CN202363971U CN201120417618XU CN201120417618U CN202363971U CN 202363971 U CN202363971 U CN 202363971U CN 201120417618X U CN201120417618X U CN 201120417618XU CN 201120417618 U CN201120417618 U CN 201120417618U CN 202363971 U CN202363971 U CN 202363971U
Authority
CN
China
Prior art keywords
operation monitoring
electric power
server
scheduling
data network
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201120417618XU
Other languages
Chinese (zh)
Inventor
曹良
徐春雷
李天龙
郑海燕
谢林枫
官国飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Jiangsu Fangtian Power Technology Co Ltd
Changzhou Power Supply Co of Jiangsu Electric Power Co
Original Assignee
Jiangsu Fangtian Power Technology Co Ltd
Changzhou Power Supply Co of Jiangsu Electric Power Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Fangtian Power Technology Co Ltd, Changzhou Power Supply Co of Jiangsu Electric Power Co filed Critical Jiangsu Fangtian Power Technology Co Ltd
Priority to CN201120417618XU priority Critical patent/CN202363971U/en
Application granted granted Critical
Publication of CN202363971U publication Critical patent/CN202363971U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/242Home appliances
    • Y04S20/244Home appliances the home appliances being or involving heating ventilating and air conditioning [HVAC] units

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The utility model relates to a centralized operation monitoring system of an electric power secondary system, comprising a centralized operation monitoring master station, a scheduling data network, a city scheduling center and a county scheduling center connected with the scheduling data network. The centralized operation monitoring master station comprises a database server, an acquisition server and an application server connected with the scheduling data network; And the city and county scheduling centers comprise terminal servers connected with the scheduling data network, electric power automation systems connected with the terminal servers, branch power distribution information detection systems and environmental parameters detection systems used for cooperating the work of an air-conditioning system. The electric power automation systems employ OPEN 3000 systems, the environmental parameters detection systems comprise environment humiture sensors and waterlogging sensors arranged under a machine room floor having a precise air-conditioning, and at the same time, in a power distribution cabinet, each branch is equipped with a measuring instrument used for measuring the power distribution information, such as voltage, current, power, etc.

