CN202706034U - Concrete spraying construction device - Google Patents

Concrete spraying construction device Download PDF

Info

Publication number
CN202706034U
CN202706034U CN 201220415254 CN201220415254U CN202706034U CN 202706034 U CN202706034 U CN 202706034U CN 201220415254 CN201220415254 CN 201220415254 CN 201220415254 U CN201220415254 U CN 201220415254U CN 202706034 U CN202706034 U CN 202706034U
Authority
CN
China
Prior art keywords
construction
concrete spraying
support
spraying
backstay
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220415254
Other languages
Chinese (zh)
Inventor
刘怀亮
黄静
汤用泉
黎学皓
郑梓扬
雷骊彪
朱云峰
李棉巧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Gezhouba Group Co Ltd
China Gezhouba Group No 1 Engineering Co Ltd
Original Assignee
China Gezhouba Group Co Ltd
China Gezhouba Group No 1 Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group Co Ltd, China Gezhouba Group No 1 Engineering Co Ltd filed Critical China Gezhouba Group Co Ltd
Priority to CN 201220415254 priority Critical patent/CN202706034U/en
Application granted granted Critical
Publication of CN202706034U publication Critical patent/CN202706034U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

A concrete spraying construction device comprises a support, a positioning rod is arranged on one side, close to a rock face, of the support, a guiding rod is movably connected with the positioning rod in an intersected mode through a hinged seat, a spray pipe used for concrete spraying is axially connected with the guiding rod in parallel, and a guiding rope is arranged on the guiding rod. The utility model provides the concrete spraying construction device and a method, by means of the structure and the method, safety of equipment and personnel under the condition of high risk in the process of concrete spraying support construction to an excavation face can be ensured. The concrete spraying construction device is an extremely important supplement for traditional manual spraying protection and mechanical spraying protection, overcomes the defect that the personnel and the equipment can not carry out safety construction, and safety risk in the process of concrete spraying construction is completed avoided. The concrete spraying construction device and the method are especially suitable for edge top arch spraying protection in the process of chamber excavation and preliminary sealed spraying protection when partial landslides happen, and fill in the blank of the concrete spraying construction method on the portions.

