CN202834382U - 一种适用于淤泥质粘土条件下的顶管机头 - Google Patents

一种适用于淤泥质粘土条件下的顶管机头 Download PDF

Info

Publication number
CN202834382U
CN202834382U CN 201220319002 CN201220319002U CN202834382U CN 202834382 U CN202834382 U CN 202834382U CN 201220319002 CN201220319002 CN 201220319002 CN 201220319002 U CN201220319002 U CN 201220319002U CN 202834382 U CN202834382 U CN 202834382U
Authority
CN
China
Prior art keywords
boss
condition
pipe
pipe pushing
clay
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201220319002
Other languages
English (en)
Inventor
张雪静
王猛
刘茂功
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinopec Oilfield Service Corp
Original Assignee
Shengli Oil Field Shengli Petroleum & Chemical Construction Corp
China Petroleum and Chemical Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shengli Oil Field Shengli Petroleum & Chemical Construction Corp, China Petroleum and Chemical Corp filed Critical Shengli Oil Field Shengli Petroleum & Chemical Construction Corp
Priority to CN 201220319002 priority Critical patent/CN202834382U/zh
Application granted granted Critical
Publication of CN202834382U publication Critical patent/CN202834382U/zh
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本实用新型提供一种适用于淤泥质粘土条件下的顶管机头,内侧分别设有凸台的刀头与支撑座构成套接结构,刀头的凸台与支撑座的凸台间设有若干个液压千斤顶,前支撑刀头,出土口由刀头上的凸台围成。所述出土口安装有格栅排列的钢制刀片,所述的套接为环形支撑座的前段位于刀头内侧的凸台的后部。本实用新型满足了地质情况差异的要求,确保了顶管施工精度及高效连续工作,可广泛应用于江南水网地区淤泥质粘土条件下的地下管道穿越铁路、道路、河流或建筑物等各种障碍物时顶管施工。

Description

一种适用于淤泥质粘土条件下的顶管机头
技术领域
本发明涉及一种工程施工中使用的顶管机头,具体涉及一种适用于淤泥 
质粘土条件下施工的顶管机头。
背景技术
江南水网地区地势低平,河湖密布,地下水位高,土质松软,传统的人工挖掘顶管,易造成套管顶部塌方事故,造成公路塌陷。根据土质特点,采用专用的机头,置于套管顶端,进行非开挖顶管施工,使用方便且可以有效防止塌方,并提高顶管施工的精度。 
发明内容
本实用新型的目的是提供一种使用方便、能有效防止塌方并提高顶管施工精度的适用于淤泥质粘土条件的顶管机头。 
本实用新型的目的可通过如下技术方案来实现:
内侧分别设有凸台的刀头与支撑座构成套接结构,刀头的凸台与支撑座的凸台间设有若干个液压千斤顶,前支撑刀头,出土口由刀头上的凸台围成。
本实用新型的目的还可通过如下技术方案来实现:
所述出土口安装有格栅排列的钢制刀片;所述的套接为环形支撑座的前段位于刀头内侧的凸台的后部。支撑座的凸台的后部环扣于混凝土套管上,出土口的大小和刀片数量可根据地质情况进行调节:当土质松软时可减少刀片数量,加大出土口,防止塌方;当土质较硬时可增加刀片数量,减小出洞土口,减小顶力;顶进过程中若发现土质变化,亦可以对刀片进行拆卸或加装。
本实用新型的有益效果是置于顶管前端进行顶管挖掘能防止人工挖掘顶管易塌方的缺点,出土口的刀片设计能够满足地质情况差异的要求,减少顶管施工过程中阻力,确保顶管施工精度及高效连续工作,可广泛应用于江南水网地区淤泥质粘土条件下的地下管道穿越铁路、道路、河流或建筑物等各种障碍物时顶管施工。
附图说明
图1是本实用新型实施例的应用状态示意图; 
    图2是本实用新型出土口截面图。
其中,1-刀头,2-支撑座,3-混凝土套管,4-液压千斤顶,5-出土口,6-刀片。
具体实施方式
下面结合附图对本实用新型的具体实施方式做进一步说明。 
根据图1和图2所示,顶管机头大小根据套管的口径制作。顶管施工时,将机头支撑座2后部环扣于混凝土套管3顶端,启动顶进装置开始顶进,机头被顶入土中,在压力的作用下,机头前端的土将被出土口5上的刀片6切削进入混凝土套管内。每个顶进行程完成后,由人工排净管内淤土,更换纵向顶铁,然后继续顶进,直到行程达到第一节混凝土套管3的长度时,吊装下一节混凝土套管,准备下一次顶进。
施工过程中可根据地勘报告和沉井下沉过程中了解到的土质情况,调整出土口5上安装的刀片6的数量。当土质松软时可减少刀片数量,加大出土口,防止塌方;当土质较硬时可增加刀片数量,减小出土口,减小顶力;顶进过程中若发现土质变化,亦可以对刀片进行拆卸或加装。由于土质不均匀,顶进过程中极易出现顶偏现象,每次顶进完成并清理完淤土后,采用激光经纬仪校验顶进的轴向偏差,并通过调液压千斤顶4调整顶进方向,保证顶管的施工精度。

