CN202530486U - Pile foundation reinforcing apparatus for current building - Google Patents
Pile foundation reinforcing apparatus for current building Download PDFInfo
- Publication number
- CN202530486U CN202530486U CN 201120552602 CN201120552602U CN202530486U CN 202530486 U CN202530486 U CN 202530486U CN 201120552602 CN201120552602 CN 201120552602 CN 201120552602 U CN201120552602 U CN 201120552602U CN 202530486 U CN202530486 U CN 202530486U
- Authority
- CN
- China
- Prior art keywords
- under
- original
- cushion cap
- pile foundation
- frame column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Abstract
The utility model discloses a pile foundation reinforcing apparatus for a current building, comprising an original framework column, an original framework column lower part, and an original framework column lower bearing platform. The pile foundation reinforcing apparatus is characterized in that the periphery of the original framework column is evenly supported by a plurality of newly-added framework column lower parts; the original bearing platform is supported by a newly-added framework column lower bearing platform.
Description
Technical field
The utility model relates to a kind of pile foundation reinforcement field of existing building, and especially existing building is reinforced the part of (seismic hardening).
Background technology
The underpin of existing building is the reinforcing of a great problem of field of reinforcement, especially building pile foundation always, does not also have ripe Scheme of Strengthening at present at home.The reinforcing of building pile foundation mainly is not have reliable construction technology and otherwise effective technique measure to ensure.Not only cause waste, prolongation engineering time, the increase construction cost of manpower, also bring construction safety hidden danger easily.This patent has solved the difficult problem on technology and the construction technology effectively.
The utility model content
The utility model technical problem to be solved is mainly to solve the existing pile foundation hypodynamic problem of carrying of (comprising stake and cushion cap).
The utility model adopts following technical scheme:
Pile foundation reinforcement device under a kind of existing building; Comprise under original frame column, the original frame column and cushion cap under original frame column; It is characterized in that: be supported with under several newly-increased frame columns being uniformly distributed with all around of original frame column, and be supported with cushion cap under the newly-increased frame column under original cushion cap.
The beneficial effect of the utility model is:
The utility model has adopted technique scheme to the problems referred to above, has both satisfied the instructions for use of engineering, and it is also very simple to construct, and most importantly degree of safety has had guarantee.
Description of drawings
Fig. 1 is the plan view of the utility model;
Fig. 2 is the sectional drawing of the line 1-1 among Fig. 1.
Wherein:
The original frame column of 1-, under the original frame column of 2-, cushion cap under the original frame column of 3-, under the newly-increased frame column of 4-, cushion cap under the newly-increased frame column of 5-.
The specific embodiment
According to embodiment the utility model is done further explain below.
Shown in Fig. 1-2, in this building, arranged 1500 * 1500mm, four pile caps under a certain post, 250 * 250 preformed piles, bearing capacity of single pile are 100KN, altogether 400KN.But after changing the top function of use, this cushion cap need bear the load of 1200KN, and obvious original cushion cap and stake all can't be born far away.For this reason, around original, being uniformly distributed with increases by 12 root piles, and diameter is 300mm, and the bearing capacity of every root pile is 100KN, and 1200KN sets up a new cushion cap simultaneously under original cushion cap altogether.
Construction technology: around original cushion cap, reach the bottom and dig 1000mm with under the manual method; Squeeze into the root pile that mend the back with machinery earlier, former cushion cap bottom surface is cleaned out the brushing interface treating agent with artificial then; Pour into a mould new cushion cap; The venthole of 2 Φ 20 of water brill on original cushion cap makes new cushion cap concrete and former cushion cap concrete combine closely co-operation simultaneously.
Before cushion cap excavation, should carry out the interim reinforcement measure of original pillar earlier, when the concrete strength of waiting to increase newly cushion cap reaches design strength, can remove interim reinforcement measure.
Obviously, the foregoing description of the utility model only be for explain clearly that the utility model does for example, and be not to be qualification to the embodiment of the utility model.For the those of ordinary skill in affiliated field, on the basis of above-mentioned explanation, can also make other multi-form variation and changes.Here can't give exhaustive to all embodiments.Conspicuous variation that every technical scheme that belongs to the utility model is amplified out or change still are in the row of the protection domain of the utility model.
