CN202730152U - 一种板壁结合的炉腹用高炉铜冷却壁 - Google Patents
一种板壁结合的炉腹用高炉铜冷却壁 Download PDFInfo
- Publication number
- CN202730152U CN202730152U CN 201220339171 CN201220339171U CN202730152U CN 202730152 U CN202730152 U CN 202730152U CN 201220339171 CN201220339171 CN 201220339171 CN 201220339171 U CN201220339171 U CN 201220339171U CN 202730152 U CN202730152 U CN 202730152U
- Authority
- CN
- China
- Prior art keywords
- copper
- cooling
- bosh
- water
- cooling wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Furnace Housings, Linings, Walls, And Ceilings (AREA)
- Blast Furnaces (AREA)
Abstract
一种板壁结合的炉腹用高炉铜冷却壁,由铜冷却壁本体、装在铜冷却壁内的铜水冷管、铜水冷管的进水口及出水口、连接孔、铜冷却壁上的燕尾槽组成,其特征在于:在铜冷却壁内的铜水冷管的进水口下方设有增强铜水冷管。本实用新型通过在炉腹和炉缸冷却壁之间增加水平冷却的水管,使炉腹炉缸结合部的冷却面积能增加至少2倍,从而大大提高风口带冷却壁散热速度,进而利于该部位渣皮的快速凝结,保护炉腹部位免于渣铁的直接接触,延长该区域冷却壁寿命。
Description
技术领域
本实用新型涉及一种高炉冷却壁,具体属于具有软水密闭循环冷却系统的大型高炉炉腹使用的铜冷却壁。
背景技术
有研究表明,球墨铸铁劣化的主要原因是CO2的侵入,CO2与基体中石墨反应的开始温度点为709℃,温度越高,反应速度越快。高炉煤气中含有大约20%左右的CO2,冷却壁和CO2接触的机会是很多的,因此从理论上讲,为保证冷却壁安全可靠地工作,冷却壁的最高工作温度应低于709℃,不能长期超过770℃。
对于2500m3以上的大型高炉而言,高炉冷却壁工作环境最恶劣的位置在软融带以下部位(即高炉炉腹部位),该区域的炉内温度远远高于770℃,该区域温度约l100~l300℃,在风口附近甚至可达 l500℃以上,采用全冷却壁冷却的大型高炉,在开炉后10年左右,炉腹、炉身下部冷却壁破损率一般较高,有时会有高达60%的水管出问题,为了减少铸铁冷却壁破损,近年来在炉腹大多采用铜冷却壁进行冷却,如2001年1月刊登于宝钢技术上的“新型高炉冷却设备—铜冷却壁”,该文献中介绍了铜的导热系数是铸铁的10倍左右,故铜冷却壁冷却能力优越,但由于炉腹和炉缸交界处存在着结构的差异,是渣铁的易集聚区,即使如此仍不能保证炉腹铜冷却壁不出问题。
为了解决上述问题,目前国内外在提高炉腹冷却壁的冷却能力方面主要做了两方面的工作,一方面将冷却壁材质由铸铁转换为铜质(轧制或者铸造),另一方面通过改进冷却壁结构,加长冷却壁长度,在炉腹下部增加凸台来增强对炉腹炉缸结合处的冷却,但这些改进相对于恶劣的炉腹工作环境恶言,取得了一定的效果,但炉腹炉缸结合部仍显冷却能力不足,并不能遏制炉腹冷却壁的破损。
实用新型内容
本实用新型的目的在于提供一种能通过改变增强铜水冷管的形状,使增强铜水冷管与铜冷却壁的热交换面积增加,而进一步增强冷却效果,进而提高高炉炉腹冷却壁的使用寿命的一种冷却效果良好的板壁结合的炉腹用高炉铜冷却壁。
实现上述目的的技术措施:
一种板壁结合的炉腹用高炉铜冷却壁,由铜冷却壁本体、装在铜冷却壁内的铜水冷管、铜水冷管的进水口及出水口、连接孔、铜冷却壁上的燕尾槽组成,其在于:在铜冷却壁内的铜水冷管的进水口下方设有增强铜水冷管。
本实用新型的特点在于:通过在炉腹和炉缸冷却壁之间增加一排水平冷却的水管,使炉腹炉缸结合部的冷却面积能增加至少2倍,从而大大提高风口带冷却壁散热速度,进而利于该部位渣皮的快速凝结,保护炉腹部位免于渣铁的直接接触,延长该区域冷却壁寿命。
附图说明
图1为本实用新型的结构示意图
图2为图1的A向结构示意图
图中:1—铜冷却壁本体,2—铜水冷管, 3—进水口,4—出水口,5—连接孔,6—燕尾槽,7—增强铜水冷管。
具体实施方式
下面结合附图做进一步描述:
一种板壁结合的炉腹用高炉铜冷却壁,由铜冷却壁本体1、装在铜冷却壁1内的铜水冷管2、铜水冷管2的进水口3及出水口4、连接孔5、铜冷却壁上的燕尾槽6组成。其在铜冷却壁1内的铜水冷管2的进水口3下方埋设有增强铜水冷管7,增强铜水冷管7也可以同铜水冷管2整体铸造。
由于增强铜水冷管7的设置,扩大了对铜冷却壁本体1的冷却面积,从而有效保证了炉腹部位免于渣铁的直接接触,使冷却壁寿命得以提高。
Claims (1)
1.一种板壁结合的炉腹用高炉铜冷却壁,由铜冷却壁本体、装在铜冷却壁内的铜水冷管、铜水冷管的进水口及出水口、连接孔、铜冷却壁上的燕尾槽组成,其特征在于:在铜冷却壁内的铜水冷管的进水口下方设有增强铜水冷管。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220339171 CN202730152U (zh) | 2012-07-13 | 2012-07-13 | 一种板壁结合的炉腹用高炉铜冷却壁 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220339171 CN202730152U (zh) | 2012-07-13 | 2012-07-13 | 一种板壁结合的炉腹用高炉铜冷却壁 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202730152U true CN202730152U (zh) | 2013-02-13 |
