CN202559307U CN 201220222186 CN201220222186U CN202559307U CN 202559307 U CN202559307 U CN 202559307U CN 201220222186 CN201220222186 CN 201220222186 CN 201220222186 U CN201220222186 U CN 201220222186U CN 202559307 U CN202559307 U CN 202559307U
Authority
CN
China
Prior art keywords
straining beam
straining
steel pipe
forming machine
sides
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220222186
Other languages
English (en)
Inventor
吴平安
龚华伟
赵志忠
刘经军
李友顺
胡骏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Gezhouba Group Co Ltd
China Gezhouba Group No 1 Engineering Co Ltd
Original Assignee
China Gezhouba Group Co Ltd
China Gezhouba Group No 1 Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group Co Ltd, China Gezhouba Group No 1 Engineering Co Ltd filed Critical China Gezhouba Group Co Ltd
Priority to CN 201220222186 priority Critical patent/CN202559307U/zh
Application granted granted Critical
Publication of CN202559307U publication Critical patent/CN202559307U/zh
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

一种U型渡槽预制拉梁组合支撑装置,包括造槽机外模,内主梁设于造槽机外模内部,造槽机内模滑动地吊挂在内主梁上,内主梁上下平面的两侧设有轨道,在内主梁上滑动地安装有用于支撑拉梁的钢管支撑架,钢管支撑架底部两侧设有与轨道配合的滑轨挡板。本实用新型提供的一种U型渡槽预制拉梁组合支撑装置,通过以造槽机箱型内主梁上平面为混凝土预制拉梁重量的承载主体、以内主梁与拉梁之间的高度尺寸为参考设计一套组合支撑装置,让拉梁的重量通过钢管支撑架由内主梁承担,造槽机内模两侧上口钢模板与混凝土预制拉梁两端相接但内模上口两侧不承担拉梁重量,使槽身钢筋不产生变形,造槽机内模不承受拉梁的重力,拆除也会变的容易。

