CN202755005U - Iron making blast furnace production monitoring alarm system - Google Patents

Iron making blast furnace production monitoring alarm system Download PDF

Info

Publication number
CN202755005U
CN202755005U CN 201220255760 CN201220255760U CN202755005U CN 202755005 U CN202755005 U CN 202755005U CN 201220255760 CN201220255760 CN 201220255760 CN 201220255760 U CN201220255760 U CN 201220255760U CN 202755005 U CN202755005 U CN 202755005U
Authority
CN
China
Prior art keywords
data
module
blast furnace
platform
alarm
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201220255760
Other languages
Chinese (zh)
Inventor
陈树军
祁海龙
张永恒
宋涛
李鸿斌
蔡保旺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Iron and Steel Group Co Ltd Chengde Branch
Original Assignee
Hebei Iron and Steel Group Co Ltd Chengde Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Iron and Steel Group Co Ltd Chengde Branch filed Critical Hebei Iron and Steel Group Co Ltd Chengde Branch
Priority to CN 201220255760 priority Critical patent/CN202755005U/en
Application granted granted Critical
Publication of CN202755005U publication Critical patent/CN202755005U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model relates to an iron making blast furnace production monitoring alarm system and belongs to the technical field of blast furnace iron making production process control. The technical scheme includes that the system comprises an information center data module (1), an iron making production information monitoring platform (2) and a cell phone short message alarm platform (3), the information center data module is connected with the iron making production information monitoring platform, and the iron making production information monitoring platform is connected with the cell phone short message alarm platform. The iron making production information monitoring platform comprises a data acquiring module (4), a data analyzing module (5) and a data management module (6). The iron making blast furnace production monitoring alarm system has the advantages that the an automation monitoring program is set, the automatic monitoring can be performed for blast furnace production data at any time, each abnormal data can be detected by the monitoring program, the picture alarm and alarm by sending short messages to relevant managers are immediately performed, and the problem of poor monitoring caused by technological levels of blast furnace operators or other reasons is solved.

