CN202626987U - Planting pile machine - Google Patents

Planting pile machine Download PDF

Info

Publication number
CN202626987U
CN202626987U CN2012202864404U CN201220286440U CN202626987U CN 202626987 U CN202626987 U CN 202626987U CN 2012202864404 U CN2012202864404 U CN 2012202864404U CN 201220286440 U CN201220286440 U CN 201220286440U CN 202626987 U CN202626987 U CN 202626987U
Authority
CN
China
Prior art keywords
hammer
overcoat
steel pipe
cover
right half
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2012202864404U
Other languages
Chinese (zh)
Inventor
王宗斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2012202864404U priority Critical patent/CN202626987U/en
Application granted granted Critical
Publication of CN202626987U publication Critical patent/CN202626987U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a planting pile machine which comprises a steel pipe, a driving hammer, an outer sleeve, and an upper sleeve, wherein the driving hammer, the outer sleeve, and the upper sleeve are sequentially sleeved on the outer wall of the steel pipe from top to bottom. Handles are respectively arranged on two sides of the driving hammer in hinge joint mode, and the driving hammer is movably sleeved on the outer wall of the steel pipe. The outer sleeve is divided into a left half outer sleeve and a right half outer sleeve, and one end of the left half outer sleeve is in hinged connection with one end of the right half outer sleeve. The other end of the left half outer sleeve and the other end of the right half outer sleeve are tightly locked on the outer wall of the steel pipe through a first locknut. The upper sleeve is divided into a left half upper sleeve and a right half upper sleeve, and one end of the left half upper sleeve and one end of the right half upper sleeve are in hinged connection. The other end of the left half upper sleeve and the other end of the right half upper sleeve are tightly locked on the other wall of the steel pipe through a second locknut. The planting pile machine can complete working through manpower without needing external motive power. The planting pile machine has the advantages of being convenient to carry, simple in operation, and easy to understand and learn. In poor environment, the planting pile machine can also rapidly proceed with working.

