CN202430978U - Removable scaffold - Google Patents

Removable scaffold Download PDF

Info

Publication number
CN202430978U
CN202430978U CN2011204661024U CN201120466102U CN202430978U CN 202430978 U CN202430978 U CN 202430978U CN 2011204661024 U CN2011204661024 U CN 2011204661024U CN 201120466102 U CN201120466102 U CN 201120466102U CN 202430978 U CN202430978 U CN 202430978U
Authority
CN
China
Prior art keywords
steel pipe
ladder
hook
pipe
basic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011204661024U
Other languages
Chinese (zh)
Inventor
刘柳炼
邱黎
何汉林
林培东
丘秉达
赵升华
鞠家龙
黄泽红
叶群英
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGDONG FOURTH CONSTRUCTION Co
Original Assignee
GUANGDONG FOURTH CONSTRUCTION Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGDONG FOURTH CONSTRUCTION Co filed Critical GUANGDONG FOURTH CONSTRUCTION Co
Priority to CN2011204661024U priority Critical patent/CN202430978U/en
Application granted granted Critical
Publication of CN202430978U publication Critical patent/CN202430978U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Ladders (AREA)

Abstract

The utility model relates to a scaffold in building construction and provides a removable scaffold which comprises more basic ladders in butt joint, wherein each basic ladder comprises two front steel pipes, two rear steel pipes, and a plurality of cross rods, which are welded, the cross rods are respectively used for being welded with the front steel pipe and the rear steel pipe on the left side and the right side to form a left long ladder and a right long ladder, the front cross rods are perpendicularly welded and connected with the front and the rear steel pipes of the left long ladder and the right long ladder, the end parts of the front and the rear steel pipes of each basic ladder are provided with connecting parts and transverse penetration holes, a casing pipe connecting piece is sleeved on the connecting part of the two basic ladders in butt joint and tightened, and an L-shaped hook is further welded or connected to the end of the basic ladder at the top. According to the utility model, the setting up and dismantling workloads are small, the moving is convenient, manpower and materials for setting up or dismantling the scaffold can be effectively reduced, the scaffold is very suitable for small-scale wall surface construction work, single procedure construction work, and engineering in which large building materials are mounted high.

