CN202925471U - Hydraulic formwork system for high pier construction - Google Patents
Hydraulic formwork system for high pier construction Download PDFInfo
- Publication number
- CN202925471U CN202925471U CN 201220464574 CN201220464574U CN202925471U CN 202925471 U CN202925471 U CN 202925471U CN 201220464574 CN201220464574 CN 201220464574 CN 201220464574 U CN201220464574 U CN 201220464574U CN 202925471 U CN202925471 U CN 202925471U
- Authority
- CN
- China
- Prior art keywords
- hydraulic
- enclosure
- high pier
- carriage
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The utility model discloses a hydraulic formwork system for high pier construction. The hydraulic formwork system comprises a steel pipe stand rod which is pre-embedded in concrete. The steel pipe stand rod penetrates through a cross beam of a supporting frame and a hydraulic jack installed on the cross beam of the supporting frame. The jack climbs upwards automatically along the stand rod through inner teeth. Climbing precision of the jack is controlled through a limiting clamp ring arranged above the jack. An enclosure is fixed on the side surface of the supporting frame. A working platform is arranged above the enclosure in a laying mode. A decoration hanging basket is installed below the enclosure. An automatic spray maintainer is installed on the decoration hanging basket. A formwork is arranged in the supporting frame. The side face of the formwork is connected with the enclosure through an adjusting lead screw which can adjust the position of the formwork in the transverse direction. The top end of the formwork is hung on the cross beam of the supporting frame through a hanging rod which can slide along the cross beam of the supporting frame in the transverse direction. A control table is fixed on the working platform and connected with the hydraulic jack through pipelines. The hydraulic formwork system for the high pier construction has the advantages of being good in safety, recyclable in construction, capable of saving cost, fast in construction speed, good in construction appearance quality, good in maintaining effect and capable of improving construction efficiency greatly.
Description
Technical field
The utility model relates to the Building technology application, particularly a kind of hydraulic formwork system for high pier construction.
Background technology
Mountain highway and railroad bridge ratio are large, span of bridge is larger, high pier is higher, present high pier maximum height reaches 195m (the Hezhang grand bridge that Hezhang County, Bijie Prefecture, Guizhou Province is domestic), bridge can well connect valley and gully, assurance road alignment, raising car speed, save the advantages such as cost of transportation, saving Land resources in mountainous areas, so the high pier of Bridges in Mountainous Areas is comparatively extensive.For high pier construction, the technique of comparative maturity mainly contains following several at present:
1, climbing formwork for construction
Creeping formwork is mainly pre-buried hanging seat built-in fitting in concrete, mounting guide rail and bearing frame, and template is climbed by guide rail.This system need to be before each concreting, the built-in fitting of pre-buried special use, high to the pre-buried required precision of built-in fitting, pre-buried control difficulty, working load and template system deadweight all reach the concrete of having built, and require high to concrete strength, concrete is easy to destroy, can not form flowing water and work continuously, built-in fitting and template have high input, and construction cost is high.Because cost is high, so choice for use is not generally done by unit in charge of construction.
2, over-form construction
Turning over mould is to adopt the circulation of two-stage template to turn over the process that rises, and over-form construction template use amount is large, and speed of application is fast, and template is mainly stressed to drawing by pull bar, and build needs remove and reinstall template at every turn, exists certain dangerous in construction.Because speed of application is very fast, outward appearance is easy to control, and uses general in high pier construction.
3, slding form operation
Sliding formwork is that template is fixed in enclosure, working load, template is stressed and the deadweight be passed to carriage, be passed to vertical rod by jack.The native system template drops into little, but pre-buried vertical rod expense is large, outward appearance, linear and verticality control difficulty in construction, concrete is had relatively high expectations, and sliding time is restive, and when sliding, template and concrete frictional resistance are large, system easily damages, and has certain danger.Because the construction outward appearance is difficult to solve, therefore generally do not select slding form operation.