Description

A kind of iron-smelting blast furnace production monitoring warning
Technical field
The utility model relates to a kind of iron-smelting blast furnace production monitoring warning, belongs to blast furnace ironmaking production process control techniques field.
Background technology
From 20 century 70s, the technician in blast furnace ironmaking field has begun the automated control technology that the primary study blast furnace is produced, but because this technology relates to many-sided multidisciplinary synthesis research such as iron-smelting process technology, computer information technology, automatic control technology and mathematical modeling technique, technical difficulty is large, and therefore blast furnace ironmaking production process fully automated does not reach gratifying degree yet so far.The utility model patent of Capital Iron ﹠ Steel General Co and University of Science ﹠ Technology, Beijing's co-applications: " Computerized blast furnace smelting expert system " (number of patent application is 93108671.X), it is a kind of method of comprehensive control blast furnace process, image data from the blast furnace sensor, according to expert's experience and knowledge and the database of fuzzy relation matrix formation, data to online collection compare, smooth state and the hot state of reasoning, judgement blast furnace state, furnace run, the result realizes the blast furnace process regulation and control according to weather report.At present, the weak point of background technology is its degree that combines with blast furnace technology characteristics complicated and changeable undertighten that still seems, can not allow in time all affected members recognize the abnormal conditions of blast furnace technology parameter, the needs of progress and the lean production of current smelting technology be can not further adapt to, its execution and application affected.
The utility model content
The utility model purpose provides a kind of iron-smelting blast furnace production monitoring warning, helps blast furnace operation technology personnel and managerial personnel that the changes in process parameters of blast furnace is carried out overall monitor and warning, solves the problems referred to above that background technology exists.
The technical solution of the utility model is:
A kind of iron-smelting blast furnace production monitoring warning, inclusion information centre data module, ironmaking production information monitoring platform and short message of mobile telephone for alarm platform, information center's data module is connected with ironmaking production information monitoring platform, and ironmaking production information monitoring platform is connected with the short message of mobile telephone for alarm platform.
Ironmaking production information monitoring platform comprises data acquisition module, data analysis module and data management module, data acquisition module is connected with breath centre data module, the output connection data analysis module of data acquisition module, the output connection data administration module of data analysis module, the output of data management module connects the short message of mobile telephone for alarm platform.
Information center's data module has contained all production data information in production scene, the data that the data acquisition module of ironmaking production information monitoring platform collects from information center's database, analyze by data analysis module, set the reference information of contrast in the data analysis module, by comparing with reference information, obtain alarm message and store entering data management module, data management module is controlled by the on-the-spot blast furnace operating personnel of computer picture alarm, data management module generates the mobile phone alarm information output simultaneously to mobile phone SMS alarm platform, alarming short message is sent on recipient's the mobile phone of setting.
The action of short message of mobile telephone for alarm platform: comprise that MAS machine server gathers the data of alarm message transmission table in real time from ironmaking production information monitoring platform, when alarm message transmission table had new information, the MAS machine sent note to recipient's mobile phone of setting according to data message.
The data management module of ironmaking production information monitoring platform is used for storing the various information of ironmaking production information monitoring platform, and it comprises Information Monitoring storage table, Information Monitoring setting table, alarm message setting table, alarm message storage table, alarm message transmission table.
The data acquisition module of ironmaking production information monitoring platform is used for acquisition monitoring point data message, for example blast furnace air quantity, high furnace roof temperature, blast-melted analysis [S], blast furnace permeability index, blast-furnace cooled water temperature, blast furnace cooling stave temperature, blast furnace temperature etc.
The data analysis module of ironmaking production information monitoring platform is used for to the data analysis of acquisition module collection, generates alarm message and deposits alarm message storage table in.
The beneficial effects of the utility model are: owing to having set automatically-monitored program, can constantly carry out automatic monitoring to the blast furnace production data, each unusual data all can monitored program detect, and carry out immediately the picture warning and send SMS alarm to the related management personnel, solved because blast furnace operating personnel's state of the art or the monitoring problem not in place that other reasons causes.
Description of drawings
Fig. 1 is structural representation of the present utility model;
Among the figure: information center's data module 1, ironmaking production information monitoring platform 2, short message of mobile telephone for alarm platform 3, data acquisition module 4, data analysis module 5, data management module 6.
Embodiment
Below in conjunction with accompanying drawing, by embodiment the utility model is described further.
In an embodiment, a kind of iron-smelting blast furnace production monitoring warning, inclusion information centre data module 1, ironmaking production information monitoring platform 2 and short message of mobile telephone for alarm platform 3, information center's data module is connected with ironmaking production information monitoring platform, and ironmaking production information monitoring platform is connected with the short message of mobile telephone for alarm platform.
Ironmaking production information monitoring platform comprises data acquisition module 4, data analysis module 5 and data management module 6, data acquisition module is connected with breath centre data module, the output connection data analysis module of data acquisition module, the output connection data administration module of data analysis module, the output of data management module connects the short message of mobile telephone for alarm platform.
Embodiment more specifically:
Include certain blast furnace air quantity data message in manufacturing monitoring system, data acquisition module gathers this information from information center's data module in real time, and alarm message is set and set air quantity in the table less than 3800m 3Begin to carry out picture warning and SMS alarm during/min and remind site operation personnel and managerial personnel.When sometime, air quantity is 3790m 3/ min, this system alarm starts, and data acquisition module is with 3790m 3These data of/min are from information center's database collection and be stored in Information Monitoring storage table, and data analysis module is according to cold flow 3790m 3These data of/min with alarm message set in the table " air quantity is less than 3800m 3Beginning to carry out picture during/min reports to the police and SMS alarm " compare, satisfy alert if, " No. 5 cold blast flows are less than 3800m to produce an alarm message 3/ min, current cold flow numerical value is 3790m 3/ min " and deposit alarm message storage table in; this alarm message carries out the picture sound and light alarm by the picture alert program; remind the site operation personnel to take measures; this alarm message deposits in the alarm message transmission table simultaneously; MAS machine server is come this information acquisition; and this information is sent on related personnel's mobile phone, in time remind managerial personnel that this blast furnace condition of production is paid close attention.

Claims (2)

1. iron-smelting blast furnace production monitoring warning, it is characterized in that inclusion information centre data module (1), ironmaking production information monitoring platform (2) and short message of mobile telephone for alarm platform (3), information center's data module is connected with ironmaking production information monitoring platform, and ironmaking production information monitoring platform is connected with the short message of mobile telephone for alarm platform.
2. a kind of iron-smelting blast furnace production monitoring warning according to claim 1, it is characterized in that: described ironmaking production information monitoring platform comprises data acquisition module (4), data analysis module (5) and data management module (6), data acquisition module is connected with breath centre data module, the output connection data analysis module of data acquisition module, the output connection data administration module of data analysis module, the output of data management module connects the short message of mobile telephone for alarm platform.
CN 201220255760 2012-06-01 2012-06-01 Iron making blast furnace production monitoring alarm system Expired - Lifetime CN202755005U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220255760 CN202755005U (en) 2012-06-01 2012-06-01 Iron making blast furnace production monitoring alarm system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220255760 CN202755005U (en) 2012-06-01 2012-06-01 Iron making blast furnace production monitoring alarm system

Publications (1)

Publication Number Publication Date
CN202755005U true CN202755005U (en) 2013-02-27

Family

ID=47734196

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220255760 Expired - Lifetime CN202755005U (en) 2012-06-01 2012-06-01 Iron making blast furnace production monitoring alarm system

Country Status (1)

Country Link
CN (1) CN202755005U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105392904A (en) * 2013-07-29 2016-03-09 杰富意钢铁株式会社 Abnormality detection method and blast-furnace operation method
CN106636539A (en) * 2016-08-31 2017-05-10 江苏恒创软件有限公司 Steelmaking converter composition real-time warning apparatus and method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105392904A (en) * 2013-07-29 2016-03-09 杰富意钢铁株式会社 Abnormality detection method and blast-furnace operation method
US9799110B2 (en) 2013-07-29 2017-10-24 Jfe Steel Corporation Abnormality detection method and blast furnace operation method
CN106636539A (en) * 2016-08-31 2017-05-10 江苏恒创软件有限公司 Steelmaking converter composition real-time warning apparatus and method thereof

Similar Documents

Publication Publication Date Title
CN110244673A (en) A kind of metal material manufacturing enterprise equipment on-line monitoring and managing method and system
CN103198147B (en) The differentiation of automatic monitoring abnormal data and processing method
CN113450065A (en) Production operation management system and method for wind power plant
CN102324066A (en) Radar chart representation method for early warning and assessment index of power system
CN113469231A (en) Fault diagnosis method, fault diagnosis system, computer device, and storage medium
CN113970627A (en) Water quality monitoring and early warning method and system
CN202755005U (en) Iron making blast furnace production monitoring alarm system
CN112561238A (en) Pumped storage power station auxiliary equipment state health evaluation system and method
CN114067234A (en) Power grid digital twin body data embedding method and system
CN117274017A (en) Carbon emission monitoring system based on enterprise operation data
CN115049326A (en) Production management system and management method
CN202854576U (en) Automobile production line data management system
CN215340800U (en) Basin management system
CN116310121A (en) Digital twin system and method for slag skin of iron-making blast furnace
CN103361454A (en) Data-filtering-based method for judging blast furnace hanging
CN115760024A (en) Intelligent building management and control platform based on BIM
CN115393142A (en) Intelligent park management method and management platform
CN114462828A (en) Safety early warning supervision system for engineering construction and supervision method thereof
CN110262439B (en) Steelmaking process quality control method and system
CN112633704A (en) Engineering construction site quality management system and method
CN115222083A (en) Steelmaking centralized control system, method and medium based on industrial Internet
CN102830659B (en) Blast furnace data filtering method
CN112053077A (en) Substation equipment monitoring and inspection system and method
CN117078022B (en) Steel plant personnel risk early warning system and method based on multi-source data fusion
Rongrong et al. Application of intelligent safety supervision based on artificial intelligence technology

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant