CN202689005U - 边框架半逆作深基坑支护结构 - Google Patents
边框架半逆作深基坑支护结构 Download PDFInfo
- Publication number
- CN202689005U CN202689005U CN 201220167962 CN201220167962U CN202689005U CN 202689005 U CN202689005 U CN 202689005U CN 201220167962 CN201220167962 CN 201220167962 CN 201220167962 U CN201220167962 U CN 201220167962U CN 202689005 U CN202689005 U CN 202689005U
- Authority
- CN
- China
- Prior art keywords
- foundation pit
- bored pile
- steel
- supporting structure
- cast
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
边框架半逆作深基坑支护结构,包括钻孔灌注桩、止水帷幕、竖向构件、设置节点的钢筋混凝土横梁、楼板,所述竖向构件包括型钢格构柱和钢管混凝土柱,所述钻孔灌注桩和所述的止水帷幕设置在基坑内部的地下室外墙的外围,所述止水帷幕位于最外侧;所述钻孔灌注桩与所述的钢筋混凝土横梁通过灌注桩围檩固定;所述钻孔灌注桩、竖向构件通过所述的钢筋混凝土横梁的节点连接,形成门式边框架;所述的竖向构件与所述的钻孔灌注桩之间设置配筋砌体剪力墙或钢支撑,形成框架-剪力墙(钢支撑)结构。本实用新型有益效果:前期无需先施工全部地下室楼板,基坑内空旷、挖土方便;后期无需爆破拆撑;适合平面尺度大的深基坑工程,节省水平、竖向支撑立柱。
Description
技术领域
本实用新型涉及一种边框架半逆作深基坑支护结构,属于软土地区深基坑支护的设计与建造技术领域。
背景技术
目前,软土地区深基坑支护的常规技术方案主要分两大类,一类为采用止水帷幕+钻孔灌注桩支护体+钢筋混凝土(钢管)水平支撑的顺作法。另一类为采用地下连续墙支护体+结构楼面梁板水平支撑的逆作法。前者工程上应用广泛,受力合理,但支撑断面往往较大,后期施工地下室结构时还需要爆破拆除,不仅费钱费时,而且不绿色环保。后者在工程用地紧张,周边地下情况复杂区域应用较多,优点是支护结构刚度大,变形小,对周边场地影响小,支撑结构用后期工程楼板代替,减少浪费,缺点是支撑楼板的立柱数量多,构造复杂,大面积结构楼板先行施工,工程精度难以保证,全封闭楼板挖土出土困难,施工难度大。
发明内容
为了克服顺作法后期需要爆破拆撑,费钱费时的缺陷以及逆作法增加大量支撑和立柱,施工工艺复杂,挖土出土困难的不足,本实用新型提出一种新的软土地区深基坑支护的边框架半逆作施工方法,其特点是不需要后期爆破拆撑,亦不需要先行施工整个地下室楼板,既节省造价、绿色环保,又避免基坑挖土出土困难,施工难度的增加。
本实用新型所述的边框架半逆作深基坑支护结构,包括钻孔灌注桩、止水帷幕、竖向构件、设置节点的钢筋混凝土横梁、楼板,所述的竖向构件包括型钢格构柱和钢管混凝土柱,所述的钻孔灌注桩和所述的止水帷幕设置在基坑内部的地下室外墙的外围,且所述的止水帷幕位于最外侧;其特征在于:所述的钻孔灌注桩与所述的钢筋混凝土横梁通过灌注桩围檩固定;所述的钻孔灌注桩、竖向构件通过所述的钢筋混凝土横梁的节点连接,形成门式边框架;所述的竖向构件与所述的钻孔灌注桩之间设置配筋砌体剪力墙或钢支撑,形成框架-剪力墙(钢支撑)结构。
所述的竖向构件位于基坑内部沿地下室外墙周向的一至两跨范围内。
位于所述的外墙内部的所述的钢筋混凝土横梁和楼板设置垂直的止水片。
本实用新型的有益效果是:1)基坑内部仅靠近地下室外墙的一至两跨范围内有四周一圈裙边结构,裙边结构作为后期永久结构使用,不造成浪费;2)后期无爆破拆撑作业,绿色环保;3)特别适合平面尺度较大的深基坑工程,节省数量众多的水平支撑构件和竖向支撑立柱,经济效益明显;4)前期无需先行施工全部地下室结构楼板,基坑内部空旷,裙边结构楼板下的暗挖作业少,挖土出土方便;5)后期配筋砌体剪力墙(钢支撑)拆除简便可行。
附图说明
图1为本实用新型的平面图
图2为本实用新型的局部平面放大图
图3为本实用新型的A-A剖面图
图4为本实用新型的B-B剖面图
图5为本实用新型的节点连接放大图
图6是本实用新型所述的节点的1-1剖视图
具体实施方式
下面结合附图进一步说明本实用新型
参照附图:
实施例1
