CN202756354U - Centering device of large-scale mining structure for installing horizontal piece and vertical piece - Google Patents

Centering device of large-scale mining structure for installing horizontal piece and vertical piece Download PDF

Info

Publication number
CN202756354U
CN202756354U CN 201220317333 CN201220317333U CN202756354U CN 202756354 U CN202756354 U CN 202756354U CN 201220317333 CN201220317333 CN 201220317333 CN 201220317333 U CN201220317333 U CN 201220317333U CN 202756354 U CN202756354 U CN 202756354U
Authority
CN
China
Prior art keywords
sheet
vertical
piece
scale mining
centering device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201220317333
Other languages
Chinese (zh)
Inventor
代春阳
卿文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN BMESC OCEAN ENGINEERING Co Ltd
Original Assignee
TIANJIN BMESC OCEAN ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN BMESC OCEAN ENGINEERING Co Ltd filed Critical TIANJIN BMESC OCEAN ENGINEERING Co Ltd
Priority to CN 201220317333 priority Critical patent/CN202756354U/en
Application granted granted Critical
Publication of CN202756354U publication Critical patent/CN202756354U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model discloses a centering device of a large-scale mining structure for installing a horizontal piece and a vertical piece. The centering device of the large-scale mining structure for installing the horizontal piece and the vertical piece comprises a cone-shaped positioning pin, a cone-shaped positioning pin hole and bolts, wherein the cone-shaped positioning pin is arranged in the middle of a butt joint structure of the horizontal piece, the one-shaped positioning pin hole is arranged in the station of the corresponding butt joint structure of the vertical piece and is capable of inserting to and matching with the cone-shaped positioning pin, the butt joint structure of the horizontal piece is connected with the corresponding butt joint structure of the vertical piece through a plurality of bolts. When the centering device of the large-scale mining structure for installing the horizontal piece and the vertical piece is used for the overall installation of the structure, only the pin is needed to be inserted into the pin hole so as to achieve the fast connection of the two structures and improve the overall installation efficiency of the structure.

Description

Large-scale Mining Structure is installed transverse sheet and vertical sheet centralising device
Technical field
The utility model relates to Mining Structure transverse sheet and vertical sheet centralising device is installed.
Background technique
Mining Structure is installed and is often adopted the burst mounting type, at build the side transverse sheet and vertical sheet are built respectively, assemble to the scene, particularly as places such as collieries, be subject to electric spark impact larger, need not electricly weld at the scene as far as possible, structure burst installation all mode with bolts is carried out, traditional orientation type adopts bolt directly to locate, because each structure chip size is larger, weight reaches tens tons, in the bolt installation process, be difficult to quick location, therefore, how to locate fast is the key that improves the structure collectivity installation efficiency.Traditional mode of transverse sheet and vertical sheet process is installed as shown in Figures 1 to 4, using first crane will found sheet 2 sets, that sheet below the transverse sheet 1 is sling, with the screw on the screw aligning transverse sheet docking structure 4 on the vertical sheet docking structure 3, and connect with bolt and nut, treat that lower floor's transverse sheet structure is connected with vertical chip architecture complete, use the same method the transverse sheet structure on upper strata is installed.Because each structure chip size is larger, weight reaches tens tons, be difficult to locate fast, so this kind method efficient is low.
Summary of the invention
The purpose of this utility model is to overcome the shortcoming of prior art, provides a kind of large-scale Mining Structure that can improve the overall installation efficient of structure that transverse sheet and vertical sheet centralising device are installed.
Large-scale Mining Structure is installed transverse sheet and vertical sheet centralising device, it comprises a conical location pin that is arranged on transverse sheet docking structure neutral position, arrange one in the vertical corresponding docking structure position of sheet and can plug together the conical positioning pin hole that cooperates with described conical location pin, the described transverse sheet docking structure docking structure corresponding with vertical sheet links to each other by a plurality of bolts.
Adopt this device when structure collectivity is installed, only need pin to insert the quick connection that pin-and-hole can be realized two structures, can improve the overall installation efficient of structure.
Description of drawings
Fig. 1 is the plan view of transverse sheet before improving and vertical sheet linkage structure;
Fig. 2 is the plan view of transverse sheet before improving and vertical sheet linkage structure;
Fig. 3 is that structure shown in Figure 2 is at the partial enlarged drawing at A place;
Fig. 4 is the plan view of vertical chip architecture before improving;
Fig. 5 is the plan view that large-scale Mining Structure of the present utility model is installed transverse sheet and vertical sheet linkage structure in transverse sheet and the vertical sheet centralising device;
Fig. 6 is the plan view of structure shown in Figure 5;
Fig. 7 is that structure shown in Figure 6 is at the partial enlarged drawing at B place;
Fig. 8 is the plan view that large-scale Mining Structure of the present utility model is installed transverse sheet and vertical sheet centralising device.
Embodiment
Device of the present utility model such as Fig. 5 are to shown in Figure 8, large-scale Mining Structure of the present utility model is installed transverse sheet and vertical sheet centralising device, it comprises a conical location pin that is arranged on transverse sheet docking structure 3 neutral positions, arrange one in the vertical corresponding docking structure position of sheet and can plug together the conical positioning pin hole that cooperates with described conical location pin, the described transverse sheet docking structure docking structure corresponding with vertical sheet links to each other by a plurality of bolts.
When structure collectivity is installed, use crane that following transverse sheet is sling, the taper shape location pin 6 of transverse sheet docking structure is inserted the conical positioning pin hole 7 of corresponding vertical sheet docking structure, realize the quick location of two structures, connect 5 with the quick mounting bolt and nut, improve the overall installation efficient of structure.When structure collectivity is installed, only need pin to insert the quick connection that pin-and-hole can be realized two structures, to improve the overall installation efficient of structure.

