CN202519631U - Emptying gate - Google Patents
Emptying gate Download PDFInfo
- Publication number
- CN202519631U CN202519631U CN2012201713318U CN201220171331U CN202519631U CN 202519631 U CN202519631 U CN 202519631U CN 2012201713318 U CN2012201713318 U CN 2012201713318U CN 201220171331 U CN201220171331 U CN 201220171331U CN 202519631 U CN202519631 U CN 202519631U
- Authority
- CN
- China
- Prior art keywords
- embedded
- flashboard
- lock frame
- anchoring bolts
- nut
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Abstract
The utility model discloses an emptying gate, which comprises a gate frame vertically arranged on a civil engineering embedded steel plate and a flashboard arranged on the gate frame, wherein a hoist which is used for driving the flashboard to move up and down along the gate frame is arranged above the gate frame, a screw rod on the hoist is connected with the flashboard, the gate frame is arranged on the civil engineering embedded steel plate through a plurality of embedded foundation bolts, one end of each embedded foundation bolt is provided with a connecting block connected with the civil engineering embedded steel plate, each of the embedded foundation bolt is provided with a screw nut 1 and a screw nut 2 which are matched with the embedded foundation bolt through screw threads, the gate frame is provided with screwed holes matched with the embedded foundation bolts, the embedded foundation bolts penetrate into the screwed holes, and the gate frame is positioned between the screw nut 1 and the screw nut 2. According to the emptying gate, the installation time is shortened, deformation in the process of installation and secondary equipment grouting can be prevented, accurate adjustment work and necessary reworking after the secondary grouting are saved, and the emptying gate has a simple structure, and is convenient to use and popularize.
Description
Technical field
The utility model relates to a kind of gate, particularly relates to a kind of emptying gate.
Background technology
Emptying gate is widely used among the engineering of various water treatments.At present, the installation of emptying gate relatively expends time in, and in the operating process; Expend great amount of manpower, after emptying gate is installed, needed back-grouting; Existing emptying gate is easy to generate distortion when back-grouting, even the work of doing over again can occur; Use very inconvenience, demand urgently improving.
The utility model content
The purpose of the utility model is to overcome above-mentioned deficiency of the prior art, and a kind of emptying gate is provided.This emptying gate has shortened the set-up time, can prevent in the process of installation and equipment back-grouting, to deform, and saved accurate adjustment work after the back-grouting and the necessary work of doing over again, and it is simple in structure, easy to use, is convenient to promote the use of.
For realizing above-mentioned purpose; The technical scheme that the utility model adopts is: a kind of emptying gate; Comprise the lock frame that vertically is installed on the civil engineering pre-embedded steel slab, be installed in the flashboard on the lock frame, the top of said lock frame is equipped with and is used to drive the headstock gear that flashboard moves up and down along the lock frame, and the screw rod on the said headstock gear is connected with flashboard; It is characterized in that: said lock frame is installed on the civil engineering pre-embedded steel slab through a plurality of pre-embedded anchoring bolts; One end of said pre-embedded anchoring bolts is provided with the contiguous block that is connected with the civil engineering pre-embedded steel slab, is equipped with on the said pre-embedded anchoring bolts and nut of pre-embedded anchoring bolts threaded engagement one and nut two, offers on the said lock frame and the suitable screwed hole of said pre-embedded anchoring bolts; Said pre-embedded anchoring bolts penetrates said screwed hole, and said lock frame is between nut one and nut two.
Above-mentioned a kind of emptying gate is characterized in that: offer through hole on the said contiguous block, an end of said pre-embedded anchoring bolts is installed in the said through hole.
Above-mentioned a kind of emptying gate is characterized in that: the left side and the right side that are positioned at flashboard on the said lock frame are provided with guide rod, offer the chute that supplies flashboard to move up and down on the said guide rod.
Above-mentioned a kind of emptying gate is characterized in that: the top of said flashboard is provided with otic placode one and otic placode two, between said otic placode one and the otic placode two connecting rod is installed, and the lower end of said screw rod is equipped with sleeve, and said jacket casing is on connecting rod.
Above-mentioned a kind of emptying gate is characterized in that: said contiguous block is processed by steel plate, and said flashboard and lock frame are processed by cast iron.
Above-mentioned a kind of emptying gate is characterized in that: said contiguous block is welded on the civil engineering pre-embedded steel slab, and an end of said pre-embedded anchoring bolts is welded on the contiguous block.
The utility model compared with prior art has the following advantages:
1, the utility model is simple in structure, and novel and reasonable design is easy to install.
2, the utility model is through being provided with pre-embedded anchoring bolts; Nut one and nut two with the pre-embedded anchoring bolts threaded engagement are installed on the said pre-embedded anchoring bolts; The installation of this emptying gate can be made things convenient for through pre-embedded anchoring bolts, simultaneously, the position of lock frame can be adjusted through the cooperation of nut one and nut two; It uses more convenient, and long service life.
3, the realization cost of the utility model is low, and result of use is good, is convenient to promote the use of.
In sum, the utility model is simple in structure, novel and reasonable design; Functional reliability is high; Long service life has been simplified the Installation and Debugging program, has shortened the set-up time; Can prevent in the process of installation and equipment back-grouting, to deform, save accurate adjustment work after the back-grouting and the necessary work of doing over again.
Through accompanying drawing and embodiment, the technical scheme of the utility model is done further detailed description below.
Description of drawings
Fig. 1 is the overall structure sketch map of the utility model.
Fig. 2 is the enlarged drawing at A place among Fig. 1.
Fig. 3 is the annexation sketch map of the utility model pre-embedded anchoring bolts and lock frame.
Fig. 4 is the structural representation of the utility model guide rod.
Description of reference numerals:
1-civil engineering pre-embedded steel slab; The 2-flashboard; 3-lock frame;
The 4-guide rod; The 4-1-chute; The 5-baffle plate;
The 6-headstock gear; The 7-screw rod; The 8-contiguous block;
The 9-pre-embedded anchoring bolts; 10-nut one; 11-nut two;
The 12-connecting rod; 13-otic placode one; The 14-sleeve;
15-otic placode two.
The specific embodiment
A kind of emptying gate as shown in figures 1 and 3; Comprise the lock frame 3 that vertically is installed on the civil engineering pre-embedded steel slab 1, be installed in the flashboard 2 on the lock frame 3; The top of said lock frame 3 is equipped with and is used to drive the headstock gear 6 that flashboard 2 moves up and down along lock frame 3; Screw rod 7 on the said headstock gear 6 is connected with flashboard 2, and said lock frame 3 is installed on the civil engineering pre-embedded steel slab 1 through a plurality of pre-embedded anchoring bolts 9, and an end of said pre-embedded anchoring bolts 9 is provided with the contiguous block 8 that is connected with civil engineering pre-embedded steel slab 1; Nut 1 and nut 2 11 with pre-embedded anchoring bolts 9 threaded engagement are installed on the said pre-embedded anchoring bolts 9; Offer the screwed hole suitable with said pre-embedded anchoring bolts 9 on the said lock frame 3, said pre-embedded anchoring bolts 9 penetrates said screwed hole, and said lock frame 3 is between nut 1 and nut 2 11.Offer through hole on the said contiguous block 8, an end of said pre-embedded anchoring bolts 9 is installed in the said through hole.Preferred way is, said contiguous block 8 is processed by steel plate, and said flashboard 2 and lock frame 3 are processed by cast iron.
In conjunction with Fig. 1 and Fig. 4, the left side and the right side that are positioned at flashboard 2 on the said lock frame 3 are provided with guide rod 4, offer the chute 4-1 that supplies flashboard 2 to move up and down on the said guide rod 4.Can make things convenient for flashboard 2 to move up and down freely.
As shown in Figure 2, the top of said flashboard 2 is provided with otic placode 1 and otic placode 2 15, between said otic placode 1 and the otic placode 2 15 connecting rod 12 is installed, and the lower end of said screw rod 7 is equipped with sleeve 14, and said sleeve 14 is enclosed within on the connecting rod 12.
As shown in Figure 3, said contiguous block 8 is welded on the civil engineering pre-embedded steel slab 1, and an end of said pre-embedded anchoring bolts 9 is welded on the contiguous block 8.
During use; Be assemblied on the lock frame 3 shifting to an earlier date prefabricated pre-embedded anchoring bolts 9, on the pre-embedded anchoring bolts 9 and be positioned at nut 2 11 and the nut 1 of back of the front of lock frame 3, purpose is a stepping brake frame 3; Select several contiguous blocks 8 of naming a person for a particular job to be welded on the civil engineering pre-embedded steel slab 1 earlier; With the levelness and the verticality of adjustment such as spirit level, ruler and line bob lock frame 3, satisfy standard and designing requirement after, tighten nut 1 and nut 2 11; Fixed, be welded on all pre-embedded anchoring bolts 9 on the civil engineering pre-embedded steel slab 1 and (will guarantee welding quality).After treating that lock frame 3 installs; Headstock gear 6 and screw rod 7 are installed; Said headstock gear 6 is installed on the baffle plate 5 of lock frame 3 tops, and the screwed hole of reserving on said screw rod 7 and the baffle plate 5 is suitable, in installation process, should guarantee the verticality of screw rod 7 and the concentricity of screw rod 7 and headstock gear 6.After treating that all install.Open headstock gear 6, assurance flashboard 2 can be opened freely in lock frame 3, and screw rod 7 can go up and down not have freely jitter phenomenon, then installation qualification in headstock gear 6.After equipment installs, need carry out the back-grouting of equipment, purpose is sealed water and fixed gate exactly; Concrete operations are following: before the equipment back-grouting, open headstock gear 6, screw rod 7 can go up and down freely in headstock gear 6; Flashboard 2 can be opened in lock frame 3 flexibly; Carry out the back-grouting of equipment then, during grouting around lock frame 3 the supporting template, template support should be solid and template with lock frame 3, template contacts with template should be tight.Finished product after the grouting just can be solid and attractive in appearance.In filling process, to smear the thin concrete of one deck all around after grouting finishes, for the concrete tamping again lock frame 3 inwalls.The utility model is through being provided with pre-embedded anchoring bolts 9; Nut 1 and nut 2 11 with pre-embedded anchoring bolts 9 threaded engagement are installed on the said pre-embedded anchoring bolts 9; The installation of this emptying gate can be made things convenient for through pre-embedded anchoring bolts 9, simultaneously, the position of lock frame 3 can be adjusted through the cooperation of nut 1 and nut 2 11; It uses more convenient, and long service life.
The above; It only is the preferred embodiment of the utility model; Be not that the utility model is done any restriction; Every according to the utility model technical spirit to any simple modification, change and equivalent structure transformation that above embodiment did, all still belong in the protection domain of the utility model technical scheme.
Claims (6)
1. emptying gate; Comprise the lock frame (3) that vertically is installed on the civil engineering pre-embedded steel slab (1) and be installed in the flashboard (2) on the lock frame (3); The top of said lock frame (3) is equipped with and is used to drive the headstock gear (6) that flashboard (2) moves up and down along lock frame (3); Screw rod (7) on the said headstock gear (6) is connected with flashboard (2); It is characterized in that: said lock frame (3) is installed on the civil engineering pre-embedded steel slab (1) through a plurality of pre-embedded anchoring bolts (9); One end of said pre-embedded anchoring bolts (9) is provided with the contiguous block (8) that is connected with civil engineering pre-embedded steel slab (1), and nut one (10) and nut two (11) with pre-embedded anchoring bolts (9) threaded engagement are installed on the said pre-embedded anchoring bolts (9), offers on the said lock frame (3) and the suitable screwed hole of said pre-embedded anchoring bolts (9); Said pre-embedded anchoring bolts (9) penetrates said screwed hole, and said lock frame (3) is positioned between nut one (10) and the nut two (11).
2. a kind of emptying gate according to claim 1 is characterized in that: said contiguous block offers through hole on (8), and an end of said pre-embedded anchoring bolts (9) is installed in the said through hole.
3. a kind of emptying gate according to claim 1 and 2 is characterized in that: the left side and the right side that are positioned at flashboard (2) on the said lock frame (3) are provided with guide rod (4), offer the chute (4-1) that supplies flashboard (2) to move up and down on the said guide rod (4).
4. a kind of emptying gate according to claim 1 and 2; It is characterized in that: the top of said flashboard (2) is provided with otic placode one (13) and otic placode two (15); Between said otic placode one (13) and the otic placode two (15) connecting rod (12) is installed; The lower end of said screw rod (7) is equipped with sleeve (14), and said sleeve (14) is enclosed within on the connecting rod (12).