Description

Portable scaffold
Technical field
The utility model relates to the scaffold in the building operations, particularly a kind of movably scaffold.
Background technology
Construct at external wall, in the maintenance engineering; Usually need set up scaffold, the closed-in construction that scaffold generally is formed by connecting mutually with removably through various connection fasteners on many montants, long transverse lever and hyphen bar sets up operations platoon's frame in the scaffold; Begin upwards to set up by ground when setting up along building; Make scaffold be covered with the whole construction metope, the constructor is that operating platform is constructed to the wall equal-height position of building with the operation framed bent, and it is big to set up or remove this scaffold work amount; Therefore can not remove easily after putting up; So that use during wall construction next time, relatively be fit to large tracts of land, long construction period, wall decoration engineering that operation is many, the weak point of this scaffold is: set up human and material resources that scaffold wants labor and need the construction period of length.
Summary of the invention
The purpose of the utility model is to propose a kind of portable scaffold; This scaffold to build and remove workload little; Have advantages such as easy to use, removable, convenient transportation, the engineering that is very suitable for single operation construction works and constructional materials is installed at the metope equal-height position.
The purpose of the utility model can realize by the following technical programs:
Portable scaffold includes steel pipe and the many ladders basically that cross bar constitutes behind 2 preceding steel pipes and 2, and cross bar comprises left cross bar, right cross bar and front rail, it is characterized in that:
Many left cross bars will be positioned at the vertical long ladder in a left side that is welded into the back steel pipe of preceding steel pipe on the left side, be 400-600mm at the preceding steel pipe on the left side and the spacing between the steel pipe of back, be spaced apart 350-500mm between two left cross bars; Many right cross bars will be positioned at that the preceding steel pipe on the right is vertical with the back steel pipe to be welded into right long ladder, the preceding steel pipe on the right and after spacing between the steel pipe be 400-600mm, be spaced apart 350-500mm between two right cross bars; The preceding steel pipe and right long terraced vertical being welded to connect of preceding steel pipe of many front rails and the long ladder in a left side, front rail is also perpendicular to left cross bar and right cross bar; The long ladder in a left side is 600-1000 mm with spacing between the long ladder in the right side, is spaced apart 350-1000mm between two front rails;
Preceding steel pipe is 3000-5000mm with the length of back steel pipe;
The removable connection of steel pipe after having at least 1 rear transverse rod to incite somebody to action terraced basically 2;
The preceding steel pipe of left cross bar distance that is positioned at long terraced two ends, a left side and back steel pipe end be 200mm at least; The preceding steel pipe of right cross bar distance that is positioned at right long terraced two ends and back steel pipe end be 200mm at least; The preceding steel pipe end of front rail distance at steel pipe two ends 200mm at least before being positioned at; Has cross-perforating near the preceding steel pipe of basic ladder and the back steel tube end part; Also include the cover pipe connections; The cover pipe connections has at least 2 spacings and is connected perforation with the corresponding sleeve pipe of the cross-perforating of basic terraced terminal part; The preceding steel pipe of 2 or a plurality of basic ladders prolonged with back steel pipe alignment be connected; The cover pipe connections is set in the end of preceding steel pipe with the back steel pipe of connect 2 basic ladders, the sleeve pipe that bolt inserts the cover pipe connections connect perforation and pass before steel pipe or back steel pipe cross-perforating and use nut screwing clamping, connect the back topmost first basic ladder be that the top is terraced.
The last end of top ladder has L shaped hook, an end transverse weld of L shaped hook or be connected on the ladder of top.
When construction needs scaffold; Select the terraced basically of proper height according to metope height or construction height; A plurality of basic ladders are begun upwards to assemble through the cover pipe connections by ground by the construction metope, connect the top ladder topmost, the hook that the top is terraced hangs on the top of a wall or the crossbeam.When the scaffold that is overlapped was higher, the middle part can adopt connector and support bar with basic ladder or top ladder removable fixed connection of connector with the metope of constructing.
Move for convenient, usually at the preceding steel pipe of the basic ladder of bottommost with the welding of steel pipe lower surface, back or be connected with cushion block, preceding steel pipe that again will basic ladder is positioned in the channel-section steel groove together with cushion block with back steel pipe end face, channel-section steel is supporting portable scaffold and is standing on the ground.
When moving,, long ladder is moved along channel-section steel with loop wheel machine or the artificial length ladder that laterally promotes.
The utlity model has following substantive distinguishing features and progress:
1, the utility model is simple in structure, practical, adopts multistage connected mode structure, can convenient and swiftly build the long scaffold of superelevation, and convenient transportation;
2, because the removable characteristics of the utility model; Large-area wall construction need not built too much scaffold, and building 1-3 on general just can convenient construction, thereby can effectively reduce the manpower and materials of building or dismantle scaffold; Improve efficiency of construction, reduce construction costs.
Description of drawings
Fig. 1 is the structural representation of the basic ladder of the utility model.
Fig. 2 is a kind of structural representation of the top ladder of the utility model.
Fig. 3 is another structural representation of the top ladder of the utility model.
Fig. 4 is the basic ladder and the top ladder syndeton sketch map of the utility model.
The specific embodiment
Below in conjunction with accompanying drawing the utility model is described further:
Embodiment 1
With reference to figure 1, Fig. 3 and Fig. 4, a kind of portable scaffold includes steel pipe 2 and the many ladders basically that cross bar constitutes behind 2 preceding steel pipes 1 and 2, and cross bar comprises left cross bar 3, right cross bar 4 and front rail 5.
The preceding steel pipe 1 that many left cross bars 3 will be positioned at the left side and back steel pipe 2 are welded into the long ladder in a left side with the spacing of 600mm, are spaced apart 500mm between two left cross bars 3; Be positioned at the preceding steel pipe 1 of left cross bar 3 distances and the back steel pipe 2 terminal 250mm of being at the terraced two ends of length, a left side, this section is left terraced connecting portion.
The preceding steel pipe 1 that many right cross bars 4 will be positioned at the right and back steel pipe 2 are welded into right long ladder with the spacing of 600mm, are spaced apart 500mm between two right cross bars 4; Be positioned at the preceding steel pipe 1 of right cross bar 4 distances and the back steel pipe 2 terminal 250mm of being at the terraced two ends of right length, this section is right terraced connecting portion.
Many front rails 5 are with long ladder in a left side and right long terraced preceding steel pipe 1 vertical being welded to connect, and front rail 5 is also perpendicular to left cross bar 3 and right cross bar 4; The long ladder in a left side is 800 mm with spacing between the right long ladder, is spaced apart 500 mm or 1000 mm between two front rails 5, and preceding steel pipe 1 end of front rail 5 distances at steel pipe 1 two ends is 250mm before being positioned at.
Left side cross bar 3 is positioned at same plane with right cross bar 4; Front rail 5 is positioned at same plane with left cross bar 3 with right cross bar 4; Preceding steel pipe 1 is 3000-5000mm with the length of back steel pipe 2.
The removable connection of steel pipe after having at least 1 rear transverse rod 9 to incite somebody to action terraced basically 2.
The left terraced connecting portion and the right terraced connecting portion of basic ladder have cross-perforating 10; Also include cover pipe connections 6; Cover pipe connections 6 has at least 2 spacings and is connected perforation 60 with the cross-perforating 10 corresponding sleeve pipes of basic terraced terminal part; 2 alignment prolong and are connected with the back steel pipe with the preceding steel pipe 1 of 2 or a plurality of basic ladders; Cover pipe connections 6 is set in the left terraced connecting portion and the right terraced connecting portion of 2 basic ladders that connect, and bolt 61 inserts the cross-perforating 10 that the sleeve pipe that overlaps pipe connections 6 connects perforation 60 and passes left terraced connecting portion or right terraced connecting portion, and connecting first basic ladder of the top, back is the top ladder.
The last end of top ladder has L shaped hook (7); One end of L shaped hook (7) can laterally be directly welded on the ladder of top; In the present embodiment; Use for convenient, the last terminal transverse weld of top ladder or the removable hook pipe 8 that is connected with, hook pipe 8 has been horizontally set with hook fixing hole 80; L shaped hook 7 has hook horizontal perforation 70, and L shaped hook 7 one ends penetrate hook pipe 8 hook fixing holes 80 interior and that pass on the hook pipe 8 with bolt 71 fixedly becomes the scalable hook with hook horizontal perforation 70 backs of linking up with on 7 with nut.
Specifically with reference to figure 4; Engineering so that wallboard to be installed on body of wall is an example; Select 2 ladders basically according to the height of body of wall; The height sums that require 2 basic ladders are a little more than the body of wall height, vertically place the 1st ladder basically in that the construction body of wall is other earlier, the sleeve pipe that passes cover pipe connections 6 at the upper end of this basic ladder terraced connecting portion in a left side and right terraced connecting portion slip joint casing connector 6 and with bolt 61 is connected bore a hole 60 with preceding steel pipe 1 with after cross-perforating 10 on the steel pipe 2 make firm the connection; Use lifting gear to rise the 2nd ladder basically; The left terraced connecting portion and the right terraced connecting portion of this basic terraced lower end are inserted into respectively in the cover pipe connections 6 that has been connected on the 1st basic ladder; And with the sleeve pipe that bolt 61 passes cover pipe connections 6 connect steel pipe 1 before perforation 60 and the 2nd the basic ladder with after cross-perforating 10 on the steel pipe 2 make firm be connected fastening; Just prolonging along the body of wall alignment of such 2 basic ladders connects into; Scaffold, the basic ladder that is positioned at the scaffold bottom are the bottom ladder, and the basic ladder that is positioned at scaffold top is the top ladder; Ladder and the fair mutually horizontal removable coupling hook pipe 8 in position in body of wall top at the top; The end that hook 7 is had hook hole 70 penetrates in the hook pipe 8, regulates distance that hook 7 penetrates hook pipe 8 and makes the other end of hook 7 stretch out the top ladder tightly to hang on the top of a wall or the crossbeam, and the hook fixing hole 80 that passes on the hook pipe 8 with bolt 71 at last is also fastening with nut with the hook hole 70 on the hook 7; The upper end of scaffold is fixed on the top of a wall or the crossbeam by hook 7, and the lower end of scaffold is by ground supports.
For making scaffold more firm, the middle part can adopt connector and support bar with basic ladder or top ladder removable fixed connection of connector with the metope of constructing.
For making scaffold be easy to move; Can be before the assembling scaffold two channel-section steels 12 of parallel placement along the ground of body of wall in advance; Bottom face welding 50 * 50mm cushion block 11 of the preceding steel pipe 1 of ladder and back steel pipe 2 in the bottom; End face with the bottom ladder is positioned over together with cushion block 11 in the groove of channel-section steel 12 again, and channel-section steel 12 is supporting scaffold on ground.
During construction, the people climbs construction location by long ladder in a left side or right long ladder, and the part (for example wallboard) of constructing can be by the side direction handling of scaffold to construction location; Can press vertically operation side by side of metope, after one section wall construction is accomplished scaffold a plurality of constructors that stand respectively up and down; Need not to remove scaffold; After the constructor leaves scaffold, promote scaffold along channel-section steel 12 it is moved to other construction locations, carry out the constructing operation of next section metope; After whole wall construction is accomplished, remove hook 7 and top ladder respectively by above-mentioned opposite operation.
Present embodiment has characteristics easy to install and use, can effectively reduce the engineering quantity that scaffolds erecting, and has reduced construction costs, and efficiency of construction is high.
Embodiment 2
With reference to figure 2; The difference of present embodiment and embodiment 1 is: the last end of top ladder has L shaped hook 7; Have a plurality of hook horizontal perforations 70 on the L shaped hook 7, an end of L shaped hook 7 laterally is posted by on the terminal preceding steel pipe of top ladder 1 and the back steel pipe 2 and with bolt 71 and passes the cross-perforating 10 of hook horizontal perforation 70 and top ladder end and use nut screwing clamping.The method for using of present embodiment is identical with embodiment 1.