4, sliding turning in conjunction with construction
it is sliding that to turn in conjunction with construction be on the slding form operation basis, fixing stencil design is become can remove and install, take full advantage of sliding formwork and the advantage of turning over mould, solved the restive and concrete initial set time trouble problem of slding form operation outward appearance, this system template is removed and is quick for installation, reduce security risk, each inter process can form continuous productive process, thereby accelerating construction progress, improve work efficiency, greatly save cost, the automatic sprinkler fire-extinguishing system that adopts has been guaranteed high pier health quality, it is the present mountain area most advanced system of high pier construction that cunning is turned in conjunction with template system, overcome creeping formwork, turn over mould, the shortcoming of sliding formwork.
Summary of the invention
The purpose of this utility model is in order to address the above problem, and has designed a kind of hydraulic formwork for high pier construction (slide-turn in conjunction with) system.
Realize that the above-mentioned purpose the technical solution of the utility model is, a kind of hydraulic formwork system for high pier construction, comprise the steel tube poles that is embedded in concrete, steel tube poles passes the header portion of carriage, hydraulic jack is arranged on the crossbeam of carriage, and the location snap ring is fixed on steel tube poles controls the hydraulic jack precision of creeping.Enclosure is fixed on the side surface of carriage, working platform is laid in the top of enclosure, the below of enclosure is installed and is modified hanging basket, modify on hanging basket the automatic spray mounted maintenance equipment is installed, template group is positioned at carriage, but the adjusting screw of the side of template group by lateral adjustments template group position is connected with enclosure, the top of template group is by hanging on the crossbeam of carriage along the suspension rod of the horizontal slip of carriage header portion, console is fixed on working platform, adopts pipeline to be connected with hydraulic jack.
Described template group is the overall structure that is joined together to form by Screw arbor with nut at both-ends by inner and outer template, but and with the adjusting screw of lateral adjustments template group position as support.
Described suspension rod is by consisting of along the slide block of carriage header portion slip, shrinking connecting-rod two parts that an end is connected with slide block.
Described adjusting screw is to screw in the structure that the screens bolt forms on leading screw.
Described working platform is provided with guardrail.
The structure of described Screw arbor with nut at both-ends is locating piece to be installed on cross bar form.
Described shrinking connecting-rod is the structure that is connected to form with the two ends of regulation cock respectively by two connecting rods.
The hydraulic formwork system that is used for high pier construction that utilizes the technical solution of the utility model to make with sliding formwork and turn over that the mould advantage is fine to combine, forms good continuous productive process operation; Owing to using automatic hydraulic sliding formwork Hoisting System, make template promote automation, the template system operating platform has enough wide work and stacks the space, guaranteed that high pier construction is not limited by night, construction material can lift in advance and be deposited on platform, prepare in advance for construction, can also reduce construction safety risk simultaneously; Template adopts adjusting screw, and installation and removal is convenient, does not need other equipment to coordinate; When system improving, template is separated with concrete surface, and the frictional force that in the elimination lifting process, template and concrete produce causes the concrete surface drawing crack, can also increase Systems balanth and safety; Also be not subjected to simultaneously the concrete initial set time restriction, be convenient to regulate concrete verticality and line style; Hanging basket system plays after being convenient to build concrete and modifies, and spray system plays automatic health effect, solves high pier health difficult.
Description of drawings
Fig. 1 is the structural representation of the hydraulic formwork system for high pier construction described in the utility model;
Fig. 2 is the structural representation of suspension rod described in the utility model;
Fig. 3 is the structural representation of adjusting screw described in the utility model;
Fig. 4 is the sectional structure chart of Screw arbor with nut at both-ends described in the utility model;
In figure, 1, concrete; 2, steel tube poles; 3, carriage; 4, hydraulic jack; 5, location snap ring; 6, enclosure; 7, working platform; 8, modify hanging basket; 9, automatic spray mounted maintenance equipment; 10, adjusting screw; 11, suspension rod; 12, console; 13, template; 14, Screw arbor with nut at both-ends; 15, slide block; 16, shrinking connecting-rod; 17, leading screw; 18, screens bolt; 19, guardrail; 20, cross bar; 21, locating piece; 22, reconcile bolt.