5. a kind of emptying gate according to claim 1 and 2 is characterized in that: said contiguous block (8) is processed by steel plate, and said flashboard (2) and lock frame (3) are processed by cast iron.
6. a kind of emptying gate according to claim 5 is characterized in that: said contiguous block (8) is welded on the civil engineering pre-embedded steel slab (1), and an end of said pre-embedded anchoring bolts (9) is welded on the contiguous block (8).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012201713318U CN202519631U (en) | 2012-04-20 | 2012-04-20 | Emptying gate |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012201713318U CN202519631U (en) | 2012-04-20 | 2012-04-20 | Emptying gate |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202519631U true CN202519631U (en) | 2012-11-07 |
Family
ID=47102586
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012201713318U Expired - Fee Related CN202519631U (en) | 2012-04-20 | 2012-04-20 | Emptying gate |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202519631U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103850330A (en) * | 2014-02-21 | 2014-06-11 | 武汉圣禹排水系统有限公司 | Ascending and descending type height-adjustable overflow plate structure |
CN105586855A (en) * | 2015-09-28 | 2016-05-18 | 中国电建集团贵阳勘测设计研究院有限公司 | Installation method and structure for scow track of water intake trash rack |
CN106759142A (en) * | 2017-01-20 | 2017-05-31 | 中冶沈勘工程技术有限公司 | A kind of bridges and culverts valve system |
CN107558598A (en) * | 2017-09-30 | 2018-01-09 | 武汉圣禹排水系统有限公司 | Bottom-open type weir gate system and bottom-open type weir gate installation method |
-
2012
- 2012-04-20 CN CN2012201713318U patent/CN202519631U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103850330A (en) * | 2014-02-21 | 2014-06-11 | 武汉圣禹排水系统有限公司 | Ascending and descending type height-adjustable overflow plate structure |
CN105586855A (en) * | 2015-09-28 | 2016-05-18 | 中国电建集团贵阳勘测设计研究院有限公司 | Installation method and structure for scow track of water intake trash rack |
CN106759142A (en) * | 2017-01-20 | 2017-05-31 | 中冶沈勘工程技术有限公司 | A kind of bridges and culverts valve system |
CN107558598A (en) * | 2017-09-30 | 2018-01-09 | 武汉圣禹排水系统有限公司 | Bottom-open type weir gate system and bottom-open type weir gate installation method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202519631U (en) | Emptying gate | |
CN201794168U (en) | Steel column butt-joint connector | |
CN102615277A (en) | Construction method for mounting rails of buggy ladle | |
CN205172592U (en) | A structure that is used for ore deposit to dig on method platform truck embedding slot saying fixed mounting | |
CN205219364U (en) | Concrete core appearance terminal surface is mended paper -back edition and is put | |
CN206986643U (en) | A kind of transverse direction pulls the hydraulic haulage winch of railway switch | |
CN201474703U (en) | Bearing structure of consolidated ring of hydraulic tunnel | |
CN202416316U (en) | Permanent anchor cable pier head model for quick supporting | |
CN215104799U (en) | Town road bridge crack reinforced structure | |
CN209874074U (en) | Porous inclined plane slip casting embedded pipe | |
CN101565953A (en) | Method for fixing pile head in filling pile static loading test | |
CN211228925U (en) | Concrete embedded part for civil engineering | |
CN204662396U (en) | A kind of tilting for high slope blocks dirty drift structure | |
CN204282609U (en) | A kind of separate type precast truss frame floor support plate | |
CN209368727U (en) | A kind of explosion-proof lifting pillar roadblock for stopping vehicles | |
CN208559697U (en) | A kind of support anchor structure of floating on water photovoltaic plant | |
CN202629489U (en) | Anchor fixing mechanism of machine tool | |
CN202012079U (en) | Pile anchor for cable crane | |
CN205857237U (en) | A kind of rock anchor base structure being applicable to mountain region photovoltaic module | |
CN205530326U (en) | Tower crane landing leg anchor | |
CN203320487U (en) | Gate jacking reinforcing device | |
CN209495067U (en) | Construction Pipe leakage stopper | |
CN203487546U (en) | Basic module for disposing distribution box | |
CN203895226U (en) | Mobile transformer refueling truck | |
CN219491092U (en) | Construction anti-seepage device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20121107 Termination date: 20170420 |