CN202609691U - Locking device for heavy-coil spool cord take-up and arranging structures for steel cords - Google Patents

Locking device for heavy-coil spool cord take-up and arranging structures for steel cords Download PDF

Info

Publication number
CN202609691U
CN202609691U CN 201220214616 CN201220214616U CN202609691U CN 202609691 U CN202609691 U CN 202609691U CN 201220214616 CN201220214616 CN 201220214616 CN 201220214616 U CN201220214616 U CN 201220214616U CN 202609691 U CN202609691 U CN 202609691U
Authority
CN
China
Prior art keywords
vertical
cantilever
fixed
bearing plate
steel cord
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN 201220214616
Other languages
Chinese (zh)
Inventor
谢进宝
杨宏
刘建涛
白学斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Hengxing Science and Technology Co Ltd
Original Assignee
Henan Hengxing Science and Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Hengxing Science and Technology Co Ltd filed Critical Henan Hengxing Science and Technology Co Ltd
Priority to CN 201220214616 priority Critical patent/CN202609691U/en
Application granted granted Critical
Publication of CN202609691U publication Critical patent/CN202609691U/en
Anticipated expiration legal-status Critical
Withdrawn - After Issue legal-status Critical Current

Links

Images

Landscapes

  • Emergency Lowering Means (AREA)

Abstract

The utility model relates to a locking device for heavy-coil spool cord take-up and arranging structures for steel cords, which comprises two vertical support walls and a vertical support plate, wherein the two vertical support walls and the vertical support plate are fixed together, two longitudinal horizontal cantilevers are fixed at a part (higher than the support walls) of the vertical support plate, and the two cantilevers are respectively provided with a longitudinal cord guiding roller; the sandwich layers of the two vertical support walls are respectively sequentially provided with a transverse guide wheel with a V-shaped slot, a spiral clamping mechanism and a pair of horizontal cord guiding wheels; the spiral clamping mechanism comprises a fixed pressing head and a movable pressing head, and a steel cord is arranged between the two pressing heads; and the support walls or the support plate and a cord arranging mechanism are fixed together. By using the device disclosed by the utility model, a steel cord is not directly impacted, so that a situation that the material performance of the steel cord is not damaged can be ensured, therefore, the qualified rate of products is high, the cord fracture rate is reduced, the labor intensity can be reduced, and the production cost can be reduced. The device is simple in structure and low in cost; and after the device is used on trial more than one year, the fault of accumulated cords caused by braking never occurs, therefore, the device is extremely beneficial for promotion and implementation.