Description

The concentrated operation monitoring system of electric power secondary system
Technical field
The utility model relates to the technical field of cities and counties' power scheduling, specifically is a kind of concentrated operation monitoring system of electric power secondary system.
Background technology
Development along with modern power network; The electrical network intellectuality has become the trend of power network development; And an important characteristic of intelligent grid is to have real-time, online and continuous security evaluation and analysis ability; Powerful early warning and prevention and control ability, and the ability of automatic trouble diagnosis, Fault Isolation and system's self-recovery, and the running status of understanding all kinds of power equipments real-time and accurately is to support the necessary condition of intelligent grid operation.Utilize The present computer technology; It is to guarantee intelligent grid safety and the important means of finding incipient fault that the communication technology and sensor technology carry out real-time monitoring to the running status of all kinds of power equipments that support the intelligent grid operation, and is the basis of monitoring various kinds of equipment running status to the data acquisition of various kinds of equipment running status with analyzing.In order to realize collection, just must set up the collection analysis platform of corresponding apparatus data to the various kinds of equipment status data.Overlap effective device data acquisition method and corresponding with it acquisition tasks execution platform and need set up one, thereby can monitor online equipment running status in real time, guarantee the safe operation of operation of power networks system in the face of numerous different types of equipment.
Summary of the invention
The technical problem that the utility model will solve provides a kind of concentrated operation monitoring system of electric power secondary system simple in structure, to realize that centralized maintenance and management are carried out in cities and counties' power scheduling.
In order to solve the problems of the technologies described above; The utility model provides a kind of concentrated operation monitoring system of electric power secondary system, comprising: concentrate operation monitoring main website, the data dispatching net that links to each other with this concentrated operation monitoring main website, control centre, city and the control centre, county that links to each other with this data dispatching net.
Said concentrated operation monitoring main website comprises: the database server, acquisition server and the application server that link to each other with said data dispatching net.Database server, acquisition server and application server are arranged in the machine room, and connect each system and equipment through the serial port terminal server through the RS485/232 serial ports.
Control centre, said city comprises with the control centre, county: the terminal server that links to each other with said data dispatching net, the power automatic system that links to each other with this terminal server, branch road power distribution information detection system and be used to cooperate the environmental parameter detection system of air-conditioning system work.Power automatic system adopts the OPEN3000 system.The environmental parameter detection system comprises: ambient temperature and humidity transducer and the water sensor of installing is being arranged under the machine room floor of precision air conditioner.Simultaneously, each branch road installs and measures instrument in power distribution cabinet, measures power distribution information, comprises voltage, electric current, power etc.But if the construction opening formula instrument transformer that the branch road distribution can not cut off the power supply.
Further, said terminal server also is connected with the electric energy information acquisition system; Said OPEN3000 system and electric energy information acquisition system open communication interface are given central monitoring system.
Further, said terminal server also is connected with UPS.
The technique scheme of the utility model is compared prior art and had the following advantages: (1) the utility model is used for realizing centralized maintenance and management are carried out in cities and counties' power scheduling.Concentrated, various electrical secondary system specialty analysis can realize that electrical secondary system inserts and the specialty analysis plug-in unitization flexibly.Information such as the operation of electrical secondary system and physical environment are taken all factors into consideration and analyzed, promote efficient and the O&M level of keeping watch on.It is that the scheduling electrical secondary system is concentrated an important subsystem of operational monitoring that the scheduling electrical secondary system is concentrated the operational monitoring collection terminal, and it and professional terminal system are accomplished the scheduling electrical secondary system jointly and concentrated the operational monitoring task.Collection terminal passes through the common remote data storehouse of read-write with the information interaction of professional end to be realized, the information interaction of collection terminal and field apparatus is through supporting the serial server realization of Socket pattern.
Description of drawings
For the content that makes the utility model is more clearly understood, below basis specific embodiment and combine accompanying drawing, the utility model is done further detailed explanation, wherein
Fig. 1 is the knot block diagram of the concentrated operation monitoring system of the electric power secondary system among the embodiment.
Embodiment
See Fig. 1, the concentrated operation monitoring system of the electric power secondary system of present embodiment comprises: concentrate operation monitoring main website, the data dispatching net that links to each other with this concentrated operation monitoring main website, control centre, city and the control centre, county that links to each other with this data dispatching net.
Said concentrated operation monitoring main website comprises: the database server, acquisition server and the application server that link to each other with said data dispatching net.Database server, acquisition server and application server are arranged in the machine room, and connect each system and equipment through the serial port terminal server through the RS485/232 serial ports.
Control centre, said city comprises with the control centre, county: the terminal server that links to each other with said data dispatching net, the power automatic system that links to each other with this terminal server, branch road power distribution information detection system and be used to cooperate the environmental parameter detection system of air-conditioning system work.Power automatic system adopts the OPEN3000 system.The environmental parameter detection system comprises: ambient temperature and humidity transducer and the water sensor of installing is being arranged under the machine room floor of precision air conditioner.Simultaneously, each branch road installs and measures instrument in power distribution cabinet, measures power distribution information, comprises voltage, electric current, power etc.But if the construction opening formula instrument transformer that the branch road distribution can not cut off the power supply.
Said terminal server also is connected with UPS (uninterrupted power supply).
Obviously, the foregoing description only be for explain clearly that the utility model does for example, and be not to be qualification to the execution mode of the utility model.For the those of ordinary skill in affiliated field, on the basis of above-mentioned explanation, can also make other multi-form variation or change.Here need not also can't give exhaustive to all execution modes.And conspicuous variation that these spirit that belong to the utility model are extended out or change still are among the protection range of the utility model.

Claims (3)

1. the concentrated operation monitoring system of an electric power secondary system is characterized in that comprising: concentrate operation monitoring main website, the data dispatching net that links to each other with this concentrated operation monitoring main website, control centre, city and the control centre, county that links to each other with this data dispatching net;
Said concentrated operation monitoring main website comprises: the database server, acquisition server and the application server that link to each other with said data dispatching net;
Control centre, said city comprises with the control centre, county: the terminal server that links to each other with said data dispatching net, the power automatic system that links to each other with this terminal server, branch road power distribution information detection system and be used to cooperate the environmental parameter detection system of air-conditioning system work.
2. the concentrated operation monitoring system of electric power secondary system according to claim 1, it is characterized in that: said terminal server also is connected with the electric energy information acquisition system.
3. the concentrated operation monitoring system of electric power secondary system according to claim 1, it is characterized in that: said terminal server also is connected with UPS.
CN201120417618XU 2011-10-28 2011-10-28 Centralized operation monitoring system of electric power secondary system Expired - Fee Related CN202363971U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201120417618XU CN202363971U (en) 2011-10-28 2011-10-28 Centralized operation monitoring system of electric power secondary system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201120417618XU CN202363971U (en) 2011-10-28 2011-10-28 Centralized operation monitoring system of electric power secondary system