Claims (1)

1. large-scale Mining Structure is installed transverse sheet and vertical sheet centralising device, it is characterized in that: it comprises a conical location pin that is arranged on transverse sheet docking structure neutral position, arrange one in the vertical corresponding docking structure position of sheet and can plug together the conical positioning pin hole that cooperates with described conical location pin, the described transverse sheet docking structure docking structure corresponding with vertical sheet links to each other by a plurality of bolts.
CN 201220317333 2012-07-03 2012-07-03 Centering device of large-scale mining structure for installing horizontal piece and vertical piece Expired - Lifetime CN202756354U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220317333 CN202756354U (en) 2012-07-03 2012-07-03 Centering device of large-scale mining structure for installing horizontal piece and vertical piece

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220317333 CN202756354U (en) 2012-07-03 2012-07-03 Centering device of large-scale mining structure for installing horizontal piece and vertical piece

Publications (1)

Publication Number Publication Date
CN202756354U true CN202756354U (en) 2013-02-27

Family

ID=47735539

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220317333 Expired - Lifetime CN202756354U (en) 2012-07-03 2012-07-03 Centering device of large-scale mining structure for installing horizontal piece and vertical piece

Country Status (1)

Country Link
CN (1) CN202756354U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103793569B (en) * 2014-01-28 2016-11-16 博迈科海洋工程股份有限公司 The segmentation docking calculation of large hydraulic natural gas storage conveyor module

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103793569B (en) * 2014-01-28 2016-11-16 博迈科海洋工程股份有限公司 The segmentation docking calculation of large hydraulic natural gas storage conveyor module

Similar Documents

Publication Publication Date Title
CN202012135U (en) Connecting piece for building and building structure system applying the connecting piece thereof
CN103938663A (en) Correction device of inclined power transmission tower made of signal-splicing steel angle principal material
CN203967521U (en) A kind of multifunctional frame frame connector
CN202756354U (en) Centering device of large-scale mining structure for installing horizontal piece and vertical piece
CN201777781U (en) Flange suspension apparatus
CN202726351U (en) Special fixture for assembling shell
CN201433059Y (en) Device for plugging and unplugging long pin shaft between main platform and mast in crane
CN203983518U (en) Substation equipment ground structure
CN202861686U (en) Non-prestressed solid square pile reinforcement framework seam welder main reinforcement clamping mechanism
CN203960920U (en) Colliery minery electric power pylon inclination adjusting device
CN202726365U (en) Connecting lug installing and welding device for rack section of derrick
CN204211397U (en) Assembly type standard knot
CN203835010U (en) Safe electric pole
CN201953137U (en) Vertical assembly alignment device on construction site of sectional tower equipment
CN203248931U (en) Deviation rectifying device for built-in foundation bolt in lines and rows
CN203669362U (en) Connecting device for connecting main truss of bailey frame and jacking stand column
CN203051345U (en) Column and arch connection part of multi-span greenhouse
CN204139163U (en) Prestressed concrete pipe pile bayonet socket block formula fast joint structure
CN204826688U (en) Novel net shell promotes pylon
CN203834502U (en) Rapid type assembling foundation based on two balance weight modules
CN202755987U (en) Connecting and improving structure for horizontal pieces and vertical pieces of large-scale mining module
CN203932337U (en) A kind of grounding pin
CN203262469U (en) Umbrella pin connection structure
CN202483191U (en) Auxiliary tool for producing tower body platform
CN203521962U (en) Connector used for connecting transformer station large-scale device pedestal and chain block

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20130227

CX01 Expiry of patent term