CN202881986U - Single-pile vertical static test pile head steel bar connection node - Google Patents

Single-pile vertical static test pile head steel bar connection node Download PDF

Info

Publication number
CN202881986U
CN202881986U CN 201220527283 CN201220527283U CN202881986U CN 202881986 U CN202881986 U CN 202881986U CN 201220527283 CN201220527283 CN 201220527283 CN 201220527283 U CN201220527283 U CN 201220527283U CN 202881986 U CN202881986 U CN 202881986U
Authority
CN
China
Prior art keywords
pile
steel bar
advocated
muscle
static test
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220527283
Other languages
Chinese (zh)
Inventor
于成江
章慧蓉
逯艳华
陆志军
庞卫涛
张斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN 201220527283 priority Critical patent/CN202881986U/en
Application granted granted Critical
Publication of CN202881986U publication Critical patent/CN202881986U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a single-pile vertical static test pile head, and in particular provides a single-pile vertical static test pile head steel bar connection node. The single-pile vertical static test pile head steel bar connection node comprises a steel bar cage and pile top reinforcing devices which are welded on the steel bar cage. The steel bar cage comprises stress main ribs and hoop ribs which are bundled up on the stress main ribs, and upper ends of the stress main ribs are processed and formed thread sections, and are cooperated with the thread sections to be connected with thread sleeves. The pile top reinforcing devices comprise pressure-bearing plates and reinforcing hoops which are welded on the pressure-bearing plates. A plurality of reserved holes are formed in the pressure-bearing plates according to positions of the stress main ribs of the steel bar cage of a filling piles, and one ends of the stress main ribs which are provided with the thread sleeves are threaded and fixed into the reserved holes. According to the single-pile vertical static test pile head steel bar connection node, the construction difficulty is reduced, a connection manner with few field welding processes, explicit force transmission and convenience in construction is provided, the node simplifies a construction process and accelerates a construction progress, and a wide popularization prospect aiming at the treatment of a vertical static test pile head is had.