Description

U型渡槽预制拉梁组合支撑装置
技术领域
本实用新型涉及水利工程大型U型渡槽施工领域,尤其是适用于在内模上部与外主梁之间狭小的空间内,用于支撑拉梁的U型渡槽预制拉梁组合支撑装置。
背景技术
某U型渡槽位于河流上,渡槽槽体为相互独立的3槽预应力混凝土U型结构,共18跨总计54段渡槽。如图1-2所示,渡槽单跨长度40m、内空尺寸长×宽×高为40.0m×9.0m×7.23m, 渡槽结构为U型钢筋混凝土后张法三向预应力薄壁渡槽,U型渡槽壁厚350mm。槽体上部设计有17根钢筋混凝土预制拉梁,如图5所示,渡槽施工采用移置式U型渡槽专用组合钢模,在槽墩上采用现浇施工法浇筑槽体混凝土。由于在造槽机外模内槽体钢筋钢铰线等已绑扎安装完毕、造槽机内模系统也从外驶入渡槽槽体浇筑区域、内模向两侧伸开到位,17根预制拉梁的吊运安装是最后一道工序,每根钢筋混凝土预制拉梁重约5.4吨,矩形断面结构,拉梁两端包括外露钢筋的最大外型尺寸为9.6m×0.5m×0.5m,拉梁预制混凝土结构尺寸为7.0m×0.5m×0.5m,由于造槽机内模顶部与外模之间空间非常狭小,预制拉梁很难吊装到位,钢筋混凝土预制拉梁为矩形断面结构,拉梁两端包括外露钢筋的最大外型尺寸为9.6m×0.5m×0.5m,预制混凝土部分的结构尺寸为7.0m×0.5m×0.5m,每根钢拉梁重约5.4吨,17根拉梁总计重约90余吨。
造槽机内主梁两侧面对称托挂造槽机内模系统、内模上口外侧与外模内侧之间的间隙为350mm,内模上口向内侧伸出长约1.5m长的人行走道悬臂,内模与外模之间没有设置钢性定位联接、只有槽身钢筋和钢铰线,预制拉梁吊装到槽身相应位置后、将拉梁两端伸出的钢筋与槽身钢筋相连接,完成拉梁的吊装工序。由于槽身钢筋不能承担拉梁重量、如果将拉梁直接放置在内模上口、让内模上口两侧承担拉梁重量、将会给内模的拆除造成非常大的困难,不但会造成内模严重变形、影响槽身结构尺寸和混凝土质量、90余吨重的拉梁压在内模两侧、还使内模的拆除变的非常困难,故拉梁在槽身内如何安装支撑定位、如何让内模方便安装拆除成了渡槽施工技术难题。
发明内容
本实用新型所要解决的技术问题是提供一种U型渡槽预制拉梁组合支撑装置,可以解决造槽机内模系统的两侧不能承担拉梁重量、不会造成造槽机内模严重变形、从而确保渡槽槽体结构尺寸和混凝土浇筑质量。
为解决上述技术问题,本实用新型所采用的技术方案是:一种U型渡槽预制拉梁组合支撑装置,包括造槽机外模,内主梁设于造槽机外模内部,造槽机内模滑动地吊挂在内主梁上,内主梁上、下平面的两侧设有轨道,在内主梁上滑动地安装有用于支撑拉梁的钢管支撑架,钢管支撑架底部两侧设有与轨道配合的滑轨挡板。
所述的钢管支撑架与拉梁之间还设有楔形木。
本实用新型提供的一种U型渡槽预制拉梁组合支撑装置,通过以造槽机箱型内主梁上平面为混凝土预制拉梁重量的承载主体、以内主梁与拉梁之间的高度尺寸为参考设计一套组合支撑装置,让拉梁的重量通过钢管支撑架由内主梁承担、渡槽槽身U型钢筋只与拉梁两端伸出的拉梁钢筋起连接作用,槽身钢筋不承担拉梁重量,造槽机内模两侧上口钢模板与混凝土预制拉梁两端相接但内模上口两侧不承担拉梁重量,使槽身钢筋不产生变形,造槽机内模不承受拉梁的重力,拆除也会变的容易。内主梁上平面与拉梁之间增加支撑装置、采用杂木制成的楔形木还能对拉梁进行适当顶紧、拉梁重量经由杂木楔子、钢管支撑架传至箱型的内主梁、达到造槽机内模不承担拉梁重量的目的,同时17根拉梁总共约90吨重力全由内主梁承担、相当在造槽机内模上增加了90吨配重、可以抵抗渡槽槽体底部浇筑混凝土时,泵送混凝土对造槽机内模底部产生的上浮力。
本实用新型设计操作安全简单可靠、解决了大型渡槽施工过程中预制拉梁支撑的技术难题,取得很好的经济效益,具有很大技术经济优势。
附图说明
下面结合附图和实施例对本实用新型作进一步说明:
图1为本实用新型中渡槽结构的主视图。
图2为图1的侧视图。
图3为本实用新型的整体横截面结构示意图。
图4为内主梁的横截面结构示意图。
图5为预制拉梁的结构示意图。
图6为本实用新型的横截面结构示意图。
图7为图6中A处的局部放大图。
图8为图6的左视图。
图中:槽墩1,造槽机外模2,渡槽槽体3,造槽机内模4,轨道5,内主梁6,拉梁7,拉梁钢筋8,滑轨挡板9,钢管支撑架10,楔形木11。
具体实施方式
如图3、4、6-8中,一种U型渡槽预制拉梁组合支撑装置,包括造槽机外模2,内主梁6设于造槽机外模2内部,造槽机内模4滑动地吊挂在内主梁6上,内主梁6上、下平面的两侧设有轨道5,在内主梁6上滑动地安装有用于支撑拉梁7的钢管支撑架10,钢管支撑架10底部两侧设有与轨道5配合的滑轨挡板9。
优化的方案,如图8中,所述的钢管支撑架10与拉梁7之间还设有楔形木11。
利用内主梁6上平面为承载体、以内主梁与拉梁之间的高度尺寸为参考设计一套支撑装置,支撑装置由钢管支撑架10、滑轨挡板9和楔形木11等组成,钢管支撑架10高度比内主梁6与拉梁7之间的高度少80mm±10mm,宽度比内主梁上平面宽30mm±10mm。
钢管支撑架10在人工推动下可以沿内主梁6上平面板式轨道5向前或向后滑移、直至推送到混凝土预制拉梁支撑适当位置。如图6中所示、钢管支撑架10顺内主梁6上平面推送到混凝土预制拉梁7下适当位置后、将拉梁7梁按设计要求调整到相应高度、用人工在钢管支撑架10与拉梁7下平面之间的空隙处、加入楔形木11并适当顶紧,则拉梁7重量经由楔形木11、钢管支撑架10传至内主梁6、达到造槽机内模4不承担拉梁7重量的目的,17根拉梁总共约90吨重力全由内主梁6承担。