Claims (1)
1. the pile foundation reinforcement device under the existing building; Comprise under original frame column, the original frame column and cushion cap under original frame column; It is characterized in that: be supported with under several newly-increased frame columns being uniformly distributed with all around of said original frame column, and be supported with cushion cap under the newly-increased frame column under the cushion cap under said original frame column.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201120552602 CN202530486U (en) | 2011-12-27 | 2011-12-27 | Pile foundation reinforcing apparatus for current building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201120552602 CN202530486U (en) | 2011-12-27 | 2011-12-27 | Pile foundation reinforcing apparatus for current building |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202530486U true CN202530486U (en) | 2012-11-14 |
Family
ID=47131681
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201120552602 Expired - Fee Related CN202530486U (en) | 2011-12-27 | 2011-12-27 | Pile foundation reinforcing apparatus for current building |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202530486U (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106121271A (en) * | 2016-07-02 | 2016-11-16 | 杭州固特建筑加固技术工程有限公司 | A kind of based on the pile splicing structure on the basis of rotary churning pile |
CN108457204A (en) * | 2018-02-10 | 2018-08-28 | 北京工业大学 | One kind carrying out bracing means for old Bridge Foundation Lack of support |
CN109555147A (en) * | 2018-10-09 | 2019-04-02 | 上海市政工程设计研究总院(集团)有限公司 | A kind of existing Bridge Group pile foundation reinforcement reconstruction structure and its remodeling method |
CN112813986A (en) * | 2021-01-06 | 2021-05-18 | 中国化学工程第十一建设有限公司 | Deep foundation pit structure and deep foundation pit construction process |
CN114991137A (en) * | 2022-07-20 | 2022-09-02 | 上海市城市建设设计研究总院(集团)有限公司 | Pile foundation reinforcing structure of existing building after seismic strengthening and transformation and construction method thereof |
CN116290899A (en) * | 2023-04-12 | 2023-06-23 | 中交第四航务工程局有限公司 | Foundation system for pile replacement and construction method |
-
2011
- 2011-12-27 CN CN 201120552602 patent/CN202530486U/en not_active Expired - Fee Related
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106121271A (en) * | 2016-07-02 | 2016-11-16 | 杭州固特建筑加固技术工程有限公司 | A kind of based on the pile splicing structure on the basis of rotary churning pile |
CN108457204A (en) * | 2018-02-10 | 2018-08-28 | 北京工业大学 | One kind carrying out bracing means for old Bridge Foundation Lack of support |
CN109555147A (en) * | 2018-10-09 | 2019-04-02 | 上海市政工程设计研究总院(集团)有限公司 | A kind of existing Bridge Group pile foundation reinforcement reconstruction structure and its remodeling method |
CN112813986A (en) * | 2021-01-06 | 2021-05-18 | 中国化学工程第十一建设有限公司 | Deep foundation pit structure and deep foundation pit construction process |
CN114991137A (en) * | 2022-07-20 | 2022-09-02 | 上海市城市建设设计研究总院(集团)有限公司 | Pile foundation reinforcing structure of existing building after seismic strengthening and transformation and construction method thereof |
CN114991137B (en) * | 2022-07-20 | 2023-07-04 | 上海市城市建设设计研究总院(集团)有限公司 | Pile foundation reinforcing structure of existing building after earthquake-proof reinforcing transformation and construction method thereof |
CN116290899A (en) * | 2023-04-12 | 2023-06-23 | 中交第四航务工程局有限公司 | Foundation system for pile replacement and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202530486U (en) | Pile foundation reinforcing apparatus for current building | |
CN203834526U (en) | Reinforced concrete bottom plate construction joint waterproof structure formed in sequence method | |
CN203639903U (en) | Side friction enhancement type precast tube pile structure | |
CN106545027A (en) | A kind of ultra-deep washes away the steel pipe pile reinforced method of foundation pile apron | |
CN203451050U (en) | Pile foundation reinforcing cage lifting rib | |
CN204298836U (en) | A kind of pile film cofferdam skeleton structure | |
CN204510246U (en) | A kind of pile foundation of bearing platform plinth structure of being reinforced by the single footing of existing building | |
CN204000859U (en) | The mutual foundation drainage pile for prestressed pipe of a kind of soft or hard interlayer | |
CN205421352U (en) | Adopt reverse construction method post -cast strip reinforced structure of dowel steel | |
CN204679074U (en) | A kind of novel surface observation pier structure | |
CN102296598B (en) | Construction method of PCC (cast-in-place concrete large-diameter pipe) pile | |
CN204780892U (en) | Tubular pile crack reinforcement structure of high strength | |
CN203222808U (en) | Foundation processing structure for floating sluice | |
CN205576872U (en) | Tower water inlet structure of power station bank convenient to construction | |
CN204898645U (en) | Building rubbish regeneration drainage CFG stake ground | |
CN204626367U (en) | A kind of ruggedized construction of refuse landfill muck foundation | |
CN206385459U (en) | A kind of portable bridge cleaning device | |
CN203795443U (en) | Drainage system for pile cap foundation pit | |
CN202273180U (en) | Self-automatic spray curing system for thin-walled high piers | |
CN207121902U (en) | Multilevel hierarchy post jacking armored concrete pretensioned prestressing hollow square pile | |
CN204645056U (en) | A kind of combined type double-row pile foundation pit support structure | |
CN216339318U (en) | Template device is consolidated to bank protection for hydraulic construction engineering | |
CN204060047U (en) | There is the super-large water tank of breast wall type without stake shallow foundation float Structure | |
CN204385179U (en) | The assembled precoated plate of a kind of anaerobic digestor | |
CN213061706U (en) | Automatic maintenance system of pier stud |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20121114 Termination date: 20131227 |