The specific embodiment
below in conjunction with accompanying drawing, the utility model is specifically described, it is the structural representation of the hydraulic formwork system for high pier construction described in the utility model as Fig. 1, as shown in the figure, a kind of hydraulic formwork system for high pier construction, comprise the steel tube poles 2 that is embedded in concrete 1, steel tube poles passes the header portion of carriage 3, hydraulic jack 4 an end by the location snap ring 5 be fixed on steel tube poles, the other end is connected with the header portion of carriage, enclosure 6 is fixed on the side surface of carriage, working platform 7 is laid in the top of enclosure, the below of enclosure is installed and is modified hanging basket 8, modify on hanging basket automatic spray mounted maintenance equipment 9 is installed, template group is positioned at carriage, but the side of template group is connected with enclosure by the adjusting screw 10 of lateral adjustments template group position, the top of template group is by hanging on the crossbeam of carriage along the suspension rod 11 that the carriage header portion laterally slides, console 12 is fixed on working platform and is electrically connected to hydraulic jack and automatic spray mounted maintenance equipment respectively.Wherein, described template group is the overall structure that is joined together to form by Screw arbor with nut at both-ends 14 by two parallel templates 13; Described suspension rod is by consisting of along the slide block 15 of carriage header portion slip, shrinking connecting-rod 16 two parts that an end is connected with slide block; Described adjusting screw is to screw in the structure that screens bolt 18 forms on leading screw 17; Described working platform is provided with guardrail 19; The structure of described Screw arbor with nut at both-ends is locating piece 21 to be installed on cross bar 20 form; Described shrinking connecting-rod is the structure that is connected to form with the two ends of regulation cock 22 respectively by two connecting rods.
The characteristics of the technical program are with sliding formwork and turn over that the mould advantage is fine to combine, form good continuous productive process operation, that is: after concreting is completed, just can carry out next joint reinforcement installation, utilize after reinforcement installation and regulate the screw mandrel stripping, by operating desk Lifting Modules frame system, rear installation form in place checks concreting, exist defective to modify on hanging basket, start the health of spray system valve, template is installed the after-pouring concrete, the circulation construction.
Owing to using automatic hydraulic sliding formwork Hoisting System, play the automation that template promotes; The template system operating platform has enough wide work and stacks the space, has guaranteed that high pier construction is not limited by night, and construction material can lift in advance and be deposited on platform, prepares in advance for construction, can also reduce construction safety risk simultaneously.Template adopts adjusting screw, and installation and removal is convenient, does not need other equipment to coordinate; When system improving, template is separated with concrete surface, and the frictional force that in the elimination lifting process, template and concrete produce causes the concrete surface drawing crack, can also increase Systems balanth and safety; Also be not subjected to simultaneously the concrete initial set time restriction, be convenient to regulate concrete verticality and line style.Hanging basket system plays after being convenient to build concrete and modifies, and spray system plays automatic health effect, solves high pier health difficult.
Template is supported in enclosure by adjusting screw, by adjusting screw disassembling bolts and installation form; The horizontal slip of template top employing, vertical adjustable suspension rod are fixed, the main fixed form of suspension rod position, the vertical adjustment bolt is convenient to the adjusting template upper-lower position, the slide block of horizontal slip coordinates template supporting wire thick stick, when the template installation and removal, slide the position of suspension rod during with leading screw installation and removal template; Two templates connect by Screw arbor with nut at both-ends, coordinate support leading screw integral body stressed, prevent that the enclosure plastic deformation from causing the swollen mould of template.By leading screw and suspension rod, Screw arbor with nut at both-ends, sliding mode system is become turn over mold technique and construct, solve slding form operation outward appearance, linear control difficulty, can also avoid the frictional force that produces between template and concrete because of sliding formwork in lifting process, improved security of system.
In the utility model, operation platform adopts angle steel to be welded in enclosure, forms enough construction operation space, and the constructability operation can be stacked material simultaneously on platform, and therefore, high pier construction is not subjected to the restriction of can not constructing night; Because platform can be stacked material, so form continuous productive process, accelerating construction progress greatly between technique; The platform surrounding guarantees with the high protective guard of steel-pipe welding 1.2m the safety that the workman constructs.Whole platform can reduce the danger of construction greatly.
In the utility model, the hanging basket that install enclosure below is the following secondary operation platform of enclosure in construction, also can facilitate to carry out concrete appearance after form removable and modify.Be installed on automatic spray mounted maintenance equipment and the pipeline of hanging basket inboard, after form removable, the opening conduits valve just can carry out automatic maintenance, guarantees high pier maintenance quality, saves maintenance costs.
In the utility model, the angle steel welding is adopted in enclosure, and enclosure is the carrier of whole system, with Load Transfer such as template, platform and external loads thereof, hanging basket, spray system and pipelines to the carriage of welding.Carriage adopts angle steel, i iron etc. to weld, and power is passed to jack, carriage be stressedly concentrate the most, the stressed weak part of rod member, therefore reinforce by the channel-section steel diagonal brace before and after carriage.
In the utility model, hydraulic jack is fixed on the carriage crossbeam, and on the steel tube poles of punching in being embedded in concrete, whole system is along the vertical rod automatic climbing under the control of console.Each climb altitude and precision are controlled by the snap ring that is arranged in vertical rod.The console platform is arranged on working platform, and hydraulic line is laid along enclosure and carriage, adopts main line and separated time to lay, and is convenient to regulate the stroke of controlling each jack.Console mainly is comprised of motor, oil pump, oil meter, operating key, alarm bell, display lamp etc.
Technique scheme has only embodied the optimal technical scheme of technical solutions of the utility model; some changes that those skilled in the art may make some part have wherein all embodied principle of the present utility model, within belonging to protection domain of the present utility model.
Claims (7)
1. hydraulic formwork system that is used for high pier construction, comprise the steel tube poles (2) that is embedded in concrete (1), it is characterized in that, steel tube poles passes the header portion of carriage (3), hydraulic jack (4) is arranged on the crossbeam of carriage, location snap ring (5) is fixed on steel tube poles controls the hydraulic jack precision of creeping, enclosure (6) is fixed on the side surface of carriage, working platform (7) is laid in the top of enclosure, the below of enclosure is installed and is modified hanging basket (8), modify on hanging basket automatic spray mounted maintenance equipment (9) is installed, template group is positioned at carriage, but the side of template group is connected with enclosure by the adjusting screw (10) of lateral adjustments template group position, the top of template group is by hanging on the crossbeam of carriage along the suspension rod (11) that the carriage header portion laterally slides, console (12) is fixed on working platform and is connected with hydraulic jack by pipeline.
2. the hydraulic formwork system for high pier construction according to claim 1, is characterized in that, described template group is the overall structure that is joined together to form by Screw arbor with nut at both-ends (14) by inner and outer template (13).
3. the hydraulic formwork system for high pier construction according to claim 1, is characterized in that, described suspension rod is by consisting of along the slide block (15) of carriage header portion slip, shrinking connecting-rod (16) two parts that an end is connected with slide block.
4. the hydraulic formwork system for high pier construction according to claim 1, is characterized in that, described adjusting screw is in the upper structure that screws in screens bolt (18) formation of leading screw (17).
5. the hydraulic formwork system for high pier construction according to claim 1, is characterized in that, described working platform is provided with guardrail (19).
6. the hydraulic formwork system for high pier construction according to claim 2, is characterized in that, the structure of described Screw arbor with nut at both-ends is that the upper locating piece (21) of installing of cross bar (20) forms.
7. the hydraulic formwork system for high pier construction according to claim 3, is characterized in that, described shrinking connecting-rod is the structure that is connected to form with the two ends of regulation cock (22) respectively by two connecting rods.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220464574 CN202925471U (en) | 2012-09-13 | 2012-09-13 | Hydraulic formwork system for high pier construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220464574 CN202925471U (en) | 2012-09-13 | 2012-09-13 | Hydraulic formwork system for high pier construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202925471U true CN202925471U (en) | 2013-05-08 |
Family
ID=48215447
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201220464574 Expired - Fee Related CN202925471U (en) | 2012-09-13 | 2012-09-13 | Hydraulic formwork system for high pier construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202925471U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105780661A (en) * | 2016-03-31 | 2016-07-20 | 中交公局第六工程有限公司 | High pier sliding and turning integrated construction formwork system |
CN112663516A (en) * | 2021-01-19 | 2021-04-16 | 江苏玖沐精工装备科技有限公司 | Construction method of bridge thin-wall hollow pier column |
-
2012
- 2012-09-13 CN CN 201220464574 patent/CN202925471U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105780661A (en) * | 2016-03-31 | 2016-07-20 | 中交公局第六工程有限公司 | High pier sliding and turning integrated construction formwork system |
CN105780661B (en) * | 2016-03-31 | 2018-06-29 | 中交一公局第六工程有限公司 | High pier cunning turns over integrated construction template system |
CN112663516A (en) * | 2021-01-19 | 2021-04-16 | 江苏玖沐精工装备科技有限公司 | Construction method of bridge thin-wall hollow pier column |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102071798B (en) | Hydraulic climbing system for wall-attached support frame | |
CN104695337B (en) | Self-lifting sliding and turnover construction system and construction method | |
CN103306208A (en) | Formwork creeping method for novel 1.6 parabola-shaped four-column type hollow variable section high pier | |
CN102345381A (en) | Hydraulic creeping formwork system and creeping formwork construction method | |
CN103306206B (en) | A kind of construction method adopting thin-wall hollow high-pier reinforcement bar support fixing of the forming frame reinforcing bar | |
CN105401679A (en) | Large-gradient cast-in-place concrete inclined roof construction method | |
CN103243649B (en) | The system and method for a kind of cable saddle Fast Installation, location | |
CN202000658U (en) | Hydraulic climbing system for wall-attached support frame | |
CN101294443A (en) | High altitude platform mounting method | |
CN204626411U (en) | A kind of pile foundation steel bar cage erecting device | |
CN105780661B (en) | High pier cunning turns over integrated construction template system | |
CN202227365U (en) | Form traveler for guide wall of underground continuous wall | |
CN201962608U (en) | Adjustable viaduct concrete anti-collision guardrail template supporting device | |
CN202925471U (en) | Hydraulic formwork system for high pier construction | |
CN105887885A (en) | Symmetric rock anchor beam concrete pouring trolley | |
CN103628692B (en) | A kind of floor beam mounting bracket and use it to install the method for floor beam | |
CN105442453A (en) | Construction method for suspension bridge tower crossbeam combination support | |
CN203222980U (en) | Stretchable patterned elevator shaft operation platform | |
CN106284989B (en) | The sliding form bracing system of double track and complete construction method | |
CN209194354U (en) | High-altitude long-span binder base-supporting shellfish thunder support construction | |
CN205669313U (en) | A kind of Universal adjustable hangs template system | |
CN104612741A (en) | Rail top air channel trolley construction method | |
CN204212065U (en) | Bridge crossing anticollision barrier punching block erection equipment | |
CN203429556U (en) | System for quickly installing and positioning cable saddle | |
CN105887884A (en) | Single-side type rock anchor beam concrete pouring trolley |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20130508 Termination date: 20180913 |