Description

One implant post device
Technical field
The utility model relates to an implant post device, relates in particular to an a kind of device of planting that is used for flood-fighting and place, building site.
Background technology
An existing device of planting often adopts the vapour-pressure type pile driver, or diesel engine oil presses power change type pile driver.Though an above-mentioned device mechanization degree of planting is high, also have following problem: all be under the assistance of oil-burning machine, to fulfil assignment, equipment goes wrong if any parts and will cause a whole set of equipment can't normally use poor reliability; Equipment is heavy, and when carrying and operation, operation and support personnel are many; Need there be the professional and technical personnel to operate, meeting do not caused the accident, contain operating speed like operational procedure; Environment for use is required height, and the performance that under rugged environment, can influence its performance maybe can't reach application target.
Summary of the invention
The technical problem that the utility model will solve: a kind of machine power that do not need is provided, and reliability is high, does not receive the device of planting that construction environment influences.
The technical solution of the utility model is: an implant post device; Comprise steel pipe, hammer, overcoat and go up cover; Said hammer, overcoat and last cover are enclosed within the outer wall of steel pipe from top to bottom successively; The both sides of said hammer are hinged with handle respectively, and the hammer movable set is on the outer wall of steel pipe, and said overcoat is divided into left half overcoat and right half overcoat; One end of a left side half overcoat and an end of right half overcoat are hinged, and the other end of the other end of left half overcoat and right half overcoat is locked on the outer wall of steel pipe through the 1st locking nut; Last cover is divided into a left side half to be gone up cover and goes up cover with right half, and it is hinged that the end and right half that cover is gone up on a left side half is gone up an end of cover, and the other end that the other end that cover is gone up on a left side half and right half is gone up cover is locked on the outer wall of steel pipe through the 2nd locking nut.
As improvement, the lower surface of hammer and the lower surface of overcoat all are taper seat, and the upper surface of overcoat and the upper surface of last cover all are taper seat, and the lower end taper seat of hammer and the upper end taper seat of overcoat are suitable; The lower end taper seat of overcoat and the upper end taper seat of last cover are suitable.
As improvement; Be positioned at the below of cover; Be with at the outer wall of steel pipe and trap; Said trapping is divided into a left side and partly traps and partly trap with the right side, and an end of partly trapping in a left side is hinged with a right end of partly trapping, and the other end of partly trapping in a left side is locked on the outer wall of steel pipe through the 3rd locking nut with the right other end of partly trapping.
As improvement, the lower surface of last cover is a taper seat, and the upper surface of trapping is a taper seat, and the lower end taper seat of last cover is suitable with the upper end taper seat of trapping.
As improvement, hammer is divided into left half hammer and right half hammer, and an end of left half hammer and an end of right half hammer are hinged, and the other end of the other end of left half hammer and right half hammer is locked together in together through the 4th locking nut.
The technique effect of the utility model is: the utility model plant a device be utilize with overcoat, on overlap and trap and be locked on the outer wall of steel pipe, operating personnel lift hammer with handle along steel pipe, and then hammer is fallen; Impact outer set upper side with the hammer lower end, the following power of pounding that overcoat will receive passes to successively again overlaps and traps because overcoat, on overlap and trap and be locked at outer wall of steel pipe; Finally, the following power of pounding that receives is passed to steel pipe, utilize deadweight of planting a device and the strength of pounding down that steel pipe is implanted earth; Whole process only can be accomplished through manpower, does not need extrinsic motive, as long as personnel's equipment puts in place; Local the utility model that the dynamic power machine pile driver can't put in place all can fulfil assignment, and easy to carry, also evolutionary operation rapidly in rugged environment; Simple to operate, understand well to be prone to learn.
Description of drawings
1, Fig. 1 plants a device sketch map for the utility model.
2, Fig. 2 plants a device half sectional view for the utility model.
The specific embodiment
Shown in Fig. 1 to 2; The utility model one implant post device; Comprise steel pipe 1, hammer 2, overcoat 3 and go up cover 4, said hammer 2, overcoat 3 and go up the outer wall that cover 4 is enclosed within steel pipe 1 from top to bottom successively, the both sides of said hammer 2 are hinged with handle 6 respectively; Hammer 2 movable sets are on the outer wall of steel pipe 1; Said overcoat 3 is divided into left half overcoat 3-1 and right half overcoat 3-2, and the end of the end of left half overcoat 3-1 and right half overcoat 3-2 is hinged, and the other end of the other end of left half overcoat 3-1 and right half overcoat 3-2 is locked on the outer wall of steel pipe 1 through the 1st locking nut 8; Last cover 4 is divided into a left side half to be gone up cover 4-1 and goes up cover 4-2 with right half, and it is hinged that the end and right half that cover 4-1 is gone up on a left side half is gone up the end of cover 4-2, and the other end that cover 4-1 is gone up on a left side half and right half is gone up the cover other end of 4-2 and is locked on the outer wall of steel pipe 1 through the 2nd locking nut 9.Hammer 2 is a taper seat with overcoat 3 lower surfaces, and the upper surface of overcoat 3 and last cover 4 is a taper seat, and the lower end taper seat of hammer 2 and the upper end taper seat of overcoat are suitable, and the lower end taper seat of overcoat 3 and the upper end taper seat of last cover 4 are suitable.Be positioned at the below of cover 4; Be with at the outer wall of steel pipe 1 and trap 5; Said trapping 5 is divided into left side 5-1 and the right side 5-2 that partly traps that partly traps; Partly the trap end of 5-1 of a left side is hinged with the end of the right 5-2 that partly traps, and partly the trap other end of 5-1 and the other end of the right 5-2 that partly traps of a left side is locked on the outer wall of steel pipe 1 through the 3rd locking nut 10.The lower surface of last cover 4 is a taper seat, and 5 the upper surface of trapping is a taper seat, on to overlap 4 lower end taper seat suitable with 5 the upper end taper seat of trapping.Hammer 2 is divided into left half hammer 2-1 and right half hammer 2-2; The end of a left side half hammer 2-1 and the end of right half hammer 2-2 are hinged; The other end of a left side half hammer 2-1 and the other end of right half hammer 2-2 are locked together in together through the 4th locking nut 7; The 4th locking nut 7 is provided with spring, and the pretightning force through spring makes left half hammer 2-1 and right half hammer 2-2 be locked at together movable set on steel pipe.Hammer 2, overcoat 3, on overlap 4 and trap and 5 be divided into left and right sides two halves, help hammer 2, overcoat 3, on overlap 4 and 5 the rapid folding of trapping, easy to operate.
Operating condition: form operation group by three operation hands, be respectively the first place steel pipe and lift handrail; Second and third locking impacts hand, and three people pull together to cooperate to accomplish and plant an operation.
Operating procedure: first step locking is installed; By first place operation hand steel pipe being put in ground lifts an end and becomes 15 degree angles approximately with ground; Second place operation hand will be trapped successively and go up and is inserted in steel pipe and lock by locking nut; Third operation hand is inserted in steel pipe with overcoat locks by locking nut, and second and third operation Handball Association power is placed in outer set upper side with hammer thereafter, accomplishes the locking installment work;
The second step steel pipe is implanted; After locking is accomplished; Three operation Handball Association power are put in steel pipe plants on the pipe point, by first place operation hand in the lower end of trapping the hand steered steel pipes of living of about 50 centimeters two, two, three operation hands are held handle respectively hammer are pounded along pushing on steel pipe is done; Steel pipe is implanted in the earth, accomplished the requirement of planting a degree of depth.
The 3rd step was removed receipts, planted after stake accomplishes; At first pulled together hammer and overcoat are removed from steel pipe by three operation hands, first place operation hand will be gone up cover and remove, and second and third operation Handball Association power will be trapped and removed, and accomplish and remove receipts.
More than accomplish and plant pile foundation operating process originally, under particular environment and situation, also should confirm job step and method based on situation.
The unspecified content of the utility model is prior art, and those skilled in the art can obtain to inspire from present embodiment and prior art, is out of shape to obtain other embodiment.Therefore, the protection domain of the utility model should be confirmed according to the protection domain of claim.