Description

Steel cord deep bid heavy industry character wheel take-up bus-bar construction latching device
Technical field:
The utility model relates to steel cord take-up latching device, is specifically related to a kind of steel cord deep bid heavy industry character wheel take-up bus-bar construction latching device.
Background technology:
During the take-up of steel cord deep bid heavy industry character wheel, when the take-up of deep bid heavy industry character wheel completely need be changed, need fix the steel cord, in the prior art, during the steel wire dishful, the long-pending line of the long-pending cable reel of take-up is being with steel wire at the long-pending line of long-pending cable reel.Take-up dishful I-beam wheel is laid down; The sky I-beam wheel of packing into continues to produce, and the eccentric well character wheel in the take-up wire-arranging mechanism utilizes a unilateral bearing in the eccentric well character wheel to pin steel wire head, does not allow steel wire when amassing line; Steel wire is loosening, the pine cover; Line ball and long-pending line when causing the long-pending line of steel wire, and former wire-arranging mechanism latching device material is aluminium casting, is easy to damage; The well character wheel is the not dead steel wire of lock often; The frequent unilateral bearing of well character wheel damages.
The utility model content:
The utility model is to overcome deficiency and the defective that prior art exists, and a kind of steel cord deep bid heavy industry character wheel take-up bus-bar construction latching device is provided.
Technical scheme: a kind of steel cord deep bid heavy industry character wheel take-up bus-bar construction latching device, comprise two vertical supporting walls and a vertical stay bearing plate, two vertical supporting walls rear sides are fixed on this vertical stay bearing plate simultaneously; Vertical stay bearing plate upper end exceeds two supporting walls, and this raised area is fixed with the cantilever of two vertical equities, and a vertical guide roller respectively is installed on two cantilevers; Guide roller, spiral clamping mechanism and a pair of horizontal guide roller of a band " V " type groove are installed in the said two vertical supporting walls interlayers from top to bottom successively; Said spiral clamping mechanism comprises fixedly a pressure head and a movable pressure head, the steel cord over against two pressure heads between; Wherein movable pressure head comprises nut and one and the bolt of this nut through being threaded that are fixed on the supporting walls, and movable pressure head and bolt the inner are fixed as one, and the part that nut is stretched out in the bolt outer end is provided with handle; Said supporting walls or stay bearing plate and wire-arranging mechanism are fixed together.
In the cantilever of said two vertical equities; It is movable cantilever that one or two cantilever is arranged; This movable cantilever is installed on the stay bearing plate through regulating mechanism, and this regulating mechanism is on stay bearing plate, to be horizontally disposed with the bar shaped chute, and the end coupling of movable cantilever is inserted in the said bar shaped chute; Be horizontally disposed with tapped bore on the said bar shaped chute lateral wall, coupling is equipped with the adjusting bolt in this tapped bore, is set with holddown spring or shell fragment between bar shaped chute inwall and the cantilever.
Said movable cantilever end is fixed with the rectangle regulating block, and this rectangle regulating block coupling is installed in the said bar shaped chute, and said adjusting bolt one end roof pressure is in this regulating block one side, and said spring or shell fragment roof pressure are at the regulating block opposite side.
Two cantilevered distal end are fixed together through a connecting panel.
The beneficial effect of the utility model: the mode of utilizing spiral to compress, steel wire head are pressed tightly, can not become flexible and escape head; And after the well character wheel made wire-crossing wheel into, steel wire did not have outside deterioration, and quality is guaranteed.Use this device steel cord product quality high, reduce wire broken rate, thereby reduce extra labor content, reduce production costs.This apparatus structure is simple, and cost is low, through the time more than a year on probation, heavily comes not have the fault that long-pending line produces because of brake to occur, and this device is beneficial to promotion and implementation very much.
Description of drawings:
Fig. 1 is the construction profile scheme drawing of the said device of the utility model;
Fig. 2 is the right elevation (Facad structure scheme drawing) of Fig. 1;
Fig. 3 is the regulating mechanism scheme drawing of cantilever among Fig. 1.
Label 1 is vertical supporting walls among the figure, 2 guide rollers for band " V " type groove, and 21 is the rotating shaft of the guide roller of band " V " type groove, and 3 is horizontal guide roller, and 31 is the rotating shaft of horizontal guide roller; 4 are fixing pressure head, and 5 is movable pressure head, and 61 is nut, and 62 is bolt; 63 is handle, and 7 is vertical guide roller, and 71 is cantilever mounted, and 72 is connecting panel; 73 is movable cantilever, and 74 is the rectangle regulating block, and 75 is spring, and 8 is vertical stay bearing plate; 9 for regulating bolt, and 10 is wire-arranging mechanism, and 11 is the winding displacement thread rod, and 12 is the steel cord.
The specific embodiment:
Referring to Fig. 1 and Fig. 2, steel cord deep bid heavy industry character wheel take-up bus-bar construction latching device comprises two vertical supporting walls 1 and a vertical stay bearing plate 8, these vertical stay bearing plate 8 vertical rear sides that insert two supporting walls, 1 interlayer.Two vertical supporting walls 1 rear sides are fixed on this vertical stay bearing plate 8 simultaneously, constitute a support frame structure.
Vertical stay bearing plate 8 upper ends exceed two supporting walls 1, and this raised area is fixed with the cantilever of two vertical equities, and a vertical guide roller 7 respectively is installed on two cantilevers.In the present embodiment, a cantilever is fixedly welded on the stay bearing plate upper end, is cantilever mounted 71; Another cantilever is movably arranged on the stay bearing plate upper end, is movable cantilever 73.Two cantilevers are on same horizontal surface, and parallel longitudinal, and two cantilevered distal end are fixed together through a connecting panel 72.
Referring to Fig. 1 and Fig. 3; Movable cantilever 73 is installed on the stay bearing plate 8 through regulating mechanism; This regulating mechanism is on stay bearing plate, to be horizontally disposed with the bar shaped chute, and the movable cantilever end is fixed with rectangle regulating block 74, and these rectangle regulating block 74 couplings are installed in the said bar shaped chute.Be horizontally disposed with tapped bore on the said bar shaped chute lateral wall, coupling is equipped with and regulates bolt 9 in this tapped bore, regulates bolt 9 one end roof pressures in this regulating block one side, utilizes spring 75 roof pressures at the regulating block opposite side.
Referring to Fig. 2, guide roller 2, spiral clamping mechanism and a pair of horizontal guide roller 3 of a band " V " type groove is installed successively from top to bottom in said two vertical supporting walls 1 interlayers.Said spiral clamping mechanism comprises fixedly a pressure head 4 and a movable pressure head 6.From process between two guide rollers 7 longitudinally, walk around the guide roller 2 of " V " type groove from the steel cord 12 of long-pending line wheel again, just over against two pressure heads between, then between the horizontal guide roller 3 through after be wrapped on the deep bid I-beam wheel.
Among Fig. 2, movable pressure head comprises nut 61 and one and the bolt 62 of this nut through being threaded that are fixed on the supporting walls, and movable pressure head 5 is fixed as one with the inner of bolt 62, and the part that nut is stretched out in the outer end of bolt 62 is provided with handle 63.
Referring to Fig. 1, supporting walls 1 or stay bearing plate 8 are fixed together with wire-arranging mechanism 10.