Claims (2)

1.一种U型渡槽预制拉梁组合支撑装置,包括造槽机外模(2),内主梁(6)设于造槽机外模(2)内部,造槽机内模(4)滑动地吊挂在内主梁(6)上,内主梁(6)上、下平面的两侧设有轨道(5),其特征是:在内主梁(6)上滑动地安装有用于支撑拉梁(7)的钢管支撑架(10),钢管支撑架(10)底部两侧设有与轨道(5)配合的滑轨挡板(9)。
2.根据权利要求1所述的一种U型渡槽预制拉梁组合支撑装置,其特征是:所述的钢管支撑架(10)与拉梁(7)之间还设有楔形木(11)。
CN 201220222186 2012-05-17 2012-05-17 U型渡槽预制拉梁组合支撑装置 Expired - Fee Related CN202559307U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220222186 CN202559307U (zh) 2012-05-17 2012-05-17 U型渡槽预制拉梁组合支撑装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220222186 CN202559307U (zh) 2012-05-17 2012-05-17 U型渡槽预制拉梁组合支撑装置

Publications (1)

Publication Number Publication Date
CN202559307U true CN202559307U (zh) 2012-11-28

Family

ID=47208976

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220222186 Expired - Fee Related CN202559307U (zh) 2012-05-17 2012-05-17 U型渡槽预制拉梁组合支撑装置

Country Status (1)

Country Link
CN (1) CN202559307U (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103526697A (zh) * 2013-10-24 2014-01-22 郑州新大方重工科技有限公司 一种用于双矩形水利渡槽施工的自行式移动模架
CN103898876A (zh) * 2014-04-09 2014-07-02 安徽水安建设集团股份有限公司 一种无对销螺栓的钢筋混凝土u型渡槽浇筑模板
CN104195958A (zh) * 2014-09-16 2014-12-10 葛洲坝集团第一工程有限公司 渡槽侧墙顶板造槽机过孔保护装置及方法
CN104278658A (zh) * 2014-09-16 2015-01-14 中国葛洲坝集团股份有限公司 一种造槽机施工槽身混凝土浇筑方法
CN104314052A (zh) * 2014-09-16 2015-01-28 葛洲坝集团第一工程有限公司 造槽机端肋模板脱模方法
CN104878729A (zh) * 2015-04-27 2015-09-02 吉林省银河水利水电新技术设计有限公司 采用异向双层预应力钢结构牛腿进行槽身结构改造的方法
CN105155474A (zh) * 2015-10-15 2015-12-16 中交第一公路工程局有限公司 急流槽施工用定型模具和急流槽的施工方法

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103526697A (zh) * 2013-10-24 2014-01-22 郑州新大方重工科技有限公司 一种用于双矩形水利渡槽施工的自行式移动模架
CN103526697B (zh) * 2013-10-24 2015-07-15 郑州新大方重工科技有限公司 一种用于双矩形水利渡槽施工的自行式移动模架
CN103898876A (zh) * 2014-04-09 2014-07-02 安徽水安建设集团股份有限公司 一种无对销螺栓的钢筋混凝土u型渡槽浇筑模板
CN103898876B (zh) * 2014-04-09 2015-02-18 安徽水安建设集团股份有限公司 一种无对销螺栓的钢筋混凝土u型渡槽浇筑模板的制造方法
CN104195958A (zh) * 2014-09-16 2014-12-10 葛洲坝集团第一工程有限公司 渡槽侧墙顶板造槽机过孔保护装置及方法
CN104278658A (zh) * 2014-09-16 2015-01-14 中国葛洲坝集团股份有限公司 一种造槽机施工槽身混凝土浇筑方法
CN104314052A (zh) * 2014-09-16 2015-01-28 葛洲坝集团第一工程有限公司 造槽机端肋模板脱模方法
CN104195958B (zh) * 2014-09-16 2016-05-04 葛洲坝集团第一工程有限公司 渡槽侧墙顶板造槽机过孔保护方法
CN104878729A (zh) * 2015-04-27 2015-09-02 吉林省银河水利水电新技术设计有限公司 采用异向双层预应力钢结构牛腿进行槽身结构改造的方法
CN104878729B (zh) * 2015-04-27 2016-09-14 吉林省银河水利水电新技术设计有限公司 采用异向双层预应力钢结构牛腿进行槽身结构改造的方法
CN105155474A (zh) * 2015-10-15 2015-12-16 中交第一公路工程局有限公司 急流槽施工用定型模具和急流槽的施工方法

Similar Documents

Publication Publication Date Title
CN202559307U (zh) U型渡槽预制拉梁组合支撑装置
CN101824800B (zh) 一种桥位现浇预应力混凝土连续梁的施工方法
CN101775903B (zh) 有粘结预应力钢筋混凝土连续梁沉降后浇带的施工方法
CN102704406A (zh) 基于组合槽型梁的道床板无拉应力施工方法
CN110700105B (zh) 高墩墩柱与系梁同步施工方法及所用模板
CN102979038A (zh) 宽幅变宽现浇箱梁移动支架
CN208668596U (zh) 一种钢筋混凝土梁板体系与预制柱装配节点
CN202658529U (zh) 一种高速铁路原位制梁预制钢筋整体吊装入模装置
CN102677624B (zh) U型渡槽仿真试验装置及方法
CN201648978U (zh) 桥位现浇预应力混凝土连续梁的系杆拱支架
CN204325821U (zh) 中低速磁悬浮低置线路连续框架式承轨梁结构
CN103074871A (zh) 一种弧形坡面混凝土滑升模板
CN202559306U (zh) U型渡槽预制拉梁吊运转向装置
CN202989781U (zh) 宽幅变宽现浇箱梁移动支架
CN212611890U (zh) 一种隧道内跨越溶洞的钢混组合拱桥
CN203066352U (zh) 自承式异形外包钢-混凝土组合梁
CN207073117U (zh) 工厂式大型渡槽施工系统
CN202559291U (zh) U型渡槽仿真试验装置
CN205576872U (zh) 便于施工的水电站岸塔式进水口结构
CN102444406A (zh) 针梁式仰拱衬砌滑行模架及其施工方法
CN102677633B (zh) U型渡槽预制拉梁吊运转向装置及方法
CN206052565U (zh) 一种梁柱式支架
CN107338768A (zh) 工厂式大型渡槽施工系统及方法
CN210256628U (zh) 一种用于混凝土预制的自适应外模系统
CN206667071U (zh) 连续梁边跨合拢装置

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121128

Termination date: 20180517

CF01 Termination of patent right due to non-payment of annual fee