Claims (5)

1. an implant post device; Comprise steel pipe (1); It is characterized in that: also be provided with hammer (2), overcoat (3) and last cover (4), said hammer (2), overcoat (3) and last cover (4) are enclosed within the outer wall of steel pipe (1) from top to bottom successively, and the both sides of said hammer (2) are hinged with handle (6) respectively; Hammer (2) movable set is on the outer wall of steel pipe (1); Said overcoat (3) is divided into left half overcoat (3-1) and right half overcoat (3-2), and an end of an end of left half overcoat (3-1) and right half overcoat (3-2) is hinged, and the other end of the other end of left half overcoat (3-1) and right half overcoat (3-2) is locked on the outer wall of steel pipe (1) through the 1st locking nut (8); Last cover (4) is divided into a left side and partly goes up upward cover (4-2) of cover (4-1) and right half; It is hinged that the end and right half that cover (4-1) is gone up on a left side half is gone up an end of cover (4-2), and a left side half is gone up the other end that the other end and right half of cover (4-1) goes up cover (4-2) and is locked on the outer wall of steel pipe (1) through the 2nd locking nut (9).
2. according to the said implant post device of claim 1; It is characterized in that: the lower surface of the lower surface of hammer (2) and overcoat (3) all is a taper seat; The upper surface of the upper surface of overcoat (3) and last cover (4) all is a taper seat, and the lower end taper seat of hammer (2) and the upper end taper seat of overcoat are suitable; The upper end taper seat of the lower end taper seat of overcoat (3) and last cover (4) is suitable.
3. according to claim 1 or 2 said implant post devices; It is characterized in that: the below that is positioned at cover (4); Outer wall at steel pipe (1) is with trap (5); Said trapping (5) is divided into that partly trapping (5-1) in a left side and partly traps (5-2) in the right side, and a left side partly the trap end of (5-2) of an end and the right side of (5-1) of partly trapping is hinged, and a left side partly the trap other end of (5-2) of the other end and the right side of (5-1) of partly trapping is locked on the outer wall of steel pipe (1) through the 3rd locking nut (10).
4. according to the said implant post device of claim 3, it is characterized in that: the lower surface of going up cover (4) is a taper seat, and the upper surface of trap (5) is a taper seat, and the lower end taper seat of last cover (4) is suitable with the upper end taper seat of trap (5).
5. according to the said implant post device of claim 4; It is characterized in that: hammer (2) is divided into left half hammer (2-1) and right half hammer (2-2); One end of a left side half hammer (2-1) and an end of right half hammer (2-2) are hinged, and the other end of the other end of left half hammer (2-1) and right half hammer (2-2) is locked together in together through the 4th locking nut (7).
CN2012202864404U 2012-06-07 2012-06-07 Planting pile machine Expired - Fee Related CN202626987U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012202864404U CN202626987U (en) 2012-06-07 2012-06-07 Planting pile machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012202864404U CN202626987U (en) 2012-06-07 2012-06-07 Planting pile machine