Publications (1)

Publication Number Publication Date
CN202363971U true CN202363971U (en) 2012-08-01

Family

ID=46575127

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201120417618XU Expired - Fee Related CN202363971U (en) 2011-10-28 2011-10-28 Centralized operation monitoring system of electric power secondary system

Country Status (1)

Country Link
CN (1) CN202363971U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116499650A (en) * 2023-06-28 2023-07-28 西安四腾环境科技有限公司 Water leakage processing unit for alarm system of hospital purification air conditioner room

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116499650A (en) * 2023-06-28 2023-07-28 西安四腾环境科技有限公司 Water leakage processing unit for alarm system of hospital purification air conditioner room
CN116499650B (en) * 2023-06-28 2023-10-24 西安四腾环境科技有限公司 Water leakage processing unit for alarm system of hospital purification air conditioner room

Similar Documents

Publication Publication Date Title
CN102427277B (en) Area intelligent power distribution network system
CN106532935B (en) For carrying out the method and its system of secondary system of intelligent substation fault diagnosis
CN103576650A (en) Operation security monitoring and managing system for airport ground equipment
CN204177912U (en) Based on Distribution Network Failure early warning and the positioning system of GIS application
CN204143233U (en) IT-room environment monitoring system
CN104502753A (en) Networked on-line real-time analysis system for electric power fault recording device and application of system
CN202231491U (en) Power distribution monitoring system
CN110658415A (en) Low-voltage distribution line fault detection method and system
CN103560590B (en) Electric network intelligent scheduling framework and its implementation
CN101826756A (en) System and method for realizing fault positioning of power distributing substation equipment
CN105376534A (en) Integrated electric power information communication monitoring platform based on wireless transmission technology
CN202565022U (en) Fault monitoring system capable of monitoring fault of electric power dispatching automation device
CN102495597A (en) Cabinet environment acquisition and monitoring equipment
CN105676157A (en) WAMS low-frequency oscillation identification function test system and WAMS low-frequency oscillation identification function test method
CN106530653B (en) Power information acquisition method
CN205389136U (en) Cable branch case standard management system
CN204567694U (en) A kind of track switch controls multimachine multiple spot switch machine and divides expression electronic monitoring warning device
CN204906004U (en) Distributed intelligent regional power grid of network layering
CN105137954A (en) Real-time on-line temperature and humidity monitoring system of transformer substation
CN204089348U (en) A kind of switchgear house remote online intelligent and safe operational system
CN202363971U (en) Centralized operation monitoring system of electric power secondary system
CN202854593U (en) Electric power comprehensive monitoring system
CN202475035U (en) Data acquisition system for power equipment
CN206115680U (en) Use electric information collection device
CN206004410U (en) Metering type power distribution network FTU device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: JIANGSU FANGTIAN POWER TECHNOLOGY CO., LTD. JIANGS

Free format text: FORMER OWNER: JIANGSU FANGTIAN POWER TECHNOLOGY CO., LTD.

Effective date: 20120926

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20120926

Address after: 213000 Tianning District, Jiangsu, Changzhou, No. 27

Patentee after: Changzhou Power Supply Co, Jiangsu Provincial Power Corp.

Patentee after: Jiangsu Fangtian Power Technology Co., Ltd.

Patentee after: Jiangsu Electric Power Company

Patentee after: State Grid Corporation of China

Address before: 213000 Tianning District, Jiangsu, Changzhou, No. 27

Patentee before: Changzhou Power Supply Co, Jiangsu Provincial Power Corp.

Patentee before: Jiangsu Fangtian Power Technology Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120801

Termination date: 20161028