Claims (4)

1. steel cord deep bid heavy industry character wheel take-up bus-bar construction latching device, it is characterized in that: comprise two vertical supporting walls and a vertical stay bearing plate, two vertical supporting walls rear sides are fixed on this vertical stay bearing plate simultaneously; Vertical stay bearing plate upper end exceeds two supporting walls, and this raised area is fixed with the cantilever of two vertical equities, and a vertical guide roller respectively is installed on two cantilevers; Guide roller, spiral clamping mechanism and a pair of horizontal guide roller of a band " V " type groove are installed in the said two vertical supporting walls interlayers from top to bottom successively; Said spiral clamping mechanism comprises fixedly a pressure head and a movable pressure head, the steel cord over against two pressure heads between; Wherein movable pressure head comprises nut and one and the bolt of this nut through being threaded that are fixed on the supporting walls, and movable pressure head and bolt the inner are fixed as one, and the part that nut is stretched out in the bolt outer end is provided with handle; Said supporting walls or stay bearing plate and wire-arranging mechanism are fixed together.
2. steel cord deep bid heavy industry character wheel take-up bus-bar construction latching device according to claim 1; It is characterized in that: in the cantilever of said two vertical equities; It is movable cantilever that one or two cantilever is arranged; This movable cantilever is installed on the stay bearing plate through regulating mechanism, and this regulating mechanism is on stay bearing plate, to be horizontally disposed with the bar shaped chute, and the end coupling of movable cantilever is inserted in the said bar shaped chute; Be horizontally disposed with tapped bore on the said bar shaped chute lateral wall, coupling is equipped with the adjusting bolt in this tapped bore, is set with holddown spring or shell fragment between bar shaped chute inwall and the cantilever.
3. steel cord deep bid heavy industry character wheel take-up bus-bar construction latching device according to claim 2; It is characterized in that: said movable cantilever end is fixed with the rectangle regulating block; This rectangle regulating block coupling is installed in the said bar shaped chute; Said adjusting bolt one end roof pressure is in this regulating block one side, and said spring or shell fragment roof pressure are at the regulating block opposite side.
4. steel cord deep bid heavy industry character wheel take-up bus-bar construction latching device according to claim 1, it is characterized in that: two cantilevered distal end are fixed together through a connecting panel.
CN 201220214616 2012-05-14 2012-05-14 Locking device for heavy-coil spool cord take-up and arranging structures for steel cords Withdrawn - After Issue CN202609691U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220214616 CN202609691U (en) 2012-05-14 2012-05-14 Locking device for heavy-coil spool cord take-up and arranging structures for steel cords

