CN202247658U - Steel pipe arch bridge - Google Patents

Steel pipe arch bridge Download PDF

Info

Publication number
CN202247658U
CN202247658U CN2011202850816U CN201120285081U CN202247658U CN 202247658 U CN202247658 U CN 202247658U CN 2011202850816 U CN2011202850816 U CN 2011202850816U CN 201120285081 U CN201120285081 U CN 201120285081U CN 202247658 U CN202247658 U CN 202247658U
Authority
CN
China
Prior art keywords
arch
interlude
steel
girder
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011202850816U
Other languages
Chinese (zh)
Inventor
李世清
范学功
李宏涛
徐建宁
刘帮新
曾凡福
解叶龙
念家香
张战通
张军剑
胡艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xiamen Construction Engineering Co Ltd of of China Railway First Engineering Group Co Ltd
Original Assignee
Xiamen Construction Engineering Co Ltd of of China Railway First Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xiamen Construction Engineering Co Ltd of of China Railway First Engineering Group Co Ltd filed Critical Xiamen Construction Engineering Co Ltd of of China Railway First Engineering Group Co Ltd
Priority to CN2011202850816U priority Critical patent/CN202247658U/en
Application granted granted Critical
Publication of CN202247658U publication Critical patent/CN202247658U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model discloses a steel pipe arch bridge, which comprises two piers, two cast-in-situ beams which are respectively arranged on the two piers, and a main beam. The main beam comprises a steel beam middle section and two closure sections, wherein the steel beam middle section is erected above the two piers in a straddling way and consists of a plurality of sections of steel beams which are assembled and fixedly connected together, and the two closure sections are respectively arranged on the two cast-in-situ beams. Moreover, the two enclosure sections are respectively closed and fixedly connected with the two ends of the steel beam middle section. Since the two closure sections are respectively closed and fixedly connected with the two ends of the steel beam middle section and the steel beam middle section consists of the plurality of sections of steel beams which are assembled and fixedly connected together, the steel pipe arch bridge has the advantages of less channel occupation time, high construction efficiency, low construction cost and high construction accuracy.

Description

A kind of steel pipe arch bridge
Technical field
The utility model relates to a kind of steel pipe arch bridge.
Background technology
Existing steel pipe arch bridge comprises that two bridge piers, two arrange the girder that is welded together by many girder steels order successively at the cast-in-place beam of two bridge piers and respectively, and said girder two ends are fixed in two cast-in-place beams respectively.Because girder is to be welded together in regular turn by many girder steels, therefore need take the navigation channel for a long time, construction cost is high, and efficiency of construction is low, and construction precision is low.
The utility model content
The utility model provides a kind of steel pipe arch bridge, and it has overcome the existing existing deficiency of steel pipe arch bridge in the background technology.
The technical scheme that is adopted that the utility model solves its technical problem is:
A kind of steel pipe arch bridge; It comprises that two bridge piers (10), two arrange a cast-in-place beam (20) and the girder at two bridge piers (10) respectively; Said girder comprises that the frame that collapses arranges the closure segment (40) at two cast-in-place beams (20) respectively on two bridge piers (10) and by the affixed girder steel interlude (30) and two of multistage girder steel assembly unit; And said two closure segments (40) close up respectively and are fixed in girder steel interlude (30) two ends.
Among one preferred embodiment: it comprises arch rib; Said arch rib comprises that two are embedded in the pre-buried place of arch springing (50) that two cast-in-place beams (20) locate, two arch tube edge joint sections (60) and respectively by the affixed arch tube interlude (70) of multistage arch tube assembly unit; A said arch tube edge joint section (60) is fixed between pre-buried place of an arch springing (50) and arch tube interlude (70) one ends, and said another arch tube edge joint section (60) is fixed between the pre-buried place of another arch springing (50) and arch tube interlude (70) other end.
Among one preferred embodiment: be fixed by welding in together between said closure segment (40) and the girder steel interlude (30).
Among one preferred embodiment: said arch tube interlude (70), arch tube edge joint section (60) and the pre-buried place of arch springing (50) are fixed by welding in together.
Among one preferred embodiment: all be provided with cement board on closure segment of said girder (40) and the girder steel interlude (30).
The present technique scheme is compared with background technology, and it has following advantage: two closure segments close up respectively and are fixed in girder steel interlude two ends, and the girder steel interlude is fixed together by the assembly unit of multistage girder steel; It is few then to take the navigation channel time; Efficiency of construction is high, and construction cost is low, and construction precision is high.Arch rib comprises the pre-buried place of two arch springings, two arch tube edge joint sections and an arch tube interlude, and support strength is high, and it is few to take the navigation channel time.
Description of drawings
Below in conjunction with accompanying drawing and embodiment the utility model is described further.
Fig. 1 has illustrated the steel pipe arch bridge sketch map.
Label declaration: bridge pier-10, cast-in-place beam-20, girder steel interlude-30, closure segment-40, arch springing pre-buried place-50, arch tube edge joint section-60, arch tube interlude-70.
The specific embodiment
A kind of steel pipe arch bridge is please referred to Fig. 1, and it comprises that two bridge piers 10, two arrange cast-in-place beam 20, a girder and two arch ribs at two bridge piers 10 respectively.
Said girder comprises a girder steel interlude 30 and two closure segments 40.Said girder steel interlude 30 collapses frame on two bridge piers 10 and affixed by the assembly unit of multistage girder steel.Said two closure segments 40 are arranged respectively at two cast-in-place beams 20.Said two closure segments 40 close up respectively and are fixed in girder steel interlude 30 2 ends.Be fixed by welding in together between said closure segment 40 and the girder steel interlude 30.All be provided with cement board on the closure segment 40 of said girder and the girder steel interlude 30.
Said arch rib comprises the pre-buried place of two arch springings 50, two arch tube edge joint sections 60 and an arch tube interlude 70.The pre-buried place 50 of said two arch springings is embedded in two cast-in-place Liang20Chu respectively.Said arch tube interlude 70 is fixed together by the assembly unit of multistage arch tube.A said arch tube edge joint section 60 is fixed between pre-buried place 50 of an arch springing and arch tube interlude 70 1 ends, and said another arch tube edge joint section 60 is fixed between the pre-buried place 50 of another arch springing and arch tube interlude 70 other ends.Said arch tube interlude 70, arch tube edge joint section 60 and the pre-buried place 50 of arch springing are fixed by welding in together.
The above; Be merely the utility model preferred embodiment; So can not limit the scope that the utility model is implemented according to this, the equivalence of promptly doing according to the utility model claim and description changes and modifies, and all should still belong in the scope that the utility model contains.

Claims (5)

1. steel pipe arch bridge; It comprises that two bridge piers (10), two arrange a cast-in-place beam (20) and the girder at two bridge piers (10) respectively; It is characterized in that: said girder comprises that the frame that collapses arranges the closure segment (40) at two cast-in-place beams (20) respectively on two bridge piers (10) and by the affixed girder steel interlude (30) and two of multistage girder steel assembly unit; And said two closure segments (40) close up respectively and are fixed in girder steel interlude (30) two ends.
2. a kind of steel pipe arch bridge according to claim 1; It is characterized in that: it comprises arch rib; Said arch rib comprises that two are embedded in the pre-buried place of arch springing (50) that two cast-in-place beams (20) locate, two arch tube edge joint sections (60) and respectively by the affixed arch tube interlude (70) of multistage arch tube assembly unit; A said arch tube edge joint section (60) is fixed between pre-buried place of an arch springing (50) and arch tube interlude (70) one ends, and said another arch tube edge joint section (60) is fixed between the pre-buried place of another arch springing (50) and arch tube interlude (70) other end.
3. a kind of steel pipe arch bridge according to claim 2 is characterized in that: be fixed by welding in together between said closure segment (40) and the girder steel interlude (30).
4. a kind of steel pipe arch bridge according to claim 2 is characterized in that: said arch tube interlude (70), arch tube edge joint section (60) and the pre-buried place of arch springing (50) are fixed by welding in together.
5. a kind of steel pipe arch bridge according to claim 1 and 2 is characterized in that: all be provided with cement board on closure segment of said girder (40) and the girder steel interlude (30).
CN2011202850816U 2011-08-05 2011-08-05 Steel pipe arch bridge Expired - Lifetime CN202247658U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011202850816U CN202247658U (en) 2011-08-05 2011-08-05 Steel pipe arch bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011202850816U CN202247658U (en) 2011-08-05 2011-08-05 Steel pipe arch bridge

Publications (1)

Publication Number Publication Date
CN202247658U true CN202247658U (en) 2012-05-30

Family

ID=46108920

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011202850816U Expired - Lifetime CN202247658U (en) 2011-08-05 2011-08-05 Steel pipe arch bridge

Country Status (1)

Country Link
CN (1) CN202247658U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103898831A (en) * 2014-04-04 2014-07-02 长沙理工大学 Ultrahigh-performance-concrete prefabricated assembled-type arch rib and manufacturing and mounting method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103898831A (en) * 2014-04-04 2014-07-02 长沙理工大学 Ultrahigh-performance-concrete prefabricated assembled-type arch rib and manufacturing and mounting method thereof
CN103898831B (en) * 2014-04-04 2016-05-18 长沙理工大学 A kind of precast splice type arch rib of ultra-high performance concrete and fabrication and installation method thereof

Similar Documents

Publication Publication Date Title
CN109826090B (en) Assembled type segmented bent cap and connecting method thereof
CN103510625A (en) Top-bottom T-shaped steel type node for connecting H-shaped steel beam with rectangular tubular column through unilateral bolts
CN103696374A (en) Straddle method of cantilever of long-span simply supported steel truss beam of horizontal curve section
RU2011114478A (en) NAVIGATION SYSTEM AND METHOD OF STURMAN MOTION ASSISTANCE
CN202247658U (en) Steel pipe arch bridge
CN204459477U (en) A kind of pre-buried pipeline fixing bracket
CN203034821U (en) Large-span arched inverted-triangular pipe truss assembly integral mould
CN202055414U (en) Fast positioning device for bellows in pre-stress box girder
CN201648975U (en) General assembly structure for bridge sections of large steel box girder
CN204266115U (en) Round end type entity pier shaft clad steel muscle colligation auxiliary positioning mould
CN202377695U (en) Multi-section continuous matched welding and splicing jig
CN201981706U (en) Prestressed bellows positioning device
CN202055187U (en) Externally prestressed reinforcing cable steering block for bridge
CN203712863U (en) Mobile prefabricated T-beam pedestal
KR20130051527A (en) Multi-way cable stayed bridge
CN203281690U (en) 90-degree bending jig
CN204039897U (en) There is the prestressed concrete short T beam bridge girder construction of large oblique angles
CN204417985U (en) The bridging of a kind of steel bow continues Oil pipeline
CN203855952U (en) Prefabricated locating component
CN204740159U (en) Concrete member is used in experiment of falling concave shape
CN102758397A (en) S-shaped steel structure bridge
CN203160115U (en) Overlong cantilever type pier capping beam of urban viaduct
CN202152492U (en) Fixing mechanism used for steel structure
CN103924582B (en) Prefabricated keeper
CN203668812U (en) Assembled arch rib

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20120530