Claims (6)

1. portable scaffold includes steel pipe (2) and the many ladders basically that cross bar constitutes behind 2 preceding steel pipes (1) and 2, and cross bar comprises left cross bar (3), right cross bar (4) and front rail (5), it is characterized in that:
Many left cross bars (3) will be positioned at the vertical long ladder in a left side that is welded into back steel pipe (2) of preceding steel pipe (1) on the left side; Being positioned at the preceding steel pipe (1) on the left side and the spacing between back steel pipe (2) is 400-600mm, is spaced apart 350-500mm between two left cross bars (3);
Many right cross bars (4) will be positioned at the vertical long ladder in the right side that is welded into back steel pipe (2) of preceding steel pipe (1) on the right; Being positioned at the preceding steel pipe (1) on the right is 400-600mm with the back spacing between the steel pipe (2), is spaced apart 350-500mm between two right cross bars (4);
Many front rails (5) and the long terraced preceding steel pipe (1) in a left side and vertical being welded to connect of preceding steel pipe (1) of right long ladder, front rail (5) is also perpendicular to left cross bar (3) and right cross bar (4); The long ladder in a left side is 600-1000 mm with spacing between the long ladder in the right side, is spaced apart 350-1000mm between two front rails (5);
The length of preceding steel pipe (1) and back steel pipe (2) is 3000-5000mm;
Have removable connection of steel pipe (2) behind 1 rear transverse rod (9) and basic ladder 2 at least.
2. portable scaffold according to claim 1 is characterized in that: be positioned at left cross bar (3) the distance preceding steel pipe (1) at long terraced two ends, a left side and back steel pipe (2) end 200mm at least; Be positioned at right cross bar (4) the distance preceding steel pipe (1) at right long terraced two ends and back steel pipe (2) end 200mm at least; Front rail (5) distance preceding steel pipe (1) end that is positioned at preceding steel pipe (1) two ends is 200mm at least; Has cross-perforating (10) near the preceding steel pipe (1) of basic ladder and steel pipe (2) end, back; Also include cover pipe connections (6); Cover pipe connections (6) has at least 2 spacings and is connected perforation (60) with the corresponding sleeve pipe of cross-perforating (10) of basic terraced terminal part; Alignment prolongs and is connected with back steel pipe (2) with the preceding steel pipe (1) of 2 or a plurality of basic ladders; Cover pipe connections (6) is set in the end of the preceding steel pipe (1) and the back steel pipe (2) of 2 basic ladders that connect; The sleeve pipe that bolt (61) inserts cover pipe connections (6) connects perforation (60) and passes preceding steel pipe (1) or the cross-perforating (10) of back steel pipe (2) and use nut screwing clamping, connect the back topmost first basic ladder be that the top is terraced.
3. portable scaffold according to claim 2 is characterized in that: the last end of top ladder has L shaped hook (7), and an end transverse weld of L shaped hook (7) is on the ladder of top.
4. portable scaffold according to claim 2; It is characterized in that: the last end of top ladder has L shaped hook (7); Have a plurality of hook horizontal perforations (70) on the L shaped hook (7), an end of L shaped hook (7) laterally is posted by terminal also the passing with bolt (71) of top ladder and links up with the terraced terminal cross-perforating (10) of horizontal perforation (70) and top and use nut screwing clamping.
5. portable scaffold according to claim 2; It is characterized in that: the last terminal transverse weld of top ladder or the removable hook pipe (8) that is connected with; Hook pipe (8) is provided with hook fixing hole (80); L shaped hook (7) has hook horizontal perforation (70), and L shaped hook (7) one ends penetrate in the hook pipe (8), passes the hook fixing hole (80) and the hook horizontal perforation (70) on the hook (7) of hook pipe (8) and uses nut screwing clamping with bolt (71).
6. according to described any portable scaffold of claim 2 to 5, it is characterized in that: the preceding steel pipe of the basic ladder of bottommost is with the welding of steel pipe lower end, back or be connected with cushion block (11).
CN2011204661024U 2011-11-22 2011-11-22 Removable scaffold Expired - Lifetime CN202430978U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011204661024U CN202430978U (en) 2011-11-22 2011-11-22 Removable scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011204661024U CN202430978U (en) 2011-11-22 2011-11-22 Removable scaffold

Publications (1)

Publication Number Publication Date
CN202430978U true CN202430978U (en) 2012-09-12

Family

ID=46780438

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011204661024U Expired - Lifetime CN202430978U (en) 2011-11-22 2011-11-22 Removable scaffold

Country Status (1)

Country Link
CN (1) CN202430978U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103741940A (en) * 2014-01-07 2014-04-23 肇庆新奥燃气有限公司 Border hook ladder
CN104005548A (en) * 2014-06-09 2014-08-27 山东电力建设第一工程公司 Steel structure installation scaffold
CN104179342A (en) * 2014-08-11 2014-12-03 广西壮族自治区冶金建设公司 Hanging cage and construction method thereof for mounting profiled steel sheets on steel structural workshop wall surface
CN104523175A (en) * 2014-12-19 2015-04-22 中山市新意念塑胶制品有限公司 Swimming barrel for child
CN105063321A (en) * 2015-09-26 2015-11-18 郭策 Preparation method of high-strength scaffold connecting piece
CN108643588A (en) * 2018-05-25 2018-10-12 中国建筑第八工程局有限公司 Wallboard installation exercise frame and its installation method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103741940A (en) * 2014-01-07 2014-04-23 肇庆新奥燃气有限公司 Border hook ladder
CN104005548A (en) * 2014-06-09 2014-08-27 山东电力建设第一工程公司 Steel structure installation scaffold
CN104179342A (en) * 2014-08-11 2014-12-03 广西壮族自治区冶金建设公司 Hanging cage and construction method thereof for mounting profiled steel sheets on steel structural workshop wall surface
CN104523175A (en) * 2014-12-19 2015-04-22 中山市新意念塑胶制品有限公司 Swimming barrel for child
CN105063321A (en) * 2015-09-26 2015-11-18 郭策 Preparation method of high-strength scaffold connecting piece
CN108643588A (en) * 2018-05-25 2018-10-12 中国建筑第八工程局有限公司 Wallboard installation exercise frame and its installation method

Similar Documents

Publication Publication Date Title
CN202430978U (en) Removable scaffold
CN204940915U (en) Dish button construction safety cat ladder
CN110360432A (en) A kind of installation method for external wall of high-rise building electronic display
CN104989098A (en) Laminated plate support frame
CN202430823U (en) Detachable steel bar processing protective shed
CN102817617B (en) Novel inhaul cable type shield originating backrest substrate system
CN204139631U (en) The guard rail of building site fast demountable
CN204059901U (en) A kind of high-altitude construction operation platform
CN201148726Y (en) Independent hanging scaffold super large operating platform
CN214464175U (en) Assembled shield constructs empty counterforce device that pushes away of TBM complete machine
CN106640146B (en) Three-dimensional reinforced bar net frame and concrete combined lining structure
CN201627358U (en) Large-section pressure pipeline concrete construction deformed steel formwork
CN214658693U (en) A fixed chassis for outer wall construction goes up and down
CN204552051U (en) The cradle structure of high-altitude crossbeam soffit monitoring point layout
CN210659182U (en) Adjustable moving platform for building construction
CN207465203U (en) A kind of wallboard storage rack
CN202559727U (en) Load-bearing support structure of template of overhead long-span floor slab of building
CN210713763U (en) Construction platform device
CN204510614U (en) A kind of M type roof truss
CN214399584U (en) Positioning structure of embedded sleeve of wall-attached embedded part of tower crane
CN203452373U (en) Ultrathin steel truss inclined wall formwork structure
CN219138315U (en) Construction platform for hanging basket downwards
CN211059476U (en) Pipeline erection welding steel frame for building construction
CN206815808U (en) A kind of iron oblique staircase
CN203603330U (en) Hanging piece for modularized building and modularized building structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20120912