Description

The construction of shotcrete device
Technical field
The present invention relates to the construction of shotcrete field, particularly in the civil engineering open excavation, dangerous excavation face is carried out a kind of device and method of concrete spraying support behind excavation, particularly personnel and equipment can not guarantee that safe place carries out the just construction of shotcrete device of spray of loose rock face closure at cavern's roof, high side wall place etc.
Background technology
At present, the shotcrete construction method that extensively adopts is to adopt spray windlass mechanical injection concrete, employing manually to hold the jet pipe sprayed mortar.When adopting existing method and apparatus to side slope scar or cavern's sprayed mortar, spraying machinery or spray anchor worker need to be positioned at high slope or the following injection of crown scar, the broken scar that just has been excavated is swept in high-pressure blast or the punching of high energy concrete material, usually have a large amount of rocks to fly even the appearance of caving in, the Focal drug-block that causes thus, the situation of casualties constantly occur.
According to the national regulation regulation, protect effect and quality for guaranteeing spray, the sprayed mortar nozzle hole need to be controlled at 60 ~ 100cm to the distance of scar, and when that is to say with spray windlass sprayed mortar, the spray windlass is apart from scar 60 ~ 100cm; When adopting the Traditional Man sprayed mortar, the spray anchor worker who holds jet pipe is apart from the about 120 ~ 160cm of scar.Too closely or too far all can cause sprayed mortar off quality and stay larger potential safety hazard.This has limited the scope of activities of sprayed mortar jet pipe.Under this restriction, existing these two kinds of sprayed mortar methods are faced with the technical barrier that can't guarantee construction safety or have a strong impact on the duration in the high-risk excavation face situations such as Mass Near The Top of Underground Cavity.
Therefore, engineering circles need to be sought a kind of shotcrete construction method of locating the personnel that can eliminate or machine security hidden danger at high side wall scar place, Mass Near The Top of Underground Cavity etc.
Summary of the invention
Technical problem to be solved by this invention provides a kind of construction of shotcrete device, the terrain operation for jet pipe can be become far to operate, thus the potential safety hazard of elimination personnel and plant equipment; Further, structure is less demanding for equipment comparatively simply, so that site operation.
For solving the problems of the technologies described above, the technical solution adopted in the present invention is: a kind of construction of shotcrete device, comprise support, side near scar on the support is provided with backstay, guide peg intersects flexible connection by twisted seat and backstay, the jet pipe that is used for sprayed mortar is connected with the guide peg axially parallel, and guide peg is provided with guide rope.
Described twisted seat is the steel pipe moving fastening.
Described guide peg is positioned at backstay length before less than being positioned at backstay length afterwards.
Described guide rope front end is connected with the afterbody of guide peg.
Described guide rope is the 2-4 root, has at least two back side top from support to walk around.
A kind of method that adopts above-mentioned device to carry out construction of shotcrete may further comprise the steps:
One, support and backstay are set;
Two, jet pipe is connected with guide peg;
Three, guide peg is movably attached to backstay;
Four, guide rope is connected to the afterbody of guide peg;
Five, operating personnel are passing through the pulling guide rope away from the position of scar spray plane, and the sensing of traction jet pipe is protected to implement the spray of Mass Near The Top of Underground Cavity and spray plane;
Realize the safe construction of sprayed mortar by above-mentioned steps.
Described guide rope quantity can determine according to spray plane size, when spray plane is larger, can be with 3 ropes when needing on a large scale rotable nozzle, on the contrary can be less than 3.
Described guide rope has at least 2 back side top from support to walk around, when this guide rope of pulling, so that the afterbody of guide peg lifts.
Described flexible connection is to connect guide peg and backstay with the steel pipe moving fastening, so that guide peg can swing, and can backstay be that rotate in the center of circle.
A kind of construction of shotcrete device provided by the invention by adopting above-mentioned structure and method, has guaranteed under high-risk environment excavation face is carried out the safety of equipment and personnel in the concrete spraying support construction.Be a kind of epochmaking that Traditional Man spray is protected, mechanical spray protects replenished, it has remedied the deficiency that personnel, plant equipment can't safe constructions, and the security risk of traditional shotcrete construction process is avoided fully.Device and method of the present invention is particularly useful for that limit crown spray in the cavern excavation process is protected, the preliminary sealing spray during local landslide is protected, and has filled up the blank on these position shotcrete construction methods.
Description of drawings
The invention will be further described below in conjunction with drawings and Examples:
Fig. 1 is process flow diagram of the present invention.
Fig. 2 is that the master who installs among the present invention looks schematic diagram.
Fig. 3 is the schematic side view of installing among the present invention.
Among the figure: support 1, backstay 2, jet pipe 3, guide peg 4, guide rope 5, sprayed mortar 6, scar 7, spray regime line 8.
The specific embodiment
In Fig. 2,3, a kind of construction of shotcrete device comprises support 1, and the side near scar 7 on the support 1 is provided with backstay 2, and guide peg 4 is by twisted seat and backstay 2 activity interconnections.Described twisted seat is the common steel tube moving fastening, and namely universal card commonly used easily obtains at the construction field (site).
The jet pipe 3 that is used for sprayed mortar is connected with guide peg 4 axially parallels, and guide peg 4 is provided with guide rope 5.
Described guide peg 4 is positioned at backstay 2 length before less than being positioned at backstay 2 length afterwards.Described guide rope 5 front ends are connected with the afterbody of guide peg 4.
Described guide rope 5 is the 2-4 root, has at least two back side top from support 1 to walk around.By spurring these two guide ropes 5 so that lift at the rear portion of guide peg 4 and jet pipe 3, the rear portion of unclamping these two guide ropes, 5 guide pegs 4 and jet pipe 3 falls under Action of Gravity Field.
The job practices of utilizing this device to carry out sprayed mortar is described as follows.
In Fig. 1, a kind of method that adopts above-mentioned device to carry out construction of shotcrete may further comprise the steps:
One, support 1 and backstay 2 are set; Described support adopts rectangle support, and the upper end arranges backstay 2 near a side of scar 7.
Two, jet pipe 3 is connected with guide peg 4; Jet pipe 3 is connected with guide peg 4 colligations.
Three, guide peg 4 is movably attached to backstay 2;
Four, guide rope 5 is connected to the afterbody of guide peg 4; Being guide peg 4 intersects flexible connection by twisted seat and backstay 2.Described flexible connection is to connect guide peg 4 and backstay 2 with the steel pipe moving fastening, so that guide peg 4 can swing, and can be center of circle rotation by backstay 2.Adopting the steel pipe moving fastening to be beneficial at the construction field (site) obtains.
Five, operating personnel are passing through the pulling guide rope away from the position of scar 7 spray planes, and the sensing of traction jet pipe 3 is protected to implement the spray of Mass Near The Top of Underground Cavity and face.
Realize the safe construction of sprayed mortar by above-mentioned steps.
Described guide rope 5 quantity can determine according to spray plane size, when spray plane is larger, can be with 3 ropes when needing on a large scale rotable nozzle 3, on the contrary can be less than 3.
Described guide rope 5 has at least 2 back side top from support 1 to walk around, when this guide rope 5 of pulling, so that the afterbody of guide peg 4 lifts.