Publications (1)

Publication Number Publication Date
CN202626987U true CN202626987U (en) 2012-12-26

Family

ID=47380198

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012202864404U Expired - Fee Related CN202626987U (en) 2012-06-07 2012-06-07 Planting pile machine

Country Status (1)

Country Link
CN (1) CN202626987U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108842771A (en) * 2018-09-21 2018-11-20 中国人民解放军军事科学院国防工程研究院 A kind of portable plant stake device of lower impact type

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108842771A (en) * 2018-09-21 2018-11-20 中国人民解放军军事科学院国防工程研究院 A kind of portable plant stake device of lower impact type

Similar Documents

Publication Publication Date Title
CN106013241B (en) Guan Liang foundation trench uprightly performs and cap excavation method station integrated structure system and construction method
CN101922243B (en) Inner jacking method and equipment for demolishing buildings
CN106950070A (en) Experimental rig for rectangular top pipe jacking construction Whole Process Simulation
CN103643669B (en) For the Apparatus and method for of survey soft soil area on-site sampling
KR101863526B1 (en) Drawing apparatus for H beam
CN204000830U (en) Merogenesis take-over type sand drain machine
CN105804048B (en) A kind of soft foundation drain bar reinforcement means
CN202626987U (en) Planting pile machine
EP2351903A3 (en) Method and device for establishing and/or enlarging a borehole
ES2361867B1 (en) METHOD OF MANUFACTURE, INFLATION AND INJECTION OF UNDERWATER PILOTS TICOS.
CN105332376A (en) Hydraulic manipulator pile-pulling clamping device and pile pulling machine
CN104110034B (en) The construction of Static Pressure Pile method of casting and penetrating resistance can be reduced
CN101338572B (en) Posthole digger
CN105113976A (en) Wire-brush-bit rotary drilling jig and method for solving bit burying, falling and jamming
CN203022001U (en) Pile-pulling device with vibrating sleeve ring
CN204418180U (en) A kind of hydraulic pressure plays a machine
CN204326075U (en) A kind of drill steel extracting apparatus
CN103061342B (en) Highway crash barrier floating type hydraulic pile driving and pile pulling device
CN205858220U (en) Get rid of drilling tool ramp transition apparatus
CN205189028U (en) Bored concrete pile pore -forming device
CN208949891U (en) A kind of green assembled construction of soil-nailed wall platform
CN104895058A (en) Full-hydraulic static-pressure dual-pipe composite expanded bore pile machine and construction method thereof
CN103046550B (en) A kind of vibrations collar pile pulling device and using method thereof
CN204703152U (en) All-hydraulic static pressure two-tube compound expanded bore pile machine
CN203741872U (en) Structure for improving elevator shaft through stiff beam

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121226

Termination date: 20150607

EXPY Termination of patent right or utility model