CN202946167U - Prefabricated assembling type lining mechanism - Google Patents

Prefabricated assembling type lining mechanism Download PDF

Info

Publication number
CN202946167U
CN202946167U CN 201220544435 CN201220544435U CN202946167U CN 202946167 U CN202946167 U CN 202946167U CN 201220544435 CN201220544435 CN 201220544435 CN 201220544435 U CN201220544435 U CN 201220544435U CN 202946167 U CN202946167 U CN 202946167U
Authority
CN
China
Prior art keywords
plate
prefabricated
base plate
liner structure
top board
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201220544435
Other languages
Chinese (zh)
Inventor
李亚军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 18th Bureau Group Co Ltd
Third Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Original Assignee
Third Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd filed Critical Third Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Priority to CN 201220544435 priority Critical patent/CN202946167U/en
Application granted granted Critical
Publication of CN202946167U publication Critical patent/CN202946167U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a prefabricated assembling type lining mechanism which comprises a top plate, a base plate and a side wall plate. A middle-level plate is arranged between the top plate and the base plate, and a middle pole is arranged between the middle-level plate and the base plate. The top plate comprises a middle top plate and a corner plate. A prefabricated longitudinal beam is arranged on the middle pole. The prefabricated assembling type lining mechanism can simplify construction procedures on spot, shortens construction period and meanwhile improves construction safety.

Description

Prefabricated assembled liner structure
Technical field
The utility model relates to a kind of liner structure, especially relates to a kind of prefabricated assembled liner structure.
Background technology
Present subway station liner structure mostly is site operation and builds, and on-site construction processes is various, and every inter process restricts mutually, and the duration is longer.And when constructing in the winter time, need to adopt the measures such as brooder, but concrete quality is difficult for assurance, heating, reinforcing bar processing may cause on-the-spot fire, bring inconvenience to site operation.
Summary of the invention
The purpose of this utility model is to provide a kind of prefabricated assembled liner structure, can simplify on-site construction processes, shortens the construction period, improves simultaneously the safety of construction.
For achieving the above object, the utility model provides a kind of prefabricated assembled liner structure, comprises top board, base plate and framed side wallboard, is provided with la m between described top board and described base plate, is provided with center pillar between described la m and described base plate.
Preferably, described top board comprises middle top board and corner plate.
Preferably, described center pillar is provided with prefabricated longeron.
Preferably, pass through cast-in-place joint between described framed side wallboard and described la m.
Preferably, pass through cast-in-place joint between described corner plate and described framed side wallboard.
Therefore, the utility model adopts the prefabricated assembled liner structure of said structure, can simplify on-site construction processes, shortens the construction period, improves simultaneously the safety of construction.
Below by drawings and Examples, the technical solution of the utility model is described in further detail.
Description of drawings
Fig. 1 is the structural representation of the prefabricated assembled liner structure embodiment of the utility model.
The specific embodiment
Embodiment
Fig. 1 is the structural representation of the prefabricated assembled liner structure embodiment of the utility model, as shown in Figure 1, comprise top board, base plate 1 and framed side wallboard 2, described top board comprises middle top board 3 and corner plate 4, be provided with la m 5 between described top board and base plate 1, be provided with center pillar 6 between la m 5 and base plate 1.Center pillar 6 is provided with prefabricated longeron 7.Between framed side wallboard 2 and la m 5, by cast-in-place joint, la m 5 both sides are equipped with gets rid of muscle, and the muscle that gets rid of of being connected with framed side wallboard with prefabricated longeron 7 is connected with welding manner, then makees the cast-in-situ concrete band.Between corner plate 4 and framed side wallboard 2, by cast-in-place joint, corner plate 4 is provided with framed side wallboard 2 joints and gets rid of muscle, will both be combined into overall structure by pouring concrete.The prefabricated units of middle top board 3 adopt rib type structure, to alleviate the deadweight of member.For ease of explanation, in the present embodiment Fig. 1, gantry crane 8 and the auxiliary chassis 9 of vault lifting also are plotted in figure.The present embodiment adopts prefabricated assembled construction, design, material, member processing and quality management and control etc. can be effectively integrated, improve the comprehensive benefit of engineering, after the piecemeal of station, member length is no more than 10m, maximum construction weight is no more than 25t, the quality of prefabricated member, the precision of on-site consolidation can reach the level of shield duct piece, make the quality level at station significantly improve; Simultaneously, the duration significantly shortens the impact that can effectively reduce Construction on Ground traffic, surrounding enviroment, and effectively avoids the impact of winter on the duration.March into the arena August as unit in charge of construction, adopt the assembling station can construct by the end of November and complete, adopt the conventional method can only be in Second Year completion in September.
Therefore, the utility model adopts the prefabricated assembled liner structure of said structure, can simplify on-site construction processes, shortens the construction period, improves simultaneously the safety of construction.
It should be noted that at last: above embodiment is only in order to the technical solution of the utility model to be described but not be limited, although with reference to preferred embodiment, the utility model is had been described in detail, those of ordinary skill in the art is to be understood that: it still can be modified or be equal to replacement the technical solution of the utility model, and these modifications or be equal to replacement and also can not make amended technical scheme break away from the spirit and scope of technical solutions of the utility model.