边框架半逆作深基坑支护结构,包括钻孔灌注桩1、止水帷幕2、竖向构件3、设置节点的钢筋混凝土横梁4、楼板5,所述的竖向构件3包括型钢格构柱31和钢管混凝土柱32,所述的钻孔灌注桩1和所述的止水帷幕2设置在基坑内部的地下室外墙6的外围,且所述的止水帷幕2位于最外侧;所述的钻孔灌注桩1与所述的钢筋混凝土横梁4通过灌注桩围檩11固定;所述的钻孔灌注桩1、竖向构件3通过所述的钢筋混凝土横梁4的节点连接,形成门式边框架;所述的竖向构件3与所述的钻孔灌注桩1之间设置配筋砌体剪力墙或钢支撑,形成框架-剪力墙(钢支撑)。
所述的竖向构件3位于基坑内部沿地下室外墙6周向的一至两跨范围内。
位于所述的外墙6内部的所述的钢筋混凝土横梁4和楼板5设置垂直的止水片321。
实施例2
以三层地下室为例,本实用新型的具体构建过程如下,第一步,施工基坑外围钻孔灌注桩与止水帷幕,以及紧靠地下室外墙的一至两跨竖向构件(包括钢管混凝土柱与临时型钢格构柱)的灌注桩,并在灌注桩内插入钢管和型钢,在钢管内浇灌混凝土形成钢管混凝土柱,同时施工降水井;第二步,施工外围灌注桩顶的围檩和边框架范围内的地下室负一层顶板结构梁板;第三步,开挖土方至负二层顶板,施工第二道灌注桩围檩和边框架范围内的地下室负二层顶板结构梁板以及边框架内的配筋砌体剪力墙(钢支撑);第四步,开挖土方至负三层顶板,施工第三道灌注桩围檩和边框架范围内的地下室负三层顶板结构梁板以及边框架内的配筋砌体剪力墙(钢支撑);第五步,开挖土方至基坑底,浇筑承台和底板;第六步,自下而上的施工地下室外墙和基坑内其余地下室主体结构;第七步,拆除临时型钢格构支撑立柱和配筋砌体剪力墙(钢支撑),完成地下室外围土体回填。
本说明书实施例所述的内容仅仅是对实用新型构思的实现形式的列举,本实用新型的保护范围的不应当被视为仅限于实施例所陈述的具体形式,本实用新型的保护范围也及于本领域技术人员根据本实用新型构思所能够想到的等同技术手段。
Claims (3)
1.边框架半逆作深基坑支护结构,包括钻孔灌注桩、止水帷幕、竖向构件、设置节点的钢筋混凝土横梁、楼板,所述的竖向构件包括型钢格构柱和钢管混凝土柱,所述的钻孔灌注桩和所述的止水帷幕设置在基坑内部的地下室外墙的外围,且所述的止水帷幕位于最外侧;其特征在于:所述的钻孔灌注桩与所述的钢筋混凝土横梁通过灌注桩围檩固定;所述的钻孔灌注桩、竖向构件通过所述的钢筋混凝土横梁的节点连接,形成门式边框架;所述的竖向构件与所述的钻孔灌注桩之间设置配筋砌体剪力墙或钢支撑,形成框架-剪力墙结构。
2.如权利要求1所述的边框架半逆作深基坑支护结构,其特征在于:所述的竖向构件位于基坑内部沿地下室外墙周向的一至两跨范围内。
3.如权利要求2所述的边框架半逆作深基坑支护结构,其特征在于:位于所述的外墙内部的所述的钢筋混凝土横梁和楼板设置垂直的止水片。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220167962 CN202689005U (zh) | 2012-04-19 | 2012-04-19 | 边框架半逆作深基坑支护结构 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220167962 CN202689005U (zh) | 2012-04-19 | 2012-04-19 | 边框架半逆作深基坑支护结构 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202689005U true CN202689005U (zh) | 2013-01-23 |
Family
ID=47544645
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201220167962 Expired - Lifetime CN202689005U (zh) | 2012-04-19 | 2012-04-19 | 边框架半逆作深基坑支护结构 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202689005U (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102650133A (zh) * | 2012-04-19 | 2012-08-29 | 苏州工业园区设计研究院股份有限公司 | 边框架半逆作深基坑支护结构的构建方法及其构建物 |
CN103243720A (zh) * | 2013-05-20 | 2013-08-14 | 中冶天工集团有限公司 | 软土地基超深基坑支护方法 |
-
2012