Description

Single-pile vertical orientation static loading test pile head steel bar connecting joints
Technical field
The utility model relates to a kind of building structure technology field, refers in particular to a kind of single-pile vertical orientation static loading test pile head steel bar connecting joints.
Background technology
More for the processing mode of engineering pile single-pile vertical orientation static loading test pile head reinforcing bar connection at present.More original a kind of mode is that the test pile pile crown is cut, and picks out the muscle of being advocated, and according to will be advocated muscle spreading and meet the anchoring requirement of engineering pile of the overlap joint of reinforcing bar or welding requirements, then concreting is high to design stake top mark; Also have some engineerings, the processing mode that connects at test pile pile crown reinforcing bar has than much progress, when the test pile pile crown is reinforced, take into full account pile crown and strengthen the effect of hoop and bearing plate, muscle is welded to connect and guarantees enough bonding strengths with strengthening hoop and bearing plate with being advocated, then after the test pile detection is complete, directly utilize pile crown bracing means welding stake top to expose dowel and carry out follow-up construction.A kind of mode in front is in waste of manpower, material resources, in the time, also can cause the pollution of environment, do not meet the green construction requirement, although the front a kind of method of rear a kind of mode has larger progress, but steel bar connecting joints is stressed too complicated, and the muscle of being advocated is difficult to carry out detection validation by test by the power transmission that bearing plate or reinforcement hoop weld.Therefore, in view of above reason, need to explore a kind of both constructabilities advocated muscle power transmission again rational connected node and job practices thereof.
Summary of the invention
The utility model is for the deficiencies in the prior art, provide now that a kind of On-site Welding Technology is few, power transmission is clear and definite, the connected mode of convenient construction, test pile is advocated muscle top exposed parts with main muscle separately, and finally connect by the screw thread steel sleeve, reach the control of one-level joint by new designs of threaded joints, guaranteed the advocated compliance of muscle power transmission of stake top.
Single-pile vertical orientation static loading test pile head steel bar connecting joints of the present utility model, comprise reinforcing cage and the stake top bracing means that is welded on the reinforcing cage, described reinforcing cage comprises advocated muscle and the stirrup that is bound on the described muscle of being advocated, and the upper end of the described muscle of being advocated is processed to form a thread segment, and cooperates described thread segment to connect a screw shell; Described stake top bracing means comprises a bearing plate and the reinforcement hoop that is welded on the described bearing plate, position according to the muscle of being advocated of the reinforcing cage of described castinplace pile on the described bearing plate offers a plurality of preformed holes, and the end that the described muscle of being advocated is provided with screw shell wears and is fixed in the described hole.
The utility model makes its beneficial effect that has be owing to adopting above technical scheme:
Adopt this node to fill up the deficiency of existing construction technology and method, test pile is advocated muscle top exposed parts reinforcing bar with main muscle separately, and finally connect by the screw thread steel sleeve, reach the control of one-level joint by new designs of threaded joints, guaranteed the advocated compliance of muscle power transmission of stake top.The utility model has reduced difficulty of construction, has improved construction precision, can provide a kind of On-site Welding Technology few, power transmission is clear and definite, the connected mode of convenient construction, the connected mode of this node both can be applicable to the Vertical Static Loading Test stake, the pulling resistant anchor pile that also can be applicable to uplift pile and utilize engineering pile to test simultaneously.This node has been simplified work progress, has accelerated construction speed, has wide promotion prospect for the processing of Vertical Static Loading Test pile head.
Description of drawings
Fig. 1 is test pile pile crown generalized section of the present utility model;
Fig. 2 is the schematical top view of of the present utility model the pressing plate of bearing responsibility;
Fig. 3 be the stressed main muscle of test pile crown of the present utility model with after plant the schematic diagram of dowel when not being connected.
The specific embodiment
For the benefit of to further understanding of the present utility model, describe below in conjunction with drawings and Examples.
In conjunction with shown in Figure 1, single-pile vertical orientation static loading test pile head steel bar connecting joints of the present utility model, comprise reinforcing cage 1 and the stake top bracing means 2 that is welded on the reinforcing cage 1, reinforcing cage 1 comprises advocated muscle 11 and the stirrup 12 that is bound on the muscle 11 of being advocated, cooperate shown in Figure 3, advocated the upper end of muscle 11 by being processed to form a thread segment 111, and matching thread section 111 connects a screw shell 13, stake top bracing means 2 comprises that a circular bearing plate 21 and vertical welding are in the reinforcement hoop 22 of bearing plate 21 peripheries, as shown in Figure 2, the position of the muscle 11 of being advocated of the reinforcing cage 1 of corresponding castinplace pile offers a plurality of preformed holes 211 on the bearing plate 21, the centre of bearing plate 21 is stayed and is established a cavity 212, is used for concreting.
Cooperate again Fig. 1 to shown in Figure 3, advocated in the utility model upper end of muscle 11 is carried out thread segment in factory and is processed, screw shell 13 and fixing with the muscle 11 of being advocated is installed, and advocated muscle 11 and stirrup 12 welding processing that screw shell 13 will be installed are made into reinforcing cage 1, finish the examination assembly unit of multistage reinforcing cage 1, stake top bracing means 2 after welding is good welds with reinforcing cage 1, an end that the muscle 11 of being advocated is provided with screw shell 13 is arranged in the preformed hole 211, the screw shell 13 of being advocated on the muscle is connected and fixed by weld seam 3 with the preformed hole 211 of bearing plate 21, the hole that forms at preformed hole 211 places of stake top bracing means 2 adopts fluid sealant 4 fillings closely knit, in case Concrete Leakage.
Reinforcing cage 1 is installed, carry out the cast-in-place pile concrete construction by cavity 212, reject pile crown and process after carry out a static loading test, test is finished, remove the fluid sealant 4 of screw shell 13 interior fillings and matching thread sleeve 13 install a bottom be provided with screw thread 51 after plant dowel 5, be connected with screw shell 13, carry out follow-up construction.
The utility model has reduced difficulty of construction, has improved construction precision, can provide a kind of On-site Welding Technology few, power transmission is clear and definite, the connected mode of convenient construction, the connected mode of this node both can be applicable to the Vertical Static Loading Test stake, the pulling resistant anchor pile that also can be applicable to uplift pile and utilize engineering pile to test simultaneously.This node has been simplified work progress, has accelerated construction speed, has wide promotion prospect for the processing of Vertical Static Loading Test pile head.

Claims (1)

1. a single-pile vertical orientation static loading test pile head steel bar connecting joints comprises reinforcing cage and the stake top bracing means that is welded on the reinforcing cage, it is characterized in that:
Described reinforcing cage comprise advocated muscle be bound in stirrup on the described muscle of being advocated, and the upper end of the described muscle of being advocated is processed to form a thread segment, and cooperates described thread segment to connect a screw shell;
Described stake top bracing means comprises a bearing plate and the reinforcement hoop that is welded on the described bearing plate, position according to the muscle of being advocated of the reinforcing cage of described castinplace pile on the described bearing plate offers a plurality of preformed holes, and the end that the described muscle of being advocated is provided with screw shell wears and is fixed in the described hole.
CN 201220527283 2012-10-15 2012-10-15 Single-pile vertical static test pile head steel bar connection node Expired - Fee Related CN202881986U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220527283 CN202881986U (en) 2012-10-15 2012-10-15 Single-pile vertical static test pile head steel bar connection node

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220527283 CN202881986U (en) 2012-10-15 2012-10-15 Single-pile vertical static test pile head steel bar connection node

Publications (1)

Publication Number Publication Date
CN202881986U true CN202881986U (en) 2013-04-17

Family

ID=48073427

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220527283 Expired - Fee Related CN202881986U (en) 2012-10-15 2012-10-15 Single-pile vertical static test pile head steel bar connection node

Country Status (1)

Country Link
CN (1) CN202881986U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102852167A (en) * 2012-10-15 2013-01-02 中国建筑第八工程局有限公司 Single-pile vertical static test pile head steel bar connection node and construction method thereof
RU2557277C1 (en) * 2014-05-29 2015-07-20 Федеральное государственное автономное образовательное учреждение высшего профессионального образования "Северный (Арктический) федеральный университет имени М.В. Ломоносова" (САФУ) Method for testing piles by static load
CN112323877A (en) * 2020-11-06 2021-02-05 江西省地质工程(集团)公司 One-time pouring construction method for static pressure test pile head of cast-in-situ bored pile

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102852167A (en) * 2012-10-15 2013-01-02 中国建筑第八工程局有限公司 Single-pile vertical static test pile head steel bar connection node and construction method thereof
CN102852167B (en) * 2012-10-15 2014-10-15 中国建筑第八工程局有限公司 Single-pile vertical static test pile head steel bar connection node and construction method thereof
RU2557277C1 (en) * 2014-05-29 2015-07-20 Федеральное государственное автономное образовательное учреждение высшего профессионального образования "Северный (Арктический) федеральный университет имени М.В. Ломоносова" (САФУ) Method for testing piles by static load
CN112323877A (en) * 2020-11-06 2021-02-05 江西省地质工程(集团)公司 One-time pouring construction method for static pressure test pile head of cast-in-situ bored pile

Similar Documents

Publication Publication Date Title
CN106381925A (en) Prefabricated reinforced concrete column and column splice joint with sleeves
CN205777098U (en) A kind of detachable assembling type concrete-filled circular steel tube column
CN2883468Y (en) Steel pipe segaments splicing joints of steel pipe concrete arches
CN206844314U (en) A kind of new prefabricated assembled bean column node
CN106381926A (en) Detachable assembly type splicing node for reinforced concrete columns
CN105201530A (en) Repairing and strengthening method for large cracks on rock tunnel lining
CN108412128A (en) A kind of connection structure of steel core concrete column
CN106337570A (en) The steel-tube grouting quick-stabilizing column structure and construction method
CN206144032U (en) Mosaic structure of assembled steel core concrete column and post
CN205712590U (en) A kind of fabricated shear wall and the attachment structure of Prefabricated concrete-filled steel tube post
CN106437032A (en) Assembled concrete filled steel tubular column splicing structure and method
CN202881986U (en) Single-pile vertical static test pile head steel bar connection node
CN103628571B (en) Beam-column joint for reverse construction method and construction method
CN201225015Y (en) Metallurgy large-scale underground tank construction formwork
CN206245471U (en) A kind of dismountable assembled steel reinforced concrete column splices node with post
CN206570955U (en) A kind of prefabricated post single hole provisions for grouting
CN102852167B (en) Single-pile vertical static test pile head steel bar connection node and construction method thereof
CN205188954U (en) Novel reinforced concrete prefabrication side stake pile extension structure
CN104196023B (en) A kind of using method of the concrete precast pipe pile pile top of band mechanical connecting device
CN206844316U (en) A kind of assembled steel reinforced concrete column with well and post splicing node
CN108240037A (en) Transverse joint connecting node between a kind of prefabricated board wall layers
CN108265856A (en) A kind of steel plate embedded part formula PC shear walls splice joint structure
CN203701087U (en) Prestressed concrete uplift pipe pile
CN209457142U (en) A kind of precast concrete composite beam and prefabricated column connected node
CN103103981A (en) Prestress wedge-shaped pipe pile joint technology and construction method thereof

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130417

Termination date: 20181015