Claims (5)

1. a prefabricated assembled liner structure, is characterized in that: comprise top board, base plate and framed side wallboard, be provided with la m between described top board and described base plate, be provided with center pillar between described la m and described base plate.
2. prefabricated assembled liner structure according to claim 1, it is characterized in that: described top board comprises middle top board and corner plate.
3. prefabricated assembled liner structure according to claim 2, it is characterized in that: described center pillar is provided with prefabricated longeron.
4. prefabricated assembled liner structure according to claim 3, is characterized in that: pass through cast-in-place joint between described framed side wallboard and described la m.
5. prefabricated assembled liner structure according to claim 4, is characterized in that: pass through cast-in-place joint between described corner plate and described framed side wallboard.
CN 201220544435 2012-10-23 2012-10-23 Prefabricated assembling type lining mechanism Expired - Lifetime CN202946167U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220544435 CN202946167U (en) 2012-10-23 2012-10-23 Prefabricated assembling type lining mechanism

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220544435 CN202946167U (en) 2012-10-23 2012-10-23 Prefabricated assembling type lining mechanism

Publications (1)

Publication Number Publication Date
CN202946167U true CN202946167U (en) 2013-05-22

Family

ID=48421874

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220544435 Expired - Lifetime CN202946167U (en) 2012-10-23 2012-10-23 Prefabricated assembling type lining mechanism

Country Status (1)

Country Link
CN (1) CN202946167U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104153389A (en) * 2014-08-11 2014-11-19 中铁建大桥工程局集团第六工程有限公司 Construction method for prefabricated assembly type subway station
CN104762990A (en) * 2015-02-11 2015-07-08 中国铁建大桥工程局集团有限公司 Modular construction method of subway station
CN113216257A (en) * 2021-06-01 2021-08-06 中铁四局集团有限公司 Full hoisting construction method for assembled subway station in pile anchor enclosing structure system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104153389A (en) * 2014-08-11 2014-11-19 中铁建大桥工程局集团第六工程有限公司 Construction method for prefabricated assembly type subway station
CN104762990A (en) * 2015-02-11 2015-07-08 中国铁建大桥工程局集团有限公司 Modular construction method of subway station
CN113216257A (en) * 2021-06-01 2021-08-06 中铁四局集团有限公司 Full hoisting construction method for assembled subway station in pile anchor enclosing structure system

Similar Documents

Publication Publication Date Title
CN204849569U (en) Steel pipe concrete stem stem prefabricated unit construction bridge pier stud of putting more energy into
CN204940886U (en) A kind of mechanism of handling vestibule
CN103243640B (en) Cap beam efficient, convenient and quick to construct and construction method thereof
CN103215894B (en) Portable interim prestressed stretch-draw anchor block
CN104695979B (en) A kind of method using tall and big chassis whole lateral moving high and big die plate
CN105442864A (en) Local reinforcing method of circular reinforced concrete column
CN203174771U (en) Annular plate node of steel pipe concrete column and bonded prestress steel bar concrete beam
CN202946167U (en) Prefabricated assembling type lining mechanism
CN105926775A (en) Novel concrete-filled steel tube beam column joint
CN103321153B (en) A kind of construction method of Mid and minor spans channel girder
CN202689536U (en) Ultra-high concrete beam and slab structure template erecting system
CN103790176A (en) Embedded short strut structure and construction method thereof
CN104032861B (en) Mixing coupled wall steel column and non-energy dissipating beam connecting node structure and construction method thereof
CN104164882B (en) Side slope builds construction method and the structure on supporting and protection structure beam basis
CN106638985A (en) Hollow concrete-filled steel tube composite column and reinforced concrete beam joint
CN203782984U (en) Horse stool rib capable of controlling elevation and flatness of slab surface
CN203129322U (en) Concrete cavity type assembled house
CN206128787U (en) Assembled dregs strorage device
CN205935352U (en) Building carrier plate is from formwork
CN206174482U (en) Outsourcing concrete ring beam reinforcing bar integral erection device of no bracket steel -pipe column
CN204212273U (en) A kind of composite steel concrete column and box concrete filled steel tube cant beam switching node
CN204875493U (en) Precast reinforced concrete post convenient to assembly
CN210288869U (en) Precast concrete board subassembly
CN204001330U (en) A kind of steel work floor
CN202164729U (en) Knee brace structure between beams of different heights

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: THE EIGHTEENTH BUREAU OF CHINA'S RAILROAD GROUP CO

Effective date: 20130427

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent of invention or patent application
CB03 Change of inventor or designer information

Inventor after: Li Chunkui

Inventor before: Li Yajun

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: LI YAJUN TO: LI CHUNKUI

TR01 Transfer of patent right

Effective date of registration: 20130427

Address after: Guanyun Zhuozhou Road, 072750 Hebei city of Baoding Province

Patentee after: CHINA RAILWAY 18TH ENGINEERING GROUP THIRD ENGINEERING Co.,Ltd.

Patentee after: CHINA RAILWAY 18 BUREAU GROUP Co.,Ltd.

Address before: Guanyun Zhuozhou Road, 072750 Hebei city of Baoding Province

Patentee before: CHINA RAILWAY 18TH ENGINEERING GROUP THIRD ENGINEERING Co.,Ltd.

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20130522