparatus.
The specific embodiment
With reference to the accompanying drawings, in conjunction with an embodiment, mobile trolley used being elaborated of lining cutting bed die that the utility model is provided.
(1) the tunnel concrete liner bed die is mobile trolley used respectively by gantry beam 16, support 15,19, and running gear 13, Carcel device 14, hanging apparatus is formed.
Gantry beam 16 two ends arrange concrete side stand 15 and reinforcing bar binding side stand 19 respectively; Carcel device 14 is set on the support 15,19, and Carcel device 14 is made up of Carcel spanner 20, Carcel nut 21, Carcel bolt 22, and the function of Carcel device 14 is used for stoping the mobile trolley used mobile inertia that produces of lining cutting bed die to the collision of support; Running gear 13 is made up of running wheel 23, running wheel axle 24, walking wheel carrier 25 and is placed support 15 and 19 bottoms, reinforcing bar binding skidding to walk track 10 respectively and the concrete skidding is walked track 12 tops; Hanging apparatus 26 on the gantry beam 16 is made up of lifting rope 17 and Chain block 18, and the pulling Chain block is realized the lifting of lining cutting bed die 1.
(2) in order to finish moving axially of lining cutting bed die, crossbeam 2 is set on the lining cutting bed die 1, at crossbeam 2 welding hangers 3.
(3) initial concrete formation:
1) after the tunnel cavern excavation is finished; difference colligation concrete top reinforcement 4, concrete lower floor reinforcing bar 5, lacing wire 8 and concrete cover cushion block 7; colligation walking rail support 9 is laid the reinforcing bar binding skidding at walking rail support 9 and is walked track 10 and connect supporting 11 with track to connect.
2) Chain block 18 on the mobile trolley used gantry beam 16 of lining cutting bed die 1 usefulness lining cutting bed die is sling, and uses Carcel device 14 that lining cutting bed die 1 is locked on the mobile trolley used support 15 of lining cutting bed die, 19.With support 15 jack-up of jack with the mobile trolley used concrete side of lining cutting bed die, frame bottom is with interim support fixation and lay the walking track, falls jack, and the running gear 13 of support drops on the track; The running gear 13 of the support 19 of reinforcing bar binding side directly drops on the reinforcing bar binding skidding and walks on the track 10.It is mobile trolley used to move the lining cutting bed die with manpower, to initial concrete work face.Extract the walking of the channel-section steel on reinforcing bar track 10 under the lining cutting bed die out, unclamp Carcel device 14, pulling Chain block 18 realizes that lining cutting bed die footpath 1 is in place.
3) concreting and form steel concrete 6.
(4) after concrete 6 cast finished, concrete 6 to be cast had reached intensity.Torn lining cutting bed die 1 open, the Chain block 18 on the mobile trolley used gantry beam 16 of lining cutting bed die 1 usefulness lining cutting bed die is sling, and uses Carcel device 14 that lining cutting bed die 1 is locked on the mobile trolley used support 15 of lining cutting bed die, 19.With support 15 jack-up of jack with the mobile trolley used concrete side of lining cutting bed die, the concrete side bottom is laid walking track 12, falls jack, and the running gear 13 of support drops on the track 12; The reinforcing bar binding side is laid walking track 10.It is mobile trolley used to move the lining cutting bed die with manpower, to next work plane, realizes that whole lining cutting bed die moves to next work plane.Reinforcing bar binding skidding under the extraction lining cutting bed die on the reinforcing bar is walked track 10, unclamps Carcel device 14, and pulling Chain block 18 realizes that lining cutting bed die 1 is radially in place.
It should be noted that at last, above embodiment is only unrestricted in order to technical scheme of the present invention to be described, although with reference to preferred embodiment the present invention is had been described in detail, those of ordinary skill in the art is to be understood that, can make amendment or be equal to replacement technical scheme of the present invention, and not breaking away from the spirit and scope of technical solution of the present invention, it all should be encompassed in the middle of the claim scope of the present invention.

Claims (3)

1. a tunnel invert concrete lining bed die is mobile trolley used, comprise: gantry beam (16), concrete side stand (15), reinforcing bar binding side stand (19), running gear (13), Carcel device (14), hanging apparatus (26), it is characterized in that: concrete side stand (15) and reinforcing bar binding side stand (19) are separately positioned on gantry beam (16) two ends, are used for supporting gantry beam (16); Bottom, the concrete skidding that running gear (13) is positioned at concrete side stand (15) and reinforcing bar binding side stand (19) walked the top that track (12) and reinforcing bar binding skidding are walked track (10), is made up of running wheel (23), running wheel axle (24), walking wheel carrier (25); Concrete side stand (15) and reinforcing bar binding side stand (19) are provided with Carcel device (14), described Carcel device (14) is made up of Carcel spanner (20), Carcel nut (21), Carcel bolt (22), is used for stoping the mobile trolley used mobile inertia that produces of lining cutting bed die to the collision of support; Hanging apparatus (26) is arranged on the gantry beam (16), is made up of lifting rope (17) and Chain block (18), and pulling Chain block (18) is realized the lifting of lining cutting bed die (1).
2. a kind of tunnel invert concrete lining bed die as claimed in claim 1 is mobile trolley used, it is characterized in that: described lining cutting bed die (1) comprises crossbeam (2) and welding hanger (3).
3. a kind of tunnel invert concrete lining bed die as claimed in claim 1 is mobile trolley used, and it is characterized in that: described Chain block (18) is provided with four groups at least.
CN 201320110972 2013-03-12 2013-03-12 Movable trolley of tunnel arch bottom concrete lining bottom die Expired - Fee Related CN203145959U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201320110972 CN203145959U (en) 2013-03-12 2013-03-12 Movable trolley of tunnel arch bottom concrete lining bottom die

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201320110972 CN203145959U (en) 2013-03-12 2013-03-12 Movable trolley of tunnel arch bottom concrete lining bottom die

Publications (1)

Publication Number Publication Date
CN203145959U true CN203145959U (en) 2013-08-21

Family

ID=48973495

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201320110972 Expired - Fee Related CN203145959U (en) 2013-03-12 2013-03-12 Movable trolley of tunnel arch bottom concrete lining bottom die

Country Status (1)

Country Link
CN (1) CN203145959U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110356782A (en) * 2019-07-17 2019-10-22 成都南方电子仪表有限公司 A kind of bogie movement system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110356782A (en) * 2019-07-17 2019-10-22 成都南方电子仪表有限公司 A kind of bogie movement system

Similar Documents

Publication Publication Date Title
CN108275573B (en) Hoisting construction method of tunnel boring machine and hoisting and translation combined equipment
CN202560245U (en) Multifunctional trolley with freely retractable arms
CN102146799B (en) Construction equipment for inverted arch of two-track tunnel of high-speed railway
CN203796297U (en) Temporary supporting device of driving working face
CN102226402B (en) Auxiliary device and method used for laying tunnel waterproofing plates
CN103726421B (en) Height and span adjustable track paver for metro construction
CN104195952A (en) Steel box girder erection method applied to steel and concrete hybrid girder cable-stayed bridge
CN109372529B (en) In-tunnel dismantling device and method for hard rock heading machine
CN102704949A (en) No-pull rod side wall construction method for underground tunnel and formwork trolley for construction
CN107747282B (en) On across both wired old bridge overall pulling down methods
CN202596743U (en) Formwork trolley for underground tunnel pull-rod-free side wall construction
CN102337905B (en) Open type TBM (Tunnel Boring Machine) fullface synchronous lining trolley for hydraulictunnel
CN104775825A (en) Shield machine single well overall originating construction method
CN103758522A (en) Temporary support method of tunneling working face and equipment thereof
CN212609137U (en) L-shaped cantilever type gantry crane
CN106869948A (en) A kind of construction that technique on shield machine's station-crossing is realized using the delivery vehicle that misses the stop
CN109930435A (en) Straddle-type monorail PC track beam construction method in a kind of circular cross section tunnel
CN202991063U (en) Large-section tunnel hydraulic trolley
CN106223983A (en) A kind of diversion tunnel inclined shaft, flat section tunneling boring primary steel mould trolley
CN108590745A (en) The transportation resources of shield method tunnel construction and its transport structure
CN105569671A (en) System and method for conveying residual soil in T-shaped underground excavation tunnel shield construction
CN102926388B (en) Earth moving method for deep foundation pit excavation
CN106837376B (en) Bind module turnover device for subway tunnel section of jurisdiction
CN203702178U (en) Bottom end supercharged type small-height tunnel lining trolley
CN203684019U (en) Height and span adjustable track laying machine for subway construction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: CHINA ELECTRIC POWER CONSTRUCTION BUILDING GROUP C

Free format text: FORMER NAME: SINOHYDRO BUREAU 2 CO., LTD.;LI HONG;HAN YUE

CP03 Change of name, title or address

Address after: 100120, Beijing, Xicheng District six paved south side street, No. 1

Patentee after: Middle electricity building Group Co., Ltd

Address before: 100120, Beijing, Xicheng District six paved south side street, No. 1 Technology Department

Patentee before: Sinohydro Bureau 2 Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130821

Termination date: 20180312