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220214616 CN202609691U (en) 2012-05-14 2012-05-14 Locking device for heavy-coil spool cord take-up and arranging structures for steel cords

Publications (1)

Publication Number Publication Date
CN202609691U true CN202609691U (en) 2012-12-19

Family

ID=47343407

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220214616 Withdrawn - After Issue CN202609691U (en) 2012-05-14 2012-05-14 Locking device for heavy-coil spool cord take-up and arranging structures for steel cords

Country Status (1)

Country Link
CN (1) CN202609691U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102745553A (en) * 2012-05-14 2012-10-24 河南恒星科技股份有限公司 Locking device of winding and cord arranging structure of steel cord grail heavy industrial character wheel
CN103706668A (en) * 2013-12-24 2014-04-09 华国洋 Steel cord drawing and coiling device

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102745553A (en) * 2012-05-14 2012-10-24 河南恒星科技股份有限公司 Locking device of winding and cord arranging structure of steel cord grail heavy industrial character wheel
CN102745553B (en) * 2012-05-14 2013-11-13 河南恒星科技股份有限公司 Locking device of winding and cord arranging structure of steel cord grail heavy industrial character wheel
CN103706668A (en) * 2013-12-24 2014-04-09 华国洋 Steel cord drawing and coiling device
CN103706668B (en) * 2013-12-24 2015-08-05 张素平 A kind of steel cord wire drawing take-up

Similar Documents

Publication Publication Date Title
CN203306266U (en) Tube and bar managing and binding system
CN106975717B (en) A kind of wirerope cutting equipment
CN104773564A (en) Automatic edge-sealing adhesive tape pasting system for large-size roll material
CN202609691U (en) Locking device for heavy-coil spool cord take-up and arranging structures for steel cords
CN2926047Y (en) Wire-rod bander
CN107140457A (en) A kind of aluminium rolls up material guide mechanism
CN204607179U (en) A kind of large-scale coiled strip seals limit tape system automatically
CN204607245U (en) A kind of wire coiling machine actinobacillus device
CN102745553B (en) Locking device of winding and cord arranging structure of steel cord grail heavy industrial character wheel
CN101323156A (en) Double-drum vulcanizer
CN205789325U (en) One scraps cable peeling device
CN205380439U (en) Copper product extrusion cuts off canceling release mechanical system in step
CN107284500A (en) A kind of firm type carrier
CN205873103U (en) Novel scalable straining device is used to rail conveyor
CN112478912B (en) Double-layer feeding anti-deviation derrick of profile production line
CN115488171A (en) Wire drawing device is used in production of aluminium package steel wire
CN108580743A (en) A kind of bracing wire bending apparatus
CN202118188U (en) Fixing press plate structure for ropes of rope reel of dragging device
CN209921759U (en) Steel coil core-pulling flush system of transportation system suitable for hot-rolled steel coil double-transportation line
CN209110070U (en) A kind of efficient automatic spring winding machine
CN208437569U (en) A kind of bracing wire bending apparatus
CN204023283U (en) A kind of pneumatic actinobacillus device of buncher
CN205820545U (en) A kind of textile industry mechanical winding line apparatus
CN215854303U (en) High stability water tank wire drawing machine pay-off
CN205032497U (en) Can turn to and pull wrench device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20121219

Effective date of abandoning: 20131113

RGAV Abandon patent right to avoid regrant