- 2012-04-19 CN CN 201220167962 patent/CN202689005U/zh not_active Expired - Lifetime
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102650133A (zh) * | 2012-04-19 | 2012-08-29 | 苏州工业园区设计研究院股份有限公司 | 边框架半逆作深基坑支护结构的构建方法及其构建物 |
CN103243720A (zh) * | 2013-05-20 | 2013-08-14 | 中冶天工集团有限公司 | 软土地基超深基坑支护方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107664035B (zh) | 盾构管廊先盾后井的施工方法 | |
CN108278116B (zh) | 一种浅埋大跨度管幕支护体系及其施工方法 | |
CN102182325A (zh) | 一种框架结构独立基础既有建筑物地下室增层方法 | |
CN105736001A (zh) | 一种采用预制构件建造地铁车站的施工方法 | |
CN105155549A (zh) | 一种大面积深基坑分区顺逆工况下的支撑体系及施工方法 | |
CN207063982U (zh) | 一种导洞内机械辅助止水暗挖车站结构 | |
CN102650133A (zh) | 边框架半逆作深基坑支护结构的构建方法及其构建物 | |
CN103104102B (zh) | 一种地下增层改造施工方法 | |
KR20140055639A (ko) | 흙막이 겸용 건축빔 구조체의 시공방법 및 그 방법에 의하여 시공된 건축빔 구조체 | |
CN109024662A (zh) | 锚杆静压桩托换无地下室建筑地下空间增层的方法 | |
CN112982481B (zh) | 一种管廊上跨地铁交叉节点处的结构施工方法 | |
CN102410031B (zh) | 桩墙法建造地下空间结构 | |
CN104652444B (zh) | 超大型深基坑中心岛式交替土方开挖的整体逆作施工方法 | |
CN110886507B (zh) | 一种既有建筑下方增层扩建的方法 | |
CN105649094A (zh) | 一种深水基础承台施工用三壁钢围堰及其施工方法 | |
CN105064711A (zh) | 一种在居民楼间施工地下车库的方法 | |
CN101498133B (zh) | 增大地下室逆作法土方开挖空间的方法和支护结构 | |
CN202689005U (zh) | 边框架半逆作深基坑支护结构 | |
CN101161947A (zh) | 一种用于基坑支护的护壁桩与降水井合一的方法 | |
CN203530958U (zh) | 一种薄壁预制叠合混凝土地下连续墙 | |
CN110607800A (zh) | 一种可周转式钢制沉井支护装置及其施工方法 | |
CN210459300U (zh) | 一种盖挖车站的围护结构 | |
KR100926323B1 (ko) | 소구경 강관을 이용한 지하 증축 공법 | |
CN107313434A (zh) | 一种深基坑地下油库及其施工方法 | |
CN209760299U (zh) | 一种避免房屋拆迁的明暗挖结合地铁车站结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C56 | Change in the name or address of the patentee | ||
CP03 | Change of name, title or address |
Address after: Suzhou City, Jiangsu province 215028 Industrial Park Suzhou Bada Street No. 111 Patentee after: ARTS GROUP CO., LTD. Address before: 215000 No. 168 Pu Pu Road, Suzhou Industrial Park, Suzhou, Jiangsu Patentee before: Suzhou Industrial Park Design & Research Institute Co., Ltd. |
|
CX01 | Expiry of patent term |
Granted publication date: 20130123 |
|
CX01 | Expiry of patent term |