CN203025766U - Tool and appliance preparation list generation device - Google Patents

Tool and appliance preparation list generation device Download PDF

Info

Publication number
CN203025766U
CN203025766U CN2012206588136U CN201220658813U CN203025766U CN 203025766 U CN203025766 U CN 203025766U CN 2012206588136 U CN2012206588136 U CN 2012206588136U CN 201220658813 U CN201220658813 U CN 201220658813U CN 203025766 U CN203025766 U CN 203025766U
Authority
CN
China
Prior art keywords
work tool
tool
preparation list
bar code
appliance preparation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2012206588136U
Other languages
Chinese (zh)
Inventor
邵懂
程炜东
吴一峰
王召
赵华
罗明亮
沈传洲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
LIN'AN POWER SUPPLY BUREAU
State Grid Corp of China SGCC
Original Assignee
LIN'AN POWER SUPPLY BUREAU
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by LIN'AN POWER SUPPLY BUREAU, State Grid Corp of China SGCC filed Critical LIN'AN POWER SUPPLY BUREAU
Priority to CN2012206588136U priority Critical patent/CN203025766U/en
Application granted granted Critical
Publication of CN203025766U publication Critical patent/CN203025766U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • General Factory Administration (AREA)

Abstract

The utility model discloses a tool and appliance preparation list generation device, which belongs to the field of power asset management. The tool and appliance preparation list generation device comprises a barcode scanner for inputting a barcode, a computer connected with the barcode scanner and used for storing/executing programs, and a printing apparatus connected with the computer. The tool and appliance preparation list generation device can automatically generate a tool and appliance preparation list, and can avoid influences on the accuracy of the tool and appliance preparation list due to large differences among substations and various types and items of tools and appliances. The device can generate a plurality of types of tool and appliance preparation list at the same time; and the entire process is accurately controlled by the computer and is not affected by other human factors, so that the tools and appliances can be prepared accurately absolutely in one step to prevent from missing or taking wrong tools and appliances.

Description

A kind of Work tool is prepared single generating device
Technical field
The utility model relates to a kind of Work tool and prepares single generating device, belongs to the electric power asset management domain.
Background technology
Electrical equipment is divided into operation, standby (cold standby and stand-by heat), three kinds of states of maintenance, is that the process of another kind of state is back brake with equipment by a kind of state-transition.By operating breaker, disconnector and minute, splice grafting ground plug-in strip or extension, dismounting ground wire be converted to electrical equipment another kind of state or make system change the method for operation from a kind of state, grid switching operation just is in this operation.In electric system, grid switching operation is one of topmost work of operations staff, grid switching operation must executable operations ticket system be made with the work monitoring, operation order is specializing of operation task, operation intention and operation scheme, being the basic and crucial of correct executable operations, is the foundation that the person on duty carries out grid switching operation.
The grid switching operation flow process is at present: accept preliminary command, fill in operation order, and---the review operations ticket is correct, and------------the pin operation order is signed in practical operation---operation is reported---to Preventive Control of Dangerous Spot in the checking apparatus name to accept the scheduling positive order.In the aforesaid operations flow process, after receiving the scheduling positive order, before the formal operation of beginning, the person on duty should be with Work tool and the key that need use in this grid switching operation, as safety helmet, multimeter, control lever, ground wire, key etc. are disposable ready, i.e. so-called beam worker utensil.
In the grid switching operation process, Work tool is formally to prepare according to operation task operation order content before operation after the operations staff accepts to dispatch positive order temporarily at present.Larger difference, Work tool type and key project are various, some operation task operation order is many but because each electric substation exists, and lack the program of reaffirming, and other human factors, be difficult to guarantee that the disposable preparation of Work tool 100% is correct, leak to take by mistake by Work tool to occur repeatedly.Consider the actual conditions of Lou taking by mistake by Work tool, some Utilities Electric Co.s have released and have used Work tool to prepare list.After the review operations ticket was correct, the person on duty counted according to operation task operation order content and personal experience Work tool and the key that this action need is used, and gathered to be filled up to Work tool and to prepare singly to go up and examine and pass through.After the operations staff accepts to dispatch positive order during the beam worker utensil, directly prepare single listed Work tool according to Work tool and the key inventory is prepared.Although at present by this organiztion measure, the correctness that Work tool is prepared increases, leakage is taken by mistake by Work tool and still is difficult to avoid.
Leakage is taken by mistake and has been extended artificially equipment by Work tool and stop the labour time, has increased electrical network in improper mode working time, makes power supply reliability descend, and economy reduces, and power grid risk strengthens.Simultaneously, leakage is taken by mistake by Work tool and also may be caused pernicious misoperation fault.
In view of this, the inventor studies this, develops specially a kind of Work tool and prepares single generating device, and this case produces thus.
The utility model content
The purpose of this utility model be to provide a kind of can avoid leak taking by mistake by Work tool and Work tool simple in structure, simple operation prepare single generating device.
A kind of Work tool is prepared single generating device, comprises the barcode scanner for the bar code input, and is connected a computing machine for storage/executive routine that is connected with barcode scanner, and the printing device that is connected with computing machine, described computing machine execution following steps:
1) building database contains the data in data, the data in the key set of listings and each typical operation task Work tool preparation list in the Work tool set of listings in this database;
2) every typical operation task Work tool in step 1) is prepared single bar code that generates correspondence, and print by printing device, stick in the typical mission operation order;
3) when the operations staff carries out a certain typical operation task, scan this typical operation task Work tool with barcode scanner and prepare single bar code, obtain the bar code key assignments, and automatic entering computer database, computing machine extracts corresponding operation task Work tool and prepares single from database according to the bar code key assignments;
4) at last the operation task Work tool that generates in step 3) is prepared single-pass and cross the printing device printout, the operations staff prepares single postorder operation of carrying out according to the Work tool of output.
Described printing device comprises 1 universal printer at least.
As preferably, described printing device also comprises 1 bar code printer.
Computing machine is carried out above-mentioned steps 1) in, the data owner in described Work tool set of listings will comprise the typonym of all operations Work tool and managing security tools and instruments in transformer station; Data owner in described key set of listings will comprise the key titles such as equipment all in transformer station, anti-error, door; The data owner that described each typical operation task Work tool is prepared in list will comprise Work tool typonym and the key title that each typical operation required by task will be used.
Computing machine is carried out above-mentioned steps 3) in, when the operations staff carries out multinomial typical operation task, can scan simultaneously the bar code of multinomial typical operation task with barcode scanner, obtain a plurality of different bar code key assignments, and automatic entering computer database, computing machine extracts corresponding operation task Work tool according to different bar code key assignments and prepares list from database, and automatically is aggregated into the Work tool preparation list of a total multioperation task.
Adopt above-mentioned Work tool to prepare single generating device, prepare singly to fill in to compare with traditional Work tool, have following advantage: the database of the first Criterion of computing machine, can guarantee each electric substation not can because of have larger difference, Work tool type project is various and affect the correctness that Work tool is prepared list; Described device can also automatically generate the Work tool of multi-mode operation task simultaneously and prepare single, and whole process is accurately controlled by computing machine, can not be subjected to other interference from human factor, guarantee that the disposable preparation of Work tool 100% is correct, can not occur again to leak and take by mistake by the Work tool event, reduce to 0 thereby will take the pernicious misoperation fault risk that may cause by Work tool by mistake because of leakage.
Below in conjunction with drawings and the specific embodiments, the utility model is described in further detail.
Description of drawings
Fig. 1 is that the Work tool of the present embodiment is prepared the single generating device structural representation.
Embodiment
As shown in Figure 1, a kind of Work tool is prepared single generating device, comprise the barcode scanner 1 for a bar code input, with is connected a computing machine 2 that is used for storage/executive routine that is connected with barcode scanner 1, and the printing device that is connected with computing machine 2, wherein, printing device comprises the Taiwan Affairs Office's public affairs and an affairs universal printer 3, and a bar code printer 4.In the present embodiment, office and affairs universal printer 3 are used for marker's utensil and prepare list or alternative document, bar code printer 4 is mainly used in generating the bar code printing that Work tool is prepared single early stage, after the single corresponding bar code printing of all typical operation task Work tools preparations is good, can remove bar code printer 4.Sometimes, for saving resource, printing device also can include only the Taiwan Affairs Office's public affairs and an affairs universal printer 3, namely is used for printing bar code, is used for again Work tool preparation singles and prints.
In the present embodiment, take hilllock jurisdiction 110kV Shiquan transformer station of sun O﹠M class as example, above-mentioned computing machine 2 is carried out following steps:
1) building database contains the data in the Work tool set of listings: the typonym that mainly comprises all operations Work tool and managing security tools and instruments in transformer station in this database; Data in the key set of listings: mainly comprise the key titles such as equipment all in transformer station, anti-error, door; Each typical operation task Work tool is prepared the data in list: mainly comprise Work tool typonym and key title that each typical operation required by task will be used;
2) print bar code: every typical operation task Work tool in step 1) is prepared single bar code that generates unique correspondence, and print 4 out by bar code printer, stick in corresponding typical mission operation order;
3) sweep bar code: when the operations staff carries out 1 operation task and becomes 1# main transformer 10kV side and change cold standby into by operation as: 110kV Shiquan, with the bar code of barcode scanner 1 this operation task of scanning in the preparation of typical operation task Work tool is single, obtain the bar code key assignments, and automatically input computing machine 2 databases, computing machine 2 extracts corresponding operation task Work tool and prepares single from database according to the bar code key assignments;
4) at last the 110kV Shiquan who generates in step 3) is become 1# main transformer 10kV side and cross office and 3 printouts of affairs universal printer by the Work tool preparation single-pass that operation changes cold standby into, the operations staff prepares single postorder of carrying out again according to the Work tool of output and operates.
Wherein, before building database, need first to the field data standardization, namely first Work tool type and all keys of 110kV Shiquan transformer station are added up, set up Work tool set of listings and the key set of listings of 110kV Shiquan transformer station, arrange the Work tool preparation list corresponding to each typical operation task of 110kV Shiquan transformer station, set up hilllock jurisdiction 110kV Shiquan transformer station of sun O﹠M class single collection of typical operation task Work tool preparation.
Above-mentioned steps 3) in, when the operations staff carries out more than the typical operation task of 1, can scan simultaneously the bar code of multinomial typical operation tasks with barcode scanner 2, obtain a plurality of different bar code key assignments, and automatic entering computer database, computing machine extracts corresponding operation task Work tool according to different bar code key assignments and prepares list from database, and automatically is aggregated into the Work tool preparation list of a total multioperation task.
Above-described embodiment and graphic and non-limiting product form of the present utility model and style, any person of an ordinary skill in the technical field all should be considered as not breaking away from patent category of the present utility model to its suitable variation or modification of doing.

Claims (3)

1. a Work tool is prepared single generating device, it is characterized in that: comprise the barcode scanner for the bar code input, and is connected a computing machine for storage/executive routine that is connected with barcode scanner, and the printing device that is connected with computing machine.
2. a kind of Work tool as claimed in claim 1 is prepared single generating device, and it is characterized in that: described printing device comprises 1 universal printer at least.
3. a kind of Work tool as claimed in claim 1 is prepared single generating device, and it is characterized in that: described printing device also comprises 1 bar code printer.
CN2012206588136U 2012-11-30 2012-11-30 Tool and appliance preparation list generation device Expired - Lifetime CN203025766U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012206588136U CN203025766U (en) 2012-11-30 2012-11-30 Tool and appliance preparation list generation device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012206588136U CN203025766U (en) 2012-11-30 2012-11-30 Tool and appliance preparation list generation device

Publications (1)

Publication Number Publication Date
CN203025766U true CN203025766U (en) 2013-06-26

Family

ID=48649732

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012206588136U Expired - Lifetime CN203025766U (en) 2012-11-30 2012-11-30 Tool and appliance preparation list generation device

Country Status (1)

Country Link
CN (1) CN203025766U (en)

Similar Documents

Publication Publication Date Title
CN106157167B (en) Secondary equipment remote control operation ticket system and implementation method of secondary equipment remote control operation ticket
CN103761624A (en) Implementing method of integrated power grid dispatching operation intelligent mistaken-early-warning preventing system
CN111768077A (en) Intelligent power grid trip event identification method based on knowledge graph
CN103578039B (en) A kind of power networks risk prewarning analysis system
CN107167704B (en) Power distribution network fault diagnosis system and method based on CIM model
CN104678960B (en) It is a kind of based on scene it is anti-error and intend ticket training off-line type Dispatching system and method
CN110829595B (en) Intelligent power station relay protection equipment overhaul safety isolation measure execution method and system
CN103903075B (en) Protection device constant value automatic management method based on fuzzy matching
CN106815373B (en) Distribution network first-aid repair big data display method and system based on BI analysis
CN101592953A (en) Based on integrated monitoring intelligent simulation error-preventing operation bill system and method thereof
CN103414251A (en) Substation network communication simulation system based on IEC 61850
CN104463696A (en) Power grid operating risk recognition and prevention method and system
CN110674282B (en) Expert knowledge rule base-based one-key sequential control operation order intelligent simulation method
CN101692585A (en) Anti-operation locking system of transformation substation automatic system
CN109462278B (en) Power system switching operation method based on PDA
CN108233536A (en) A kind of intelligent program remote handling system
CN104091243A (en) Intelligent switching operation ticket mechanism designing and achieving method
CN103326467A (en) Protection action report implementation method based on information protection main station device recorded information
CN109782724B (en) Control method for preventing misoperation-locking and terminal equipment
CN106093636B (en) The analog quantity check method and device of the secondary device of smart grid
CN105186686B (en) A kind of dispatching of power netwoks intelligent error preventing policy system based on full mesh topology
CN112529445A (en) Scheduling power failure and recovery condition anti-misoperation method and system based on artificial intelligence
CN112214901A (en) Distribution network scheduling instruction ticket security checking method and system based on traversal tree
CN103793370A (en) Automatic intelligent substation information sheet generating system
CN102968697A (en) Generation device and method of tool and instrument preparation list