Claims (5)

1. construction of shotcrete device, comprise support (1), it is characterized in that: the upper side near scar (7) of support (1) is provided with backstay (2), guide peg (4) intersects flexible connection by twisted seat and backstay (2), the jet pipe (3) that is used for sprayed mortar is connected with guide peg (4) axially parallel, and guide peg (4) is provided with guide rope (5).
2. a kind of construction of shotcrete device according to claim 1, it is characterized in that: described twisted seat is the steel pipe moving fastening.
3. a kind of construction of shotcrete device according to claim 1, it is characterized in that: described guide peg (4) is positioned at backstay (2) length before less than being positioned at backstay (2) length afterwards.
4. a kind of construction of shotcrete device according to claim 1, it is characterized in that: described guide rope (5) front end is connected with the afterbody of guide peg (4).
5. a kind of construction of shotcrete device according to claim 4, it is characterized in that: described guide rope (5) is the 2-4 root, has at least two back side top from support (1) to walk around.
CN 201220415254 2012-08-21 2012-08-21 Concrete spraying construction device Expired - Fee Related CN202706034U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220415254 CN202706034U (en) 2012-08-21 2012-08-21 Concrete spraying construction device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220415254 CN202706034U (en) 2012-08-21 2012-08-21 Concrete spraying construction device

Publications (1)

Publication Number Publication Date
CN202706034U true CN202706034U (en) 2013-01-30

Family

ID=47586352

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220415254 Expired - Fee Related CN202706034U (en) 2012-08-21 2012-08-21 Concrete spraying construction device

Country Status (1)

Country Link
CN (1) CN202706034U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102817360A (en) * 2012-08-21 2012-12-12 中国葛洲坝集团国际工程有限公司 Concrete spraying construction device and method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102817360A (en) * 2012-08-21 2012-12-12 中国葛洲坝集团国际工程有限公司 Concrete spraying construction device and method
CN102817360B (en) * 2012-08-21 2015-04-08 中国葛洲坝集团国际工程有限公司 Concrete spraying construction device and method

Similar Documents

Publication Publication Date Title
CN108952796B (en) One kind being based on the antireflective modularization pumping method of pectination bottom plate layer-through drilling pressure break
CN102182472B (en) Backfill repairing method for tunnel collapse cavity
CN106761792A (en) A kind of full-sleeve full-rotation drill sleeve and shield cutter preceding object thing sweep-out method
CN105041322A (en) Method and system for reinforcing hole for push bench to go in and out
CN110469340A (en) A kind of rock burst tunnel double-shielded TBM card machine is got rid of poverty construction method
CN106679519A (en) Static blasting demolition method for interior reinforced concrete supports
CN108150187A (en) A kind of huge loose talus shield encircles the method into hole
CN205477660U (en) Little clean apart from tunnel in rock pillar reinforcerment system
CN202706034U (en) Concrete spraying construction device
CN102817360B (en) Concrete spraying construction device and method
CN111577311A (en) Construction process of cantilever type heading machine in soft rock tunnel
CN202767978U (en) Rotatable telescopic cutting device of comprehensive mechanical rock lane tunneling unit
CN102322263A (en) Roof cutting and pillar dilapidation method in goaf
CN202055850U (en) Full mechanized roadway remote end surface protective device
CN204570667U (en) Hand excavated pile aperture safety device
CN201459742U (en) Arch-shaped protection system
CN110500120A (en) A kind of tunnel large size landslide emergency immediate processing method
CN109578070A (en) Hole method is looked in a kind of filling borehole bottom
CN110030001A (en) A kind of construction method that mountain tunnel is appeared
CN209538196U (en) The structure of engineering slope and underground chamber excavation and support simultaneously in a kind of Toppling Deformation rock mass
CN110985017B (en) Construction method for shield tunneling of rainwater box culvert under expansive soil stratum
CN206860184U (en) A kind of full-sleeve full-rotation drill sleeve
Joass et al. Risk management and remediation of the north wall slip, West Angelas Mine, Western Australia
CN103422870A (en) Roof supporting method for full super-high seam mining
CN208251118U (en) Slope reinforcement device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant