CN202441042U - Novel steel pipe scaffold - Google Patents
Novel steel pipe scaffold Download PDFInfo
- Publication number
- CN202441042U CN202441042U CN2012200408445U CN201220040844U CN202441042U CN 202441042 U CN202441042 U CN 202441042U CN 2012200408445 U CN2012200408445 U CN 2012200408445U CN 201220040844 U CN201220040844 U CN 201220040844U CN 202441042 U CN202441042 U CN 202441042U
- Authority
- CN
- China
- Prior art keywords
- scaffold
- tube
- steel pipe
- vertical
- novel steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Abstract
The utility model belongs to a scaffold for buildings, and particularly relates to a novel steel pipe scaffold. The novel steel pipe scaffold comprises an arc-shaped steel pipe frame, a crossed rod, a scaffold board and an adjustable base, wherein vertical pipes are arranged at two sides of the arc-shaped steel pipe frame; pedals are arranged in the middles of the outer sides of the vertical pipes; the upper parts of the vertical pipes are welded together with a cross pipe and an arc-shaped supporting pipe; connecting pipes are arranged on the tops of the vertical pipes; and holes are arranged on the top of the connecting pipes and at the bottoms of the vertical pipes; and foot blocking rods are additionally arranged between holes under the two vertical pipes at the outer side of the scaffold. The novel steel pipe scaffold has the advantages that structure is simple, installation is convenient, and appearance is attractive, materials are saved, strength is good and the like, and is safe and reliable.
Description
Technical field
The utility model belongs to scaffold for building, especially a kind of novel steel tube scaffold.
Background technology
Present rapid development of social economy, building trade are in advance, and existing all kinds of scaffolds have been widely used in the realm of building construction, and old job practices and instrument progressively are eliminated, and are substituted continual renovation, constantly perfect by more advanced technical equipment.The scaffold of using with regard to building operations also is the same, and is through repeatedly improving, progressively perfect.But in use still there are some problems, complex structure, cost is higher, and the construction safety performance is poor, and spare and accessory parts are more, and management is inconvenient, and installs and waste time and energy, and old shape steel tube shelf structure is unreasonable, intensity is low.
Summary of the invention
The utility model provides a kind of novel building construction simple in structure, easy for installation, that intensity is good, safe and reliable to use the gate-type steel pipe scaffold to above deficiency.
The utility model solves the technical scheme that its technical problem adopted:
A kind of novel steel tube scaffold comprises camber steel pipe frame, crossbar, scaffold floor, adjustable base; Its camber steel pipe frame both sides are vertical tube; The outer middle side part of vertical tube is provided with foot rest; Riser upper portions and transverse tube and circular arc stay pipe weld together, and the top of vertical tube is provided with tube connector, and tube connector top and vertical tube bottom are provided with the hole; Between the Kong Yukong below two vertical tubes of the scaffold outside, set up the retaining foot lever; Be welded with crossbar on two vertical tubes of the described scaffold outside; Described scaffold bottom camber steel pipe frame is equipped with adjustable base; Described vertical tube bottom is identical with the hole size at tube connector top.
Insert on the tube connector of lower floor's camber steel pipe frame riser upper end upper strata camber steel pipe frame vertical tube lower end during installation, inserts the retaining foot lever again and get final product; Scaffold floor is placed on the transverse tube top, makes things convenient for personnel to walk about.The beneficial effect of the utility model is:
Simple in structure, easy for installation, handsome in appearance, save advantages such as material, intensity are good, safe and reliable.
Description of drawings
Fig. 1 is the structural representation of the utility model combination.
Fig. 2 is the structural representation of the utility model camber steel pipe frame.
Among the figure, 1. vertical tube; 2. transverse tube; 3. arc stay pipe; 4. tube connector; 5. hole; 6. foot rest; 7. crossbar; 8. scaffold floor; 9. retaining foot lever; 10. adjustable base.
The specific embodiment
Shown in accompanying drawing; A kind of novel steel tube scaffold comprises camber steel pipe frame, crossbar 7, scaffold floor 8, adjustable base 10; Its camber steel pipe frame both sides are vertical tube 1, and vertical tube 1 outer middle side part is provided with foot rest 6, and vertical tube 1 top and transverse tube 2 weld together with circular arc stay pipe 3; The top of vertical tube 1 is provided with tube connector 4, and tube connector 4 tops and vertical tube 1 bottom are provided with hole 5; Between the Kong Yukong below two vertical tubes of the scaffold outside, set up retaining foot lever 9; Be welded with crossbar 7 on two vertical tubes of the described scaffold outside; Described scaffold bottom camber steel pipe frame is equipped with adjustable base 10; Described vertical tube 1 bottom is identical with the hole size at tube connector 4 tops.
Insert on the tube connector 4 of lower floor camber steel pipe frame vertical tube 1 upper end upper strata camber steel pipe frame vertical tube 1 lower end during installation, inserts retaining foot lever 9 again and get final product; Scaffold floor 8 is placed on transverse tube 2 tops, makes things convenient for personnel to walk about.
Claims (4)
1. novel steel tube scaffold; Comprise camber steel pipe frame, crossbar, scaffold floor, adjustable base; It is characterized in that: its camber steel pipe frame both sides are vertical tube, and the outer middle side part of vertical tube is provided with foot rest, and riser upper portions and transverse tube and circular arc stay pipe weld together; The top of vertical tube is provided with tube connector, and tube connector top and vertical tube bottom are provided with the hole; Between the Kong Yukong below two vertical tubes of the scaffold outside, set up the retaining foot lever.
2. a kind of novel steel tube scaffold according to claim 1 is characterized in that: be welded with crossbar on two vertical tubes of the scaffold outside.
3. a kind of novel steel tube scaffold according to claim 1 is characterized in that: scaffold bottom camber steel pipe frame is equipped with adjustable base.
4. a kind of novel steel tube scaffold according to claim 1 is characterized in that: the vertical tube bottom is identical with the hole size at tube connector top.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012200408445U CN202441042U (en) | 2012-02-09 | 2012-02-09 | Novel steel pipe scaffold |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012200408445U CN202441042U (en) | 2012-02-09 | 2012-02-09 | Novel steel pipe scaffold |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202441042U true CN202441042U (en) | 2012-09-19 |
Family
ID=46822496
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012200408445U Expired - Fee Related CN202441042U (en) | 2012-02-09 | 2012-02-09 | Novel steel pipe scaffold |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202441042U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104389415A (en) * | 2014-11-26 | 2015-03-04 | 樊守立 | Scaffold |
-
2012
- 2012-02-09 CN CN2012200408445U patent/CN202441042U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104389415A (en) * | 2014-11-26 | 2015-03-04 | 樊守立 | Scaffold |
CN104389415B (en) * | 2014-11-26 | 2016-08-24 | 樊守立 | Scaffold |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202347830U (en) | Simple construction operation frame | |
CN202441042U (en) | Novel steel pipe scaffold | |
CN205801953U (en) | A kind of concrete pipe sheet bracket | |
CN202672687U (en) | Three-point lifting scaffolding | |
CN204023417U (en) | For building the bearing pin bracket of high pier 0# block concrete | |
CN203034769U (en) | Scaffold for building construction | |
CN203846780U (en) | Semi-automatic lifting type operating platform device | |
CN202055509U (en) | Upright rod installation structure of directly-inserted scaffold | |
CN204174915U (en) | Scaffold | |
CN203666706U (en) | Simple two-wheel lever transportation tool | |
CN206917061U (en) | A kind of steel construction assembled wallboard | |
CN202731261U (en) | Movable scaffold with adjustable height | |
CN202509750U (en) | Height-adjustable type scaffold | |
CN207538481U (en) | A kind of floor height changeable type input and output material platform | |
CN203769634U (en) | Adjustable engineering climbing ladder | |
CN203270785U (en) | Brace system used for steel structure | |
CN202467138U (en) | Mobile scaffold for building construction | |
CN204059922U (en) | Walking supporting component | |
CN204163367U (en) | Cat ladder frame operating platform | |
CN203817686U (en) | Welding fixture for connecting rack | |
CN204418696U (en) | Vertical reinforcement spreading lifting assistor | |
CN202483083U (en) | Concrete split heads | |
CN204194489U (en) | Steel pipe brace | |
CN203755627U (en) | Movable type scaffold | |
CN204893349U (en) | A special top utensil for high platform equipment fixing |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20120919 Termination date: 20150209 |
|
EXPY | Termination of patent right or utility model |