Claims (1)

1.一种适用于淤泥质粘土条件下的顶管机头,其特征在于内侧分别设有凸台的刀头(1)与支撑座(2)构成套接结构,刀头(1)的凸台与支撑座(2)的凸台间设有若干个液压千斤顶(4),前支撑刀头(1),出土口(5)由刀头(1)上的凸台围成。
2.根据权利要求1所述的一种适用于淤泥质粘土条件下的顶管机头,其特征在于所述出土口(5)安装有格栅排列的钢制刀片(6)。
3.根据权利要求1所述的一种适用于淤泥质粘土条件下的顶管机头,其特征在于所述的套接为环形支撑座(2)的前段位于刀头(1)内侧的凸台的后部。
CN 201220319002 2012-07-02 2012-07-02 一种适用于淤泥质粘土条件下的顶管机头 Expired - Lifetime CN202834382U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220319002 CN202834382U (zh) 2012-07-02 2012-07-02 一种适用于淤泥质粘土条件下的顶管机头

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220319002 CN202834382U (zh) 2012-07-02 2012-07-02 一种适用于淤泥质粘土条件下的顶管机头

Publications (1)

Publication Number Publication Date
CN202834382U true CN202834382U (zh) 2013-03-27

Family

ID=47946090

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220319002 Expired - Lifetime CN202834382U (zh) 2012-07-02 2012-07-02 一种适用于淤泥质粘土条件下的顶管机头

Country Status (1)

Country Link
CN (1) CN202834382U (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103883796A (zh) * 2014-04-07 2014-06-25 葛洲坝集团第一工程有限公司 泥砂淤泥区手掘式顶管施工装置及方法
CN104344074A (zh) * 2014-09-17 2015-02-11 辽河石油勘探局 格栅顶冲装置
CN108386608A (zh) * 2018-05-02 2018-08-10 广东中科华冉智网科技有限公司 小管径塑料排水管顶管机具及塑料排水管顶管施工方法
CN108662281A (zh) * 2018-05-31 2018-10-16 成都金玉雄辉建筑工程有限公司 顶管装置及顶管施工方法
CN111577975A (zh) * 2020-05-25 2020-08-25 四川石油天然气建设工程有限责任公司 减小夯管管壁阻力的夯进设备及其夯进施工工艺

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103883796A (zh) * 2014-04-07 2014-06-25 葛洲坝集团第一工程有限公司 泥砂淤泥区手掘式顶管施工装置及方法
CN103883796B (zh) * 2014-04-07 2015-12-02 葛洲坝集团第一工程有限公司 泥砂淤泥区手掘式顶管施工装置及方法
CN104344074A (zh) * 2014-09-17 2015-02-11 辽河石油勘探局 格栅顶冲装置
CN108386608A (zh) * 2018-05-02 2018-08-10 广东中科华冉智网科技有限公司 小管径塑料排水管顶管机具及塑料排水管顶管施工方法
CN108386608B (zh) * 2018-05-02 2023-06-16 中国瑞林工程技术股份有限公司东莞分公司 小管径塑料排水管顶管机具及塑料排水管顶管施工方法
CN108662281A (zh) * 2018-05-31 2018-10-16 成都金玉雄辉建筑工程有限公司 顶管装置及顶管施工方法
CN108662281B (zh) * 2018-05-31 2020-07-07 成都金玉雄辉建筑工程有限公司 顶管装置及顶管施工方法
CN111577975A (zh) * 2020-05-25 2020-08-25 四川石油天然气建设工程有限责任公司 减小夯管管壁阻力的夯进设备及其夯进施工工艺
CN111577975B (zh) * 2020-05-25 2021-12-03 四川石油天然气建设工程有限责任公司 减小夯管管壁阻力的夯进设备及其夯进施工工艺

Similar Documents

Publication Publication Date Title
CN202834382U (zh) 一种适用于淤泥质粘土条件下的顶管机头
CN103924602B (zh) 深厚软土基坑施工方法
CN103321244B (zh) 砂土地基既有建筑增设地下室的施工方法
CN104389315B (zh) 固结灌浆钻孔桩墙及其施工方法
CN204199335U (zh) 一种减小phc管桩施工挤土效应的泄压井
CN103046931A (zh) 一种竖井/导井冲击式钻机冲击成孔施工方法
CN104747202A (zh) 矩形顶管机的多刀盘组合式切削系统
CN204139199U (zh) 用于场地平整的挡护结构
CN203755301U (zh) 耐抗力螺旋地桩
CN205857173U (zh) 一种应用在水上灌注桩的新型钢护筒护套
CN205502063U (zh) 一种复合式支挡结构
CN203271620U (zh) 一种组合型钻杆
CN105803957B (zh) 一种箱涵顶进装置及箱涵顶进方法
CN204920798U (zh) 一种可收张式两翼扩孔钻头
CN102535452A (zh) 一种新型工程桩
CN201078234Y (zh) 立井施工过流砂层的整体液压钢板桩帷幕
CN202706049U (zh) 一种钢筋混凝土水池沉井
CN102493436A (zh) 矩形抗滑桩人工掘进新工法
CN109944251A (zh) 软质岩层钢板桩打入的引孔施工方法
CN205134332U (zh) 市政排水管线坑槽支护结构
CN204591141U (zh) 一种钻孔扩底结构
CN204532359U (zh) 矩形顶管机的多刀盘组合式切削系统
CN208294522U (zh) 一种富水砂卵石地层的导洞内截水帷幕
CN202945681U (zh) 一种基槽自动挡板
CN205907735U (zh) 梯形水沟一次性开挖成型斗子

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: SINOPEC OILFIELD SERVICE CORPORATION

Free format text: FORMER OWNER: SHENGLI PETRO-CHEMICAL BUILDING CO LTD, SHANGLI OIL FIELD

Effective date: 20150906

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20150906

Address after: 100728 Beijing, Chaoyangmen, North Street, No. 22, No.

Patentee after: CHINA PETROLEUM & CHEMICAL Corp.

Patentee after: SINOPEC OILFIELD SERVICE Corp.

Address before: 100728 Beijing, Chaoyangmen, North Street, No. 22, No.

Patentee before: CHINA PETROLEUM & CHEMICAL Corp.

Patentee before: SHENGLI OIL FIELD SHENGLI PETROLEUM & CHEMICAL CONSTRUCTION Corp.

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20130327