CN202265351U - Power-driven chain block cascading lifting device - Google Patents

Power-driven chain block cascading lifting device Download PDF

Info

Publication number
CN202265351U
CN202265351U CN2011201721860U CN201120172186U CN202265351U CN 202265351 U CN202265351 U CN 202265351U CN 2011201721860 U CN2011201721860 U CN 2011201721860U CN 201120172186 U CN201120172186 U CN 201120172186U CN 202265351 U CN202265351 U CN 202265351U
Authority
CN
China
Prior art keywords
chain
power
electronic
pole
driven
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011201721860U
Other languages
Chinese (zh)
Inventor
孝国忠
鲍玉萍
孙东明
李学军
张春宇
李家双
李国强
戚少明
白雪峰
贾睿新
刘来
白洁
姚彦
何志新
杨志光
杨建平
何家伟
胡江
胡耀涛
申爱华
冷金明
孙凯
武晓宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Heilongjiang installation engineering Co
Original Assignee
Heilongjiang installation engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Heilongjiang installation engineering Co filed Critical Heilongjiang installation engineering Co
Priority to CN2011201721860U priority Critical patent/CN202265351U/en
Application granted granted Critical
Publication of CN202265351U publication Critical patent/CN202265351U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model provides a power-driven chain block cascading lifting device. Large-scale hoisting machinery is required in the construction of multilayer and high-rise building roofs, but the scheduling is extremely difficult in the site crossed construction because of a narrow construction site. The power-driven chain block cascading lifting device comprises a left hold pole (1) and a right hold pole (2), wherein the left hold pole is connected with a left power-driven guide chain (3), the left power-driven guide chain is connected with a group of guide chains (4), the right hold pole is connected with a right power-driven guide chain (5), the right power-driven guide chain is connected with a group of guide chains, the left power-driven guide chain is connected with the right power-driven guide chain through a controller (6), and the lower end of each guide chain is connected with a hanging hook. The device provided by the utility model can be used for lifting heavy object.

Description

Electronic jack serial connection bont
Technical field:
the utility model relates to a kind of later-model jack stringer, is specifically related to a kind of electronic jack serial connection bont.
Background technology:
When multilayer and skyscraper roofing construction, need large scale hoisting machinery, and this moment on-the-spot crossed construction, the place of production is narrow, the scheduling difficulty very big.
To the engineering actual conditions, this builds maximum 3 tons of the liter weights that rise of tower crane that former civil engineering unit adopts .And employing self-propelled hydraulic truck crane; Calculating palpus use rated load weight according to radius of turn (car position, the suitable station of main building distance is above 46 meters) and lifting altitude (adding that the front adds layer and step above 49 meters) outward is 250 tons large-scale crane, and crane arm at least must 76 meters.The price of a machine-team is 25000 yuan, even eight foldings are also wanted 20000 yuan, each ton steel structure will increase by 4000 to 5000 yuan of costs.The low temperature effect mechanical efficiency also has considerable influence for safety of operation still more.Construction unit has vetoed the scheme of civil engineering unit.
Summary of the invention:
The purpose of the utility model provides a kind of can significantly reducing the cost, and is the electronic jack serial connection bont that can substitute large-scale construction equipment under certain execution conditions.
Above-mentioned purpose realizes through following technical scheme:
a kind of electronic jack serial connection bont; Its composition comprises: left pole, right pole, described left pole connect the electronic chain of leading in a left side, and a described left side is electronic leads chain and connect one group and lead chain; Described right pole connects the right electronic chain of leading; The described right side is electronic leads chain and connects one group and lead chain, and the electronic chain of leading in a described left side connects the right electronic chain of leading through controller, and the described chain lower end of leading connects hanging hook.
described electronic jack serial connection bont, described left pole and described right pole all have one group of solid drawn pipe to be formed by connecting.
Beneficial effect:
1. the utility model can promote the use of other field.Material facility vertical transport when keeping in repair like high level.
the utility model safety, reliable, economical and effective.Can also reduce labour intensity.Because power is conventional power supply, the influence of low temperature is smaller.So field of application is general, there is not any restriction in the use.
the utility model has been simplified construction organization, in the past with crane need the commanding at least must four-player (by roof, ground, the crane, installation site).This product can reduce commanding two people, is convenient to commander, and without crane, operation field focuses on an indoor place, significantly reduces safety hazard.
the utility model is compared saving mechanical stage student contributions pooled to pay for class activities per ton more than 4000 yuan with using wheel crane; Can save 40,000 yuan for 10 tons, 100 tons can reach 400,000 members; And the also corresponding reduction of labour cost.
the utility model is applied in to amount in the engineering wherein accomplishes 158 tons of liftings; Deduct more than 50 ten thousand yuan of the expense cost-cuttings of electronic jack; Both solve the technical barrier in civil engineering and the owner construction, reduced investment to the owner again.
Description of drawings:
accompanying drawing 1 is the structural representation of this product.
The specific embodiment:
Embodiment 1:
a kind of electronic jack serial connection bont; Its composition comprises: left pole 1, right pole 2, and described left pole 1 connects the electronic chain 3 of leading in a left side, and a described left side is electronic leads chain 3 and connects one group and lead chain 4; Described right pole 2 connects the right electronic chain 5 of leading; The described right side is electronic leads chain 5 and connects one group and lead chain, and the electronic chain 3 of leading in a described left side connects the right electronic chain 5 of leading through controller 6, and described chain 4 lower ends of leading connect hanging hook 7.
Embodiment 2:
embodiment 1 described electronic jack serial connection bont, described left pole and described right pole all have one group of solid drawn pipe 8 to be formed by connecting.
Embodiment 3:
embodiment 1 or 2 described electronic jack serial connection bonts; According to weather, place, a liter weight, lifting altitude, on the basis of past construction experiences, propose to utilize the electronic basic specification function that connects; With its expansion; Two jack series connection increase lifting altitude, when hoisting depth is too high, can also further improve.Such as increasing the 3rd jack, or take the Alley Oop mode, should possess this moment aerial or the air security service platform is set.Utilize the key property of jack, several electronic jacks are cascaded accomplish the vertical-lift of particular space structures.
Installation method:
1, one tool only son and heir pole respectively is set at two ends, roof truss installation site, sunlight hall.Pole is φ 159 * 6 solid drawn pipes, long 5m.Can satisfy 8 tons of hoisting capacities.The pole fixed form adopts anchor ear, and each fuses with pedestal (high 1 m, 600 * 600 reinforced columns) together up and down.
, on pole, hang electronic jack.The jack string that every end is 20m by two lifting altitudes hangs over together, and the operator is at pedestal next door control rising or falling speed.
, the chain of bottom jack is put into maximum security improvement length, controller and jack are fixed together, and power supply are broken off.Chain with the top jack is put into maximum security improvement length again.Accomplish the operation of the other end simultaneously.
, that prefabricated roof truss is transported into the hall is indoor, places the suspension hook below, after checking of dimensions, direction are errorless.As prescribed is connected with suspension hook.
, examination are hung.Confirm to confirm to change over to formal lifting by on scene commander behind the safe and feasible.
, the two ends operator plays roof truss at the uniform velocity evenly and rises to setting height(from bottom) under unified command.Start the electronic jack in top at first simultaneously, waited to be raised to the security row journey, during promptly total hoisting depth 1/2, PTO Power Take Off.Then with bottom jack power connection.Start the bottom jack and continue to hoist, until reaching setting height(from bottom).
, unload hook, dismounting jack, pole

Claims (1)

1. a kind of electronic jack is connected in series bont; Its composition comprises: left pole, right pole is characterized in that: described left pole connects the electronic chain of leading in a left side, and a described left side is electronic leads chain and connect one group and lead chain; Described right pole connects the right electronic chain of leading; The described right side is electronic leads chain and connects one group and lead chain, and the electronic chain of leading in a described left side connects the right electronic chain of leading through controller, and the described chain lower end of leading connects hanging hook.
electronic jack serial connection bont 2. according to claim 1 is characterized in that:, described left pole and described right pole all have one group of solid drawn pipe to be formed by connecting.
CN2011201721860U 2011-05-26 2011-05-26 Power-driven chain block cascading lifting device Expired - Lifetime CN202265351U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011201721860U CN202265351U (en) 2011-05-26 2011-05-26 Power-driven chain block cascading lifting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011201721860U CN202265351U (en) 2011-05-26 2011-05-26 Power-driven chain block cascading lifting device

Publications (1)

Publication Number Publication Date
CN202265351U true CN202265351U (en) 2012-06-06

Family

ID=46156159

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011201721860U Expired - Lifetime CN202265351U (en) 2011-05-26 2011-05-26 Power-driven chain block cascading lifting device

Country Status (1)

Country Link
CN (1) CN202265351U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112141874A (en) * 2020-09-25 2020-12-29 中国二十二冶集团有限公司 Installation method of dust hood in limited space

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112141874A (en) * 2020-09-25 2020-12-29 中国二十二冶集团有限公司 Installation method of dust hood in limited space
CN112141874B (en) * 2020-09-25 2022-04-08 中国二十二冶集团有限公司 Installation method of dust hood in limited space

Similar Documents

Publication Publication Date Title
CN105692470B (en) Inner climbing crane tower and its operating method
CN103711301A (en) Construction method and device for two-track movable electric basket and lifting hoist
CN204782016U (en) Hoist and mount of curtain wall glass plate and conveyor
CN103437563B (en) A kind of mounting method for large steel-strctrue building steel frame
CN106015729B (en) A kind of reverse method in place of evaporated flue under sealing power house
CN204899238U (en) Unitized curtain wall plate hoist device
CN103899093A (en) Step-by-step hoisting construction method of mega-frame steel truss beam
CN202530769U (en) Large span steel structure high-altitude subsection hoisting support system
CN205077878U (en) Unit type curtain plate hoisting device
CN104153586B (en) A kind of suspension cable hangs the construction method of mounting purlines
CN206562264U (en) A kind of hanging device for transport outside high-rise building
CN106567542A (en) Super high-rise double tower building steel structure corridor assembling method
CN108049666A (en) A kind of echelon installation method of super plane multilayer steel truss electronic workshop steel construction
CN204691326U (en) Multifunctional mobile component processing plant
CN202265351U (en) Power-driven chain block cascading lifting device
CN101818563B (en) Jack-up integral lifting mobile platform and using method
CN111364622A (en) Construction method of long-span arched net rack strip-shaped building
CN203461720U (en) Simple cantilever hoisting machine
CN207312994U (en) Power station major diameter surge shaft steel lining cantilevered annular track boom hoisting
CN207047703U (en) A kind of beam piece prestressed stretch-draw jack easy device in place
CN206720680U (en) A kind of roofing color corrugated sheet steel lifting device
CN112456348B (en) Heat absorber hoisting method
CN205575534U (en) Lattice formula groined type support body lifting means
CN208056658U (en) Aerial for industrialized building makes building machine
CN204754150U (en) Dish -type node formula scaffold

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20120606

CX01 Expiry of patent term