Family
ID=47655869
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201220339171 Expired - Fee Related CN202730152U (zh) | 2012-07-13 | 2012-07-13 | 一种板壁结合的炉腹用高炉铜冷却壁 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202730152U (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104677113A (zh) * | 2015-03-16 | 2015-06-03 | 湖南水口山有色金属集团有限公司 | 一种侧吹炉及其水套 |
CN108315518A (zh) * | 2018-03-30 | 2018-07-24 | 湖州虹君机械有限公司 | 铜制冷却装置 |
CN108315517A (zh) * | 2018-03-30 | 2018-07-24 | 湖州虹君机械有限公司 | 铜制快速冷却装置 |
CN109468421A (zh) * | 2019-01-10 | 2019-03-15 | 中冶华天工程技术有限公司 | 一种水平交错可调式高炉软水冷却系统 |
-
2012
- 2012-07-13 CN CN 201220339171 patent/CN202730152U/zh not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104677113A (zh) * | 2015-03-16 | 2015-06-03 | 湖南水口山有色金属集团有限公司 | 一种侧吹炉及其水套 |
CN108315518A (zh) * | 2018-03-30 | 2018-07-24 | 湖州虹君机械有限公司 | 铜制冷却装置 |
CN108315517A (zh) * | 2018-03-30 | 2018-07-24 | 湖州虹君机械有限公司 | 铜制快速冷却装置 |
CN109468421A (zh) * | 2019-01-10 | 2019-03-15 | 中冶华天工程技术有限公司 | 一种水平交错可调式高炉软水冷却系统 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202730152U (zh) | 一种板壁结合的炉腹用高炉铜冷却壁 | |
CN103468846B (zh) | 一种带有内嵌式水冷却系统的高炉出渣沟 | |
CN215209518U (zh) | 一种易挂渣的热面覆铜强冷铸铁冷却壁 | |
CN205205161U (zh) | 一种强化传热的高炉冷却壁 | |
CN202730153U (zh) | 一种冷却效果良好的板壁结合的炉腹用高炉铜冷却壁 | |
CN207002769U (zh) | 一种高炉冷却装置 | |
CN205576184U (zh) | 一种导热良好的高炉炉缸 | |
CN205077079U (zh) | 一种高炉炉腹用冷却壁 | |
CN207987279U (zh) | 一种转炉球形炉底结构 | |
CN201442956U (zh) | 带有空气冷却通道的高炉主铁沟 | |
CN201545856U (zh) | 带水冷的铸钢渣沟冷却器 | |
CN201942693U (zh) | 多层铸钢冷却壁 | |
CN207763491U (zh) | 一种熔炉炉底及熔炉 | |
CN206467259U (zh) | 一种高炉炉腹炉缸衔接部位冷却壁保护结构 | |
CN201501888U (zh) | 大型高炉冷却壁镶嵌石墨块 | |
CN202359181U (zh) | 一种底吹炼铅炉氧枪水冷装置 | |
CN201421266Y (zh) | 铸钢冷却板 | |
CN202808837U (zh) | 一种设有凸台的铜冷却壁 | |
CN207002770U (zh) | 一种装配式高炉冷却装置 | |
CN220116581U (zh) | 一种氧气底吹炉口保护铜水套 | |
CN2892875Y (zh) | 高炉炭质炉底冷却装置 | |
CN219709502U (zh) | 一种高炉用球墨铸铁镶铸铜新型冷却壁 | |
CN211170917U (zh) | 一种隔热性好的铝电解槽内衬 | |
CN210826388U (zh) | 一种铝电解槽用侧部内衬 | |
CN103017542B (zh) | 一种闪速炉复合陶瓷水冷铜套及其生产方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20170717 Address after: 430083, Gate No. 2, Qingshan District, Hubei, Wuhan Patentee after: Wuhan iron and Steel Company Limited Address before: 430080 Wuhan, Hubei Friendship Road, No. 999, Wuchang Patentee before: Wuhan Iron & Steel (Group) Corp. |
|
TR01 | Transfer of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20130213 Termination date: 20210713 |
|
CF01 | Termination of patent right